1
LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 RC1 Construction and Test Plan
503 618 522 354 950 1406 LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 1 /10
2
Overall project plan presented at DOE LARP review 6/1/05
LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 2 /10
3
Single Jaw Thermal Test
Thermocouples measure temperature distribution Reference bar, water cooled to maintain straightness (radiation shield ?) Standoffs fix jaw distance to reference bar at center Capacitive proximity sensors at ends Flexible end mounts Orientation: may be rotated 90o, or 180o or on end 2 x 5 kW heaters, coupled with thermal grease LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 3 /10
4
Single Jaw Thermal Test
Purpose: measure cooling effectiveness and thermal deformations Internal helical cooling channels Jaw not rotatable Central aperture stop with flexible jaw end supports Commercial electric resistance heaters, coupled with thermal grease SS power ~10 kW, evenly distributed No transient testing FE model test => validation of simulations Water connections by conventional mechanical fittings Tank purged with inert gas to protect the copper jaw (?) Machine strain-relief grooves and re-test LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 4 /10
5
RC1 Mechanical Prototype
FY06 RC1 consists of jaws, tank & actuators - evaluated for horizontal (shown), vertical (90o) and skew (+/- 45o) orientations. FY07, RC2 Variant: use CERN vac tank, dummy jaws of correct weight LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 5 /10
6
RC1 Mechanical Prototype
Purpose: bench top testing of the jaw actuating mechanism in all necessary orientations lidded vacuum tank for easy access Need CERN adjustment mechanism - no support stand for RC1 Realistic cooling water feed-throughs and flexible connections no realistic connections to external world: no beam pipe aperture in tank, ad-hoc access to tank for cooling tubes, ad-hoc jaw aperture and rotation control, ad-hoc instrumentation connections for position, temperature, etc. RC2 will incorporate LHC-compliant interfaces Probably not possible to apply heat loading Variant: use dummy jaws of correct weight => use actual CERN vacuum tank (modify: removable cover) Use CERN Phase I components to the max extent possible LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 6 /10
7
Thermal & Mechanical Test Schedule
CY 06: 1 2 3 4 5 6 7 8 9 10 11 12 Thermal RC1 Mechanical RC1 Report & RC2 planning LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 7 /10
8
Thermal & Mechanical Test Milestones
Begin end Thermal test: engineer now 2/14 Thermal test: detail design 2/16 3/29 Assy complete, begin Thermal testing 5/1 5/30 Mech test: engineer 2/24 3/30 Mech test: detail design 4/3 7/17 Assy complete, begin Mechanical testing 9/22 12/6 LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 8 /10
9
Project Cost Estimates
Item (fract FTE) Category Basis Amount ($k) Tot ($k) ME1 (.5) Salary MS Project Work Plan 78.4 ME2 (.73) 145.9 Postdoc (.32) 32.2 Postdoc (.68) As assigned 87.8 Physicist (.3) 60.0 Mech Desgnr (.65) Assy tech (.42) 50.3 533.0 Equip Lab M&S vendors 57.0 Test articles M&S & shop NLC fab cost + 4x drilled jaw estimate 101.6 Total 691.6 LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 9 /10
10
Lab Area Selected in End Station B
Item Cost ($k) Chiller, etc 10.5 Vacuum eq’t 21.5 Heater controller 3.7 Gantry 6.4 Tools, table 4. instrumentation 10.0 Total 56.1 LARP LHC PHASE II COLL REVIEW – RC1 CONSTRUCT & TEST - E. Doyle 15 Dec No 10 /10