1 EN 4946 – Refurbishment of Electrical Substations
Gerardo Velázquez Gutiérrez - EN-EL-ENP

2 Projects Summary Projects completed. New 400/66 kV Substation BE2.
Renovation 400 kV Protection & Control System. The SPS test stand for HiLumi Crab Cavities East Area Consolidation. Building 272 – Workshop TE-MPE.

3 Projects completed. 66/18 kV Protection System Upgrade
Building 272 – Test Lab for TE-MPE. RPADO Converters for TE-EPC Test Lab building 272 Commissioning Works in LHC4

4 New 400/66 kV Substation BE2 & 400 kV Protection & Control System: Design and Execution Phase
Role: Project Engineer Status: Design Phase taking in account possible 400 kV extension, Users, RTE and French Authorities. Transformer Design – On going. 400 kV Protection – Design Phase. Preliminary civil works done. Next steps: Civil Engineering – Execution phase. Validation of the mechanical design of the transformer

5 The SPS test stand for Crab Cavity projects.
Role: Project Manager Main client: BE-RF Location: BA6 and LSS6 1200 kVA requested by the users. Scope: Installation of a new 2 MVA 18/0.4 kV transformer in building BA6. 400V Electrical distribution 21 kW UPS power 1kW Secured network Energization foreseen January 2018

6 The East Area & 272 – Workshop TE-MPE
East Area Consolidation Role: Project Manager Client: EN-EA Electrical Consolidation in East Area to be done during LS2. Conceptual Design Report finished by June 2017. Building 272 – Workshop Role: Project Manager Client: TE-MPE New Electrical Installation for the new workshop. Status of the works: Energization beginning July 2017.