Development of a FLC Model for Predicting Schedule Impacted by Change Orders in Construction Projects Jieh-Haur Chen Dec
2
Introduction Problem Statement Methodology
Change orders cause schedule problems raising disputes in construction projects. Methodology Find the correlation in historical data. This correlation will be used in establishing a mathematical model, fuzzification, and fuzzy control rules. Use fuzzy approach to predict and measure construction schedules being impacted by change orders.
3
Data Analysis Mechanical and electrical contractors’ roles
4
Data Analysis Project Type
5
Data Analysis Percent of Change Public vs. Private
Distribution of the Percent Change
6
Data Analysis Reasons of Change Orders 37.1% 1.4% 1.1% 1% 21.5% 3.7%
Additions Change Code Change Tech. Deletions Design Changes Design Coord. Design Error Mat. Handling Material Avail. 37.1% 1.4% 1.1% 1% 21.5% 3.7% 7% 2.9% Over inspection Rework Schedule comp. Site Layout Unknown Cond. Value Eng. Weather Others 2.4% 3.1% 0.5% 25 1.9%
7
FLC Model 5 state variables Role, Project type, % Change, Feature,
And Reasons
8
Discussion and Future Work
Predicted Schedule = Yet to process the FLC model successfully. Fuzzification Fuzzy rules