Download presentation
Presentation is loading. Please wait.
1
ADVANCES IN GRINDING technology
DM Mihir
2
CONTENTS Introduction Bond’s Work Index Different Grinding Equipment's
Crushing Grinding Bond’s Work Index Different Grinding Equipment's Grinding Circuits Ball Mill Rod Mill & Ball Mill SAG Mill & Ball Mill HPGR & Ball Mill Case Study Results Conclusion References
3
INTRODUCTION
4
Stress Forces - 1 courtesy: metso
Tensile
5
Compression
6
Stress Forces - 3 courtesy: metso
Impaction
7
Stress Forces - 4 courtesy: metso
Shearing
8
BOND’S WORK INDEX W= 10Wi ( 1/√P – 1/√F )
Bond’s Work Index (Wi) is the energy required, expressed as kWh/short ton to size reduce a material of infinitely large size particles to a product of 80% passing 100 microns. Following Equation is used to estimate specific power consumption for scale up purposes. W= 10Wi ( 1/√P – 1/√F )
9
DIFFERENT GRINDING EQUIPMENTS
BALL MILL In general the length of the mill is slightly higher than the diameter though not a rule. The grinding media is spherical . The size dispersion of the product is high.
10
ROD MILL Length is higher than the diameter as a rule.
The grinding media is rods. Mill product is coarse grind. ROD MILL
11
SEMI AUTOGENEOUS MILLS
Diameter is very large compared to length. Grinding media is feed lumps plus % ball charged. Less sensitive to feed size composition unlike AG mills. SEMI AUTOGENEOUS MILLS
12
HIGH PRESSURE GRINDING ROLLS
(HPGR) Two Rotating Rolls one fixed & other sliding against the fixed roll under pressure. High power saving. Product discharged as cake.
13
GRINDING CIRCUITS Fig:1 BALL MILL CIRCUIT
1) Ore Bin 2) Ball Mill 3) Mill Discharge sump 4) Mill Discharge Pump to Hydrocyclone 5) Hydrocyclone Fig:1 BALL MILL CIRCUIT
14
COMBINATION OF ROD & BALL MILL
F = feed, 1) Rod Mill 2) Mill Discharge Sump 3) Pump 4) Hydrocyclone 5) Ball Mill Fig: 2 COMBINATION OF ROD & BALL MILL
15
COMBINATION OF SAG & BALL MILL
F = feed, 1) SAG Mill 2) Mill Discharge Sump 3) Pump 4) Hydrocyclone 5) Ball Mill Fig: 3 COMBINATION OF SAG & BALL MILL
16
Fig:4 COMBINATION OF HPGR & BALL MILL
1) Ore Bin 2) HPGR 3) HPGR Discharge Screen Under Size Sump 4) Pump 5) Hydrocyclone 6) Ball Mill 7) Pump 8) Hydrocyclone Fig:4 COMBINATION OF HPGR & BALL MILL
17
CASE STUDY- 1 1500 TPD Jharmarkotra Phosphate Concentrator is laid in two streams with two ball mills operating in parallel. Each ball mill is driven by a 600 kW motor (fig:1) giving a throughput of 750 TPD. Energy Consumption in the 1500 TPD plant (Grinding, Floatation, Thickening & Filtration) per ton of the Ore treated was 49 kWh/ton at the best operating conditions. A roller press (HPGR) with drive motors of 700 kW ( ) was retro fitted into one of the grinding circuit (fig:4) such that the roller press works in tandem with the ball mill. This has resulted into increased throughput of 3000 TPD. The power consumption of TPD plant (Grinding, Floatation, Thickening & Filtration) reduced to 31 kWh/ton of the Ore treated at best operating conditions.
18
RESULTS: TABLE: 1 TABLE: 2
19
Case Study - 2 At Rampur- Agucha lead zinc mines of M/s Hindustan Zinc Ltd, grinding circuits with rod mill – ball mill and SAG mill – ball mill were installed depending on the changing hardness of ore from different mine pits. For harder ores SAG – ball mill combination is preferred.
20
Power Consumption of Rod/SAG mill Circuits.
Historical record suggests that rod mill-ball mill circuit including secondary crusher consumed kWh per ton of ore to achieve ground product of d80 at 63 microns. Whereas SAG mill- ball mill including primary crusher consumed kWh per ton of ore to achieve ground product of d80 at 63 microns.
21
Salient features of SAG- Ball Mill circuit
Primary crusher feed is 1.2 meters and the product size is -150 mm. It may be noted that entire secondary crushing plant is avoided in SAG- BM circuits. Cost of consumables is 30% higher for SAG – BM circuits compared to RM – BM circuits. Maintenance cost of RM- BM to SAG- BM circuits is 1: 1.1 .
22
CONCLUSION: It can be seen that the grinding circuit of HPGR – Ball Mill are highly energy efficient(1,3). Attempts are being made(4) to replace ball mill from HPGR – Ball Mill circuits with verti mills or stirred media grinding mills where very fine product sizes are acceptable/desired. RM- BM circuits consume less power, less grinding media/ other consumables and also maintenance cost is less. SAG – BM circuits do not need secondary crushing, can handle ores with varying characteristics and causes less dust pollution.
23
REFERENCES: Basics in Minerals Processing, Metso, 2012.
(a) Sekhar, D M R., Jain, C L., Jhamarkotra Phosphate Ore Processing Plant, International Mineral Processing Congress, Turkey, 2006. (b) HPGR in the Grinding Circuit of Phosphate Concentrator, 3 Joachintiarder, A T., Minerals Processing, Volume 53, 07-08/2012. 4 Drozdiak, JA., Klein,B., Nadolski,S.,& Bamber, A., A Pilot Scale Examination of a High Pressure Grinding Roll & Stirred Mills Comminution Circuit., International Autogeneous, Semi Autogeneous Grinding & High Pressure Grinding Roll Technology, Canada, 2011.
24
REFERENCES 5. Srikath Reddi, J Balasubramanian and Laxman Shektawat, Evaluating the Performance of Different Grinding Circuits at Rampura Agucha Mines, MPT- 2014, Andhra University.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.