1 Preparing Baby MIND for Japan
E. Noah 26th July 2017

2 Transport logistics: Geneva-Japan
Main topics today Transport logistics: Geneva-Japan What are the transport options? What is the timeline? Equipment for packing Storage issues Installation of Baby MIND at J-PARC Installation requirements What are the installation options? Installation sequencing w.r.t. sideMRD and WAGASCI? Preparation work: Integration with WAGASCI systems Electronics to be developed (MCB, MCR daughter board) DAQ

3 TRANSPORT

4 All options: Shipping sequence: Transport options
ARMCO + scintillator: Send 4 chassis on 20’ Hardtop x4 (no control of temperature!!) with scintillator modules. Option to insulate on the inside (though not much room) Check maximum admissible load per meter ARMCO + scintillator: Send 4 chassis on 20’ flatrack x4 (no control of temperature!!) with scintillator modules with cover! Max. risk of damage to scintillator modules. Can design wood cover to go around plastic water-tight cover. ARMCO + scintillator: Send 4 chassis in 4 reefers (40’ High Cube Reefer) on rollers: i.e. push into container, and pull back out of container. Check load per meter in container with DB schenker. Check height. Check how to attach to container ARMCO separate to scintillator: Send 4 chassis with ARMCO only standard 20’ flatrack x4 scintillator modules in separate reefer!! Shipping sequence: Send everything at once Send in two separate shipments: one in September, one in November

5 Shipping option 1) Roof opening dimensions: Hapag-Lloyd 20’ hardtop container (example given here is Hapag-Lloyd) 2260 3930 2150 Inside dimensions: Hapag-Lloyd Door opening dimensions: Hapag-Lloyd

6 Shipping option 4) Scintillator modules shipping: 1 or 2 refrigerated (reefer) containers Loaded horizontally on special oversize palettes Magnet modules shipping: 4 platforms Tarpaulins to protect from weather 1 chassis loaded on each: 18 to 20 t each

7 INSTALLATION

8 See slides by Minamino-san.
Installation at J-PARC All options: Install several small chassis: re-use some Baby MIND transport chassis. Install several small chassis: all new. Install one big chassis for all. See slides by Minamino-san.

9 Work plan options: To do:
To do list Work plan options: Plan September trip: (Etam+Laurent+??) test with a wooden structure all the actions to unload and install in the pit. To do: Contact Muffat/Krattinger to review a few options DB Schenker Quote for special palette (Ordem SA and others) Design of palette Quote for wooden box covers for flatrack transport. Design of rolling system IF small chassis system Based on Chariot de transport FUTURO ( Design pivot system to be able to displace chassis in different directions. With butée à billes SKF