Presentation is loading. Please wait.

Presentation is loading. Please wait.

Elisabetta Ronchieri WP3

Similar presentations


Presentation on theme: "Elisabetta Ronchieri WP3"— Presentation transcript:

1 Elisabetta Ronchieri WP3
WP3 Status Update Elisabetta Ronchieri WP3

2 Content State of the Recruitment State of the Deliverables/Milestones
Reminder of WP3 Objectives/Tasks Workplan

3 State of the Recruitment
From 01/01/06 Guillermo Diez-Andino Sancho 100% Enrico Ferro 50% Elisabetta Ronchieri and Matteo Selmi were still on EGEE and have contributed as required to start up the activities and avoid delays From 01/04/06 Enrico Ferro 100% Elisabetta Ronchieri 100% Matteo Selmi 50% During these months strong collaboration with Alberto Di Meglio WP1 and Marc-Elian Begin WP5

4 WP3 Comand Line Interfaces
Team composition Current WP3 team WP3 Leader INFN Elisabetta Ronchieri WP3 Deputy INFN Enrico Ferro WP3 Comand Line Interfaces INFN Elisabetta Ronchieri, Matteo Selmi, Enrico Ferro WP3 Web Service CERN Guillermo Diez-Andino Sancho

5 State of the Deliverables/Milestones
List of deliverables D3.1 Configuration Build and Integration Specification at PM03 (DONE) D3.2 Interoperability Reports Specifications, Configuration, Build and Intgegration System at PM12 D3.3 Final Evaluation report and configuration, build and integration system at PM22 List of milestones M3.1 Configuration, Build and Integration System deployed in the ETICS resource pools (prototype) at PM12 M3.2 Configuration, Build and Integration System deployed in the ETICS resource pools (Final Release) at PM22 D3.1 Configuration, Build and Integration Specifications PM03 (31 March) Contribution for the Quarterly report PM03 (DONE)

6 Reminder of WP3 objectives/taks
List of objectives Provide a configuration schema to capture the configuration information of software developed by projects Provide a configuration, build and integration system based on existing or adapted tools List of tasks Define and analyze requirements starting from existing software projects, such as EGEE, DILIGENT, etc. Verify requirements for new EU projects or national initiatives: EU-OMII, etc. Adapt and maintain software tools for building, configuring and testing software Collaborate with WP2 in the deployment of tools Collaborate with WP4 in the definition and integration of middleware project tests

7 Workplan 1/3 31 March 14 April -> 19 May
Complete Read Mode Commands and Read WS Methods (DONE) etics-workspace-setup etics-get-project etics-checkout etics-build etics-list-project etics-list-resource etics-list-platform etics-list-property etics-list-configuration etics-show-configuration-structure etics-test 14 April -> 19 May Add the hash in the build command (DONE) Complete the job submission via NMI (DONE) etics-remote-build Add the packager in the client command (DONE)

8 Workplan 2/3 31 May 31 May -> 16 June
Define methods for the handling of users and roles Define new commands etics-list-user, etics-list-role, etics-user and etics-role Prototype for Edit mode commands and Edit WS Methods etics-platform etics-module 31 May -> 16 June Complete Edit mode commands and WS Methods etics-configuration etics-command tics-resource etics-property

9 Workplan 3/3 30 June 30 June -> 16 July ???
Complete security checks in Edit commands Complete user and role Commands etics-user etics-role etics-list-user etics-list-role 30 June -> 16 July Add the report. ??? etics-status-build We are waiting for WP2 API or command in order to get the status of the build. etics-remote-test


Download ppt "Elisabetta Ronchieri WP3"

Similar presentations


Ads by Google