Site Grading of Terrace
Norman W. Garrick CE 4410 Spring Lecture 7
2
Terrace slopes 3/% down to top Side slopes in cut: 3:1 max
110 109.5 Terrace: 4 m by 5 m Terrace slopes 3/% down to top Side slopes in cut: 3:1 max 107.0 107.5 108.0 108.1 108.1 108.5 109.0 4 m 109.5
3
110 109.5 107.0 107.5 107.8 107.8 108.0 108.1 108.1 108.5 109.0 4 m 109.5
4
Contour 108.5 is 1.2 m from Point A
110 109.5 Contour is 1.2 m from Point A 107.0 107.5 107.8 107.8 108.0 A 108.1 108.1 108.5 109.0 4 m 109.5
5
Contour 109 is 2.7 m from Point A
110 109.5 Contour 109 is 2.7 m from Point A 107.0 107.5 107.8 107.8 108.0 A 108.1 108.1 108.5 109.0 4 m 109.5
6
Contour 108 crosses the terrace
110 109.5 Contour 108 crosses the terrace 107.0 107.5 107.8 107.8 108.0 A 108.1 108.5 109.0 4 m 109.5
7
Contour 109.5 is 4.2 m from Point A
110 109.5 Contour is 4.2 m from Point A 107.0 107.5 107.8 107.8 108.0 A 108.1 108.1 108.5 109.0 4 m 109.5
8
Same relationship for Point B
110 109.5 Same relationship for Point B 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m 109.5
9
110 109.5 Repeat for C and D 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m 109.5
10
110 109.5 Draw Contour 108 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m 109.5
11
110 109.5 Draw Contour 108.5 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m 109.5
12
110 109.5 Draw Contour 109 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m
13
110 109.5 107.0 107.5 108.0 108.5 109.0 Draw Contour 109.5 107.8 107.8 A B 108.1 108.1 4 m
14
Complete Grading Plan 4 m 110 109.5 107.0 107.5 107.8 107.8 108.0 A B
108.1 108.1 108.5 109.0 4 m
15
110 109.5 Any Design Issues? 107.0 107.5 107.8 107.8 108.0 A B 108.1 108.1 108.5 109.0 4 m
16
Creating a Diversion X X X 4 m 110 109.5 107.0 107.2 107.5 107.8 107.8
108.0 A 108.1 108.1 107.7 107.7 X X X 107.9 108.5 109.0 4 m 109.5
17
Complete the 108 ft Contour
110 109.5 Complete the 108 ft Contour 107.0 107.2 107.5 107.8 107.8 108.0 A 108.1 108.1 107.7 107.7 X X X 107.9 108.5 109.0 4 m 109.5
18
110 109.5 108 Ft Contour Lines 107.0 107.2 107.5 107.8 107.8 108.0 A 108.1 108.1 107.7 107.7 X X X 107.9 108.5 109.0 4 m 109.5
19
Complete Grading with Diversion
110 109.5 Complete Grading with Diversion 107.0 107.2 107.5 107.8 107.8 108.0 A 108.1 108.1 107.7 107.7 X X X 107.9 108.5 109.0 4 m 109.5
20
Calculation of Cut and Fill
21
110 109.5 107.0 107.5 108.0 108.5 109.0 106.5
22
110 109.5 107.0 107.5 108.0 108.5 109.0 106.5 A B
23
Profile A - B Proposed Existing A B
24
110 109.5 107.0 107.5 108.0 108.5 109.0 106.5 Limits of Cut and Fill
25
How do we Calculation Cut and Fill?
We look at three methods: Average End Area Method Contour Area Method Borrow Pit Method
26
Average End Area Method
Typically used for linear projects such as roads, railroads, canals
27
Find area of Fill and Cut separately
for selected cross-sections Volume of Fill (or cut) between Two Cross-sections = [(A1 + A2)/2 ] * L Where: A1 is area of fill for Cross-section 1 A2 is area of fill for Cross-section 2 L is distance between 1 and 2
28
A refinement to this approach is used
when A1 or A2 is an end cross-section (there is not fill or cut) In this case, (A1+A2)/2 * L Over estimates the volume since The shape of the earthwork is more Like a pyramid. In this case a more accurate formula Is [(A1+A2)/3] * L (Note there is an error in text for this formula)