EDR HLRF Work Packages Draft Summary
GDE Meeting, Beijing, February R. Larsen, SLAC for HLRF Collaboration Rev. March 2, 2007
2
ILC HA Electronics R&D R. Larsen SLAC
EDR Assumptions EDR to be completed in two more years, i.e. end of FY09. Will include detailed technical and cost plans that are considerably more mature than RDR. Will include a schedule and funding profile consistent with the plans. Will be sufficiently mature to provide a basis for international funding requests, implying technology down-selects close if not already in hand industrialization, industrial cost estimates close if not already in hand. February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
3
ILC HA Electronics R&D R. Larsen SLAC
Work Package Goals Work packages to be defined for two phases: R&D for FY08-09 (plans ongoing) Engineering packages for industrialization of prototypes, early production runs (by EDR FY09) Following lists topics for work packages for HLRF BCD, ACD designs Modulators, Klystrons, HLRF Example: Marx Modulator February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
4
ILC HA Electronics R&D R. Larsen SLAC
BCD Modulator BCD Modulator Modularization Redesign: Racks assemblies, main cap bank, switches, charger, bouncer cap bank & switches Procurement Package development with industry Bid packages for industry prototypes BCD Modulator Industrialization Factory & Test Modeling Factory Cost modeling Industrialization Plan, cost verification, ramp-up Maintenance Model, development of fixtures, personnel cost February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
5
ILC HA Electronics R&D R. Larsen SLAC
Marx Modulator Marx Modulator Unit 1 Complete Vernier, Charger & tests Pulse flattening alternatives, algorithms, testing Packaging, implementation in ESB Marx Modulator DFM Packaging redesign Board improvements Diagnostic controls redesign, implementation waveform sampling probes, testing Fabrication, test Unit 2 Installation & testing Unit 2 Fabrication, test Units 3-4 Installation & testing Units 3-4 February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
6
ILC HA Electronics R&D R. Larsen SLAC
Marx Modulator-2 Marx Modulator Industrialization Factory, cost models Factory work package development Factory fabrication Units 3-4 February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
7
ILC HA Electronics R&D R. Larsen SLAC
Klystrons BCD - MBK Klystron Commercial prototypes procurement, test plan Performance verification plans Cost analysis test systems Industry cost verification plans ACD - SBK Klystron Development plan, costs Unit 1 Test plan, costs Unit 1 DFM Unit 2 development, test plan, cost plan Factory Model, test, cost plan Maintenance model, cost analysis Industrialization plan, ramp-up, cost verification February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
8
ILC HA Electronics R&D R. Larsen SLAC
RF Distribution BCD - RF Distribution Track TTF, XFEL developments, industrialization, technical results ACD - RF Distribution Development plan, costs Prototype 1 Prove at basic level with 1-2 hybrids & cavity couplers w/ loads Develop plan, costs for integrated structure Develop factory model, test plan with industry Develop staging and installation preparation model, costs February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
9
Work Package Flow Example 1: Marx Modulator
LAB ENGRG. TEAM Generate Bid Packages Oversee Vendor Production Oversee Vendor-Based QC, Testing Oversee Vendor-Based Integration, Production Engineering. Oversee Vendor based Full System Test Customer Acceptance February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
10
Work Package Flow Example 2: General Contractor (GC)
LAB ENGRG. TEAM Generate Work Pkgs. General Contractor, Sub-Contractors Partner w/ GC to place sub-contracts, establish all procedures, support factory QC & test at all levels Monitor QC test results all stages incl. Full System tests February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
11
WP Discussion: Collaboration
Basic decisions needed about how to structure work. Some options: Engineering development of WP can be done by one laboratory or inter-lab inter-regional collaboration (preferred) Integrated WP’s can be bid in part or in whole to vendors in 3 regions Getting prototypes from 3 regions (e.g. klystrons) preferred Management needs tight control over process Management models need to be developed. February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
12
ILC HA Electronics R&D R. Larsen SLAC
WP Discussion 2 Process development resources needed for: Overall WP and sub-tasks Qualified engineering to develop WP’s Design engineering QC and testing System integrators Contracts liaison Etc. Models for each phase needed in order to analyze resource types, scheduling, loading for duration. February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
13
ILC HA Electronics R&D R. Larsen SLAC
Task Table February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
14
ILC HA Electronics R&D R. Larsen SLAC
February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
15
ILC HA Electronics R&D R. Larsen SLAC
February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC
16
ILC HA Electronics R&D R. Larsen SLAC
Summary WP stage will involve major expansion of engineering resources in ILC. Planned R&D for currently low on WP resources necessary for EDR. EDR report writing resources need to be added to above. February 2, 2007 ILC HA Electronics R&D R. Larsen SLAC