DC56 Budget, Schedule & People
Matthias Grosse Perdekamp, Illinois DC56 Project Sub-tasks Schedule (IV) Budget and Funding Plans DC56 Review at CERN, November 14th, 2012
2
DC56 Review at CERN, November 14th, 2012
DC56 Project Task: Develop and construct two large area drift chambers for the COMPASS large angle tracking spectrometer (LAT) Physics: COMPASS II experimental program in DVCS, Drell-Yan and Primakoff reactions as approved by the CERN Research Board on Technology: Planar, drift chambers of 8 mm sense wire pitch with 8 views closely following the existing COMPASS DC4 design Straws 1&2 DC4 DC123 The two LAT straw stations are aging and will be replaced by DC56. DC56 Review at CERN, November 14th, 2012
3
DC56 Review at CERN, November 14th, 2012
Support from CERN and COMPASS (1) Letter from Dr. Sergio Bertolucci, CERN Director of Research and Computing, of with affirmation of support for COMPASS II physics program (2) Letter from Drs. Fabienne Kunne and Andrea Bressan, COMPASS spokespeople, of in support of DC56 project. DC56 Review at CERN, November 14th, 2012
4
DC56 Review at CERN, November 14th, 2012
DC Collaboration Institutions: Contributions Abilene Christian University, Abilene, TX, USA NSF M. Daugherty, R. Towell, 4 undergraduate students Institute of Physics Academia Sinica, Taipei, Taiwan NSC, institutional W.-C. Chang, M.-L. Chu, C.-Y. Hsieh, C.-H. Lin Albert Ludwigs University, Freiburg, Germany BMBF H. Fischer, F. Herrmann CEA Saclay, Saclay, France in kind D. Durand, A. Magnon, S. Platchkov CERN, Geneva, Switzerland G. Mallot INFN Torino, Torino, Italy in kind M. Chiosso, O. Denisov, A. Maggiora, D. Panzieri, S. Takekawa University of Illinois, Urbana, IL, USA NSF R. Bi, J. Blackburn, L. Bartoszek, I. Choi, M. Grosse Perdekamp, N. Makins, P. Montuenga, J.C. Peng, C. Riedl, E. Thorsland (total of ~8 FTE/year over 2 years) Engineers Technicians DC56 Review at CERN, November 14th, 2012
5
DC56 Review at CERN, November 14th, 2012
DC Subtasks I Electronics (Wen-Chen Chang, IAPS) Project management + budget IPAS (W.-C. Cheng) Purchases for FEE IPAS (W.-C. Cheng) CMAD chip INFN Torino (D. Panzieri) FEE + TDC R&D, prototyping IPAS (W.-C. Cheng) FEE + TDC mass production IPAS (W.-C. Cheng) FEE + TDC testing IPAS (W.-C. Cheng) FEE + TDC installation IPAS (W.-C. Cheng) LV systems IPAS (W.-C. Cheng) Readout/Gandalf boards Freiburg University (H. Fischer) Purchases readout Freiburg University (H. Fischer) DC56 Review at CERN, November 14th, 2012
6
DC56 Review at CERN, November 14th, 2012
DC Subtasks II Mechanical detector hardware and integration (Matthias Grosse Perdekamp, UIUC) Project management + budget UIUC (M. Perdekamp) Purchases & contracts: R&D + construction UIUC (M. Perdekamp) Drift chamber R&D, including prototypes UIUC, ACU (I. Choi) Test beam at FNAL ACU, UIUC (I. Choi) Drift chamber design UIUC, Saclay (A. Magnon) Overall system integration: DC hardware + shielding, grounding, LV/HV and cooling UIUC, Saclay (A. Magnon) Mechanical strength analysis Saclay/UIUC (L. Bartoszek) Anode plane construction UIUC, ACU (C. Riedl) Cathode plane construction Saclay (D. Durand) Gas window construction UIUC (C. Riedl) Construction of mechanical support frames UIUC (C. Riedl) Design and setup of gas system UIUC (I. Choi) DC56 Review at CERN, November 14th, 2012
7
DC56 Review at CERN, November 14th, 2012
DC Subtasks III Mechanical detector hardware and Integration cont’d (Caroline Riedl, UIUC) Final assembly at Saclay Saclay, UIUC (A. Magnon) Installation at CERN UIUC, ACU, Saclay (C. Riedl) Safety CERN (G. Mallot) Commissioning UIUC and Saclay (C. Riedl) HV systems ACU (M. Daugherty) Shipping/Transports UIUC (C. Riedl) DC56 Review at CERN, November 14th, 2012
8
DC56 Review at CERN, November 14th, 2012
DC Subtasks IV Software and simulations (Naomi Makins) Integration in GEANT & simulations INFN Torino (S. Takakawa) Slow control & Monitoring software ACU (M. Daugherty) Alignment + calibration software UIUC (N. Makins) DC56 Integration in COMPASS tracking UIUC (N. Makins) DC56 Review at CERN, November 14th, 2012
9
DC56 Review at CERN, November 14th, 2012
DC56 Schedule: Electronics Activity Timeline FEM 01/08/2012 – 30/06/2013 (11 mons) --Design/Layout/Fab (1st prototype) 01/08/2012 – 30/11/2012 (4 mons) --Test 01/12/2012 – 31/01/2013 (2 mons) --Package of CMAD Chip 01/02/2013 – 28/02/2013 (1 mons) --Design/Layout/Fab (2nd prototype) 01/02/2013 – 31/03/2013 (2 mons) 01/04/2013 – 30/06/2013 (3 mons) DCM 01/08/2012 – 30/06/2013 (10 mons) --Design/Layout /Fab (2nd prototype) Mass production 01/07/2013 – 31/08/2013 (2 mons) Final test 01/09/2013 – 31/10/2013 (2 mons) Delivery of FEE Components to CERN 01/11/2013 – 30/11/2013 (1 mon) On-site Installation of DC FEE 14/07/2014 – 30/09/2014 (2.5 mons) DC56 Review at CERN, November 14th, 2012
10
Timeline – Electronics – IPAS
Jan Feb Mar April May June July Aug Sep Oct Nov Dec 2012 asdfadsfasdfasdfasdfasdfasdfasdf 2013 2014 Milestones: E1 Tests of the CMAD chip with DC prototypes at CERN to verify the CMAD chip as the right choice of the preamplifier device. E2 Tests of complete chains of FEE with DC prototypes in beam test at FNAL. E3 Completion of production of all FEE modules. Design/Layout/Fab (prototype A) Test E1 Design/Layout/Fab (prototype A) Test E2 Pack CMAD E3 Test Design/Layout/Fab (prot B) Test of Prototype B Final Test Delivery to CERN Mass Production Float Design/Layout/Fab (prot B) Test Test of Prototype B On-site Installation of FEE Float FEE Aug 2012 – June 2013 DCM Aug 2012 – June 2013 DC56 Review at CERN, November 14th, 2012
11
DC56 Review at CERN, November 14th, 2012
DC56 Milestones Electronics Electronics Milestones E1 Tests of the CMAD chip with DC prototypes at CERN to verify the CMAD chip as the right choice of the preamplifier device (Feb, 2013) E2 Tests of complete chains of FEE with DC prototypes in beam test at FNAL (Jul, 2013) E3 Completion of production of all FEE modules (Nov, 2013) DC56 Review at CERN, November 14th, 2012
12
DC56 Review at CERN, November 14th, 2012
DC Schedule, Milestones: R&D Activity Timeline Prototype DC56A design & construction 01/04/2012 – 30/09/2012 (6 mons) CMAD test with PA06 16/11/2012 – 15/12/2012 (1 mons) Prototype.DC56A test at CERN 07/01/2013 – 28/02/2013 (2 mons) Prototype .DC56B design & construction 10/10/2012 – 28/02/2013 (4.5 mons) Beam tests at FNAL 01/04/2013 – 28/06/2013 (4 mons) Graphite stability test 01/02/2013 – 28/06/2013 (5 mons) R&D Milestones R1 Completion of prototypes DC56-A and B (Mar 2013) R2 Graphite stability test (July 2013) R3 Beam test at FNAL (July 2013) DC56 Review at CERN, November 14th, 2012
13
DC56 Review at CERN, November 14th, 2012
Timeline – DC56 R&D Jan Feb Mar April May June July Aug Sep Oct Nov Dec 2012 asdfadsfasdfasdfasdfasdfasdfasdf 2013 Milestones: R1 Completion of prototypes DC56-A and B R2 Graphite stability test R3 Beam test at FNAL Design and Construction of Prototype A Cosmic ray test at UIUC Prot.B design & assembly DC56 design 1st FEM prototype R1 CMAD test with PA06 R2 Test at CERN DC56 - A Prot B D&A Graphite stability test DC56 construction DC56 R3 DC56 - B 2nd FEM prototype 1st and 2nd DCM FEE test FEE mass production FEE Beam Test at FNAL DC56 Review at CERN, November 14th, 2012
14
DC56 Review at CERN, November 14th, 2012
DC Schedule: Design + Construction Activity Timeline Design 03/12/2012– 28/06/ (7 mons) --Mechanical strength analysis 03/12/2012 – 31/01/2013 (2 mons) --Mechanical design 14/01/2013 – 28/06/2013 (5.5 mons) --HV boards 04/03/2013 – 29/03/2013 (1 mons) --External support for FEE cards 01/04/2013 – 28/06/ (3 mons) --Integration (grounding scheme, LV, HV, cooling) Design and R&D Review Week of July 8, 2013 Construction 01/07/2013 – 27/06/ (12 mons) --Procurement & contracting from UIUC 01/07/2013 – 01/11/ (4 mons) --Anode Production at FNAL 04/11/2013 – 28/03/ (5 mons) --Cathode Production at Saclay --Mechanical frames & gas windows at UIUC 04/11/2013 – 28/02/ (4 mons) -- Assembly & tests at Saclay 06/04/ /06/ (3 mons) Installation & Commissioning 15/07/2014 – 31/10/ (4.5 mons) Installation at CERN 15/07/2014 – 31/08/ (1.5 mon) Commissioning 01/09/2014 – 28/11/ (3 mons) DC56 Review at CERN, November 14th, 2012
15
DC56 Review at CERN, November 14th, 2012
Timeline - Design Jan Feb Mar April May June July Aug Sep Oct Nov Dec 2012 asdfadsfasdfasdfasdfasdfasdfasdf 2013 2014 Milestones: D1 Complete Strength Analysis D2 Complete Design Strength Analysis D2 Mechanical Design HV Boards External Support Strength Analysis Integration D1 DC56 Review at CERN, November 14th, 2012
16
Timeline – Construction and Commissioning
Jan Feb Mar April May June July Aug Sep Oct Nov Dec 2012 asdfadsfasdfasdfasdfasdfasdfasdf 2013 2014 Milestones: C1 Complete construction C2 Complete assembly & testing at Saclay C3 Complete installation at CERN C4 Complete commissioning Procurement & contracting from UIUC Anode Production at FNAL Cathode Production at Saclay Mechanical frames & gas windows at UIUC C1 C2 C3 Anode Production at FNAL Cathode Production at Saclay Assembly & tests at Saclay Installation at CERN Commissioning Mechanical frames & gas windows at UIUC C4 DC56 Review at CERN, November 14th, 2012
17
DC56 Review at CERN, November 14th, 2012
Milestones: Design and Construction Design Milestones D1 Complete Strength Analysis (Feb, 2013) D2 Complete Design (Jul, 2013) Construction Milestones C1 Complete construction (Apr, 2014) C2 Complete assembly & testing at Saclay (Jul, 2014) C3 Complete installation at CERN (Sep, 2014) C4 Complete commissioning (Dec, 2014) DC56 Review at CERN, November 14th, 2012
18
DC56 Review at CERN, November 14th, 2012
DC56 Funding Sources 1) IPAS development and mass production of FEE & engineering NSC + IPAS institutional funds 2) Freiburg funds the GANDALF boards for readout BMBF 3) INFN Torino contribute the CMAD wafers INFN Torino 4) CEA Saclay contributes the DC4 tooling & engineering CEA Saclay 5) UIUC funds the R&D, design and construction of detector hardware a. $100k for R&D + support for two technicians NSF-PHY b. NSF MRI with total of $987k including confirmed matching: $100k from UIUC and funding for electronics from IPAS. Status: submitted to UIUC pre-campus competition for MRI program on November-7th. DC56 Review at CERN, November 14th, 2012
19
DC56 Review at CERN, November 14th, 2012
DC Budget MRI at ACU hardware for detector assembly 48,000 support for ACU students 32,000 support for assembly technician, 6 months 40,000 high voltage 20,000 10% contingency 14,000 Total ACU 154,000 MRI at Illinois stiffening frames 229,000 composite frames 220,000 printed circuit anode and field wire boards 68,000 anode wire (20 mu) 9,000 field wire (100 mu) 17,000 cathode foil 5,000 graphite coating 21,000 gas windows 6,000 pins & screws o-rings 2,500 connectors 20,000 various mechanical pieces 14,700 Total without contingnecy 621,200 10% contingency 62,120 Total Illinois 683,320 Costs are based on DC4 cost reported by D. Durand + inflation 10% contingency, as based on actual cost DC56 Review at CERN, November 14th, 2012
20
DC56 Review at CERN, November 14th, 2012
DC Budget Electronics, IPAS , Freiburg and Torino Engineers, technicians for R&D 50,000 CMAD chips 60,000 Packing of CMAD chips 8,000 Mass production 150,000 GANDALF boards 23,000 Total electronics 291,000 Other Costs Shipping container UIUC – Saclay 4,000 Transport UIUC – Saclay (two deliveries) 12,000 Shipping container Saclay – CERN Transport Saclay – Cern 3,000 Prototype R&D 77,000 Support for ACU faculty 48,000 Total other costs 148,000 Total project cost: $1,276,320 Funding sources: MRI, IPAS, INFN Torino, Freiburg, UIUC-NSF-umbrella DC56 Review at CERN, November 14th, 2012
21
DC56 Review at CERN, November 14th, 2012
Summary o The project aims to develop and construct two large area drift chambers for the COMPASS large angle tracking spectrometer (LAT) o A group of institutions with the necessary expertise for the DC56 project has been formed: IPAS, ACU, CERN, Freiburg, Saclay, Torino, UIUC o Using the DC4 drift chamber technology developed at Saclay eliminates technical risks and will make it possible to progress fast. o Utilize capabilities of wire chamber labs at FNAL, Saclay and UIUC. o Rely on existing electronics know-how in COMPASS (Freiburg & Torino) and on engineering expertise at IPAS. DC56 Review at CERN, November 14th, 2012
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.