Contract Performance Charts
Applying charts to the A-12 program
2
Scheduled Completion Date
CONTRACT PERFORMANCE Scheduled Completion Date 120 100 80 60 40 20 D o l a r s i n M BCWS BCWP ACWP 74.5 70.5 95.5 Target Contractor’s Est Program Manager’s Est 75.9 99.2 105.4
3
COST/SCHEDULE VARIANCE TRENDS
30 20 10 -10 -20 -30 Scheduled Completion Date D o l a r s i n M Variance at Completion Contractor Program Manager Schedule Variance Cost Variance Management Reserve 10 Pct Threshold Band
4
Detailed A-12 Example
5
CONTRACT PERFORMANCE GD/MCAIR A-12 FSED A-12 Adv Tac Acft AS OF 12/31/89 6000 5000 4000 3000 2000 1000 D o l a r s i n M S t a r C o m p l e t E f o r t C m p l e S i g n f c a t F l i g h t F i r s t BCWS BCWP ACWP 1745.0 1279.2 1597.1 Target Program Manager’s Est Contractor’s Est 4042.3 4808.7 4302.7
6
COST/SCHEDULE VARIANCE TRENDS
GD/MCAIR A-12 FSED N C-0050 A-12 Adv Tac Acft AS OF 12/31/89 400 200 -200 -400 -600 -800 C o m p l e t D o l a r s i n M S t a r F l i g h t E f o r t C m p l e F i r s t S i g n f c a t Cost Variance Sched Variance Mgmt Reserves 10% Thresholds -317.9 -465.8 318.8 Start/Complete Date Program Manager’s Est Contractor’s Est -766.4 -260.4
7
FSD CONTRACT ESTIMATE AT COMPLETION
EAC $5.6B $6.6B $6.7B $6.8B $7.5B PERFORMANCE TO DATE (CPI) CURRENT PERIOD PERFORMANCE (90 DAY CPI) COST & SCHEDULE PERFORMANCE (CPI X SPI) PROJECTED PERFORMANCE AT COMPLETION PROJECT OFFICE CONCLUSION: RANGE: $6.0B TO $7.5B POINT: $6.8B
8
100 90 80 70 60 50 40 30 20 10 F-15 F-18 F-16 P e r c n t C o s (TY $) A-12 First Flight Jan 93 A-12 Percent Time
9
CONCLUSION THE MAGNITUDE AND DIVERGENCE OF THESE COST PROJECTIONS INDICATE THE NEED FOR AN ASSESSMENT OF ACTUAL REMAINING FSD EFFORT AND A DETAILED ESTIMATE BASED ON AN ENGINEERING BUILD-UP.