Implementation Support
Ministry of Industry and Commerce Department of Planning and Cooperation Foreign Aid Division National Implementation Unit EIF Tier-2 Project: Strengthening National Quality Infrastructure and Industrial Statistics in the Lao PDR Implementation Support Project Review Committee Meeting By Sengphanomchone Inthasane, DPC, MOIC 25 May 2016
2
Contents Project Summary Technical Support Project Performance
Procurement Financial Management M&E IV Work Plan
3
Project Summary Project title:
Strengthening National Quality Infrastructure and Industrial Statistics in Lao PDR Grant recipient of entity: Department of Planning and Cooperation, MoIC Main Implementing entities: Department of Standardization and Metrology, MoST; and Department of Industry and Handicraft, MoIC Starting date: December 2013 End date: December 2016 Duration: 3 years EIF funding sought: USD 2,458,000
4
Project Summary (cont.)
Objective to increase quality, safety and reliability of Lao products and services, and improve competitiveness through implementing national standards, technical regulations and formulating and implementing viable industrial development policies based on systematic, comparable and action-oriented country analysis. Project components: Component A: Development of National Quality Infrastructure (USD 1,745,000) Component B: Enhancement of the Industrial Statistics (USD 713,000)
5
Project Performance: Technical Support
Launching the project Drafting the annual work plan Technical inputs to IA’s capacity building program Communicating with the EIF Consolidating quarterly progress report Drafting semi-annual and annual Narrative Report
6
Project Performance: Procurement
No. Activity Contract signed Consultants: 1 Intl. Procurement Specialist (part-time) Feb 1, 2014 2 Nat. Procurement Officer (NIU) Jun 1, 2014 3 Nat. Project Coordinator (DSM) Jul 28, 2014 4 Intl. Expert on Metrology Aug 29, 2014 5 Intl. Expert on Accreditation/Quality Center Sep 13, 2014 6 UNIDO Oct 27, 2014 7 Nat. IT Officer Oct 30, 2014 8 Intl. Expert on Standardization Nov 10, 2014
7
Project Performance: Procurement (cont.)
No. Activity Contract Signed Goods: 1 Office equipment Jun 16, 2014 2 Vehicle for Mobile Lab Jun 19, 2014 3 Lab Equipment Oct 14, 2015
8
Project Performance: Financial Management
Amount spent in 2014: US$ 440, (17.5%) Amount spent in 2015: US$ 530, (21%) Amount planned for 2016: US$ 756, (30%) Remaining after 2016: US$ 792, (31.5%)
9
Project Performance: M&E
Output Indicators Target 2014 2015 2016 A1: Procedures for developing national standards and adopting international standards developed 2 - 1 Participation in ISO and WTO TBT Committee 6 A2: Quality System Manual for Labs developed Calibration service unit created
10
Project Performance: M&E (cont.)
Output Indicators Target 2014 2015 2016 A3: ISO/IEC accreditation standards and guides obtained 100 - 28 Associate membership of APLAC 1 A4: National quality needs assessment survey conducted Operational plan for Quality Center Developed
11
Project Performance: M&E (cont.)
Output Indicators Target 2014 2015 2016 B: Staff Trained 12 - 34 Database system developed 1 Prototype software system developed List of the statistical indicators developed Finally, the outputs expected from Component B have also been adequately achieve. It is noted here that the number of staffs trained has been overred the target. the number includes the staff members mainly industrial statisticians in the provincial department who were also heavily trained that who we were not foreseen would be one of the core beneficiaries when we designed the project. This is because the DIH has decided to lead the survey process and involved the provincial department of industry and commerce as much as possible for data collection and entry, as oppose to hiring external consulting firm. The database system has been developed as well as the Prototype Software System. The list of statistical indicators will be developed following the completion of Manufacturing Establishment Survey.
12
Finalizing the procurement of Lab equipment
2016 Work Plan Finalizing the procurement of Lab equipment Proposal for the no-cost extension Budget Revision Drafting the Request Capacity Building – Project Management
13
Thank You for your attention