EHN1: CE Integration process updating
Martin Manfredi SMB-SE
2
ROUTING SERVICES ‘EAU INCENDIE’– SALEVE SIDE - TG DONE
ROUTING SERVICES ‘EAU INDUSTRIELLE’ AND ‘EAU POMPAGE – JURA SIDE – TG => OK DONE Reference plan submitted by CV have been forwarded to contractor ROUTING SERVICES ‘EAU INCENDIE’– SALEVE SIDE - TG DONE Reference plan submitted by CV have been forwarded to contractor JR: Piquage DN 80 + bride + obturation par plaque pleine communiqué CERN_CV ? TBC TBC JR: Piquage DN 50 + bride + obturation par plaque pleine communiqué
3
VENTILATION GRILLES: Position to be confirmed by CV DONE
Lift up of 400mm ??
4
CABLE TRAY ON NORTH GABLE: PENDING
The possible options of intervention (SMB <-> EL): EL to temporary remove the tray and protect the cables (before mid-July) before the dismantling process start --> Our contractor remove the entire surface of the wall --> You come back to reposition your cables (after CE handover). EL to permanently remove the tray by fixing the hall cable lighting in the steel beam (like the other axis?) and deviate/cut, after your internal evaluation, the other cables (before mid-July) --> Our contractor remove the entire surface of the wall; Our contractor retains inconvenient or unfeasible to operate even without the tray and we finally conclude to dismantle only the portion below the tray and keep the rest there --> No impact for EL. We will deal with the cables protection during the dismantling process.
5
GRATING STEPS: DONE
6
CALE DYNAMOMÉTRIQUE: DONE
7
Martin Manfredi SMB-SE
EHN1: Status CE works Martin Manfredi SMB-SE
8
Next Steps: Activities scheduled untill end-MARCH
08/03/2016 (1) INSIDE PITS: (A+B) Erection/Installation precast internal walls (209 elements in total). 70% DONE. Currently working on 1st and 2nd level on the PIT B; (2) SLAB SYSTEM: S4, S5 lower slab and drainage complex to be executed. Backfilling process in parallel Execution remaining part of the retaining wall on top of the GHN106 by end-February
9
Martin Manfredi SMB-SE
EHN1: Planning CE works Martin Manfredi SMB-SE
10
DRAFT : Discussion w/ contractor ongoing Deadlines to be confirmed
TRAVAUX CHARPENTE MÉTALLIQUE DRAFT : Discussion w/ contractor ongoing Deadlines to be confirmed 11/08 02/09 16/09 Official building delivery date is 15/08; Delay during WP1 activities led to review WP2 schedule; New planning with delivery date shifted to 16/09 (+4wks); End of North gable dismantling (concrete wall ongoing) End of the CE activities inside the building (outside on going) PARTIAL HANDOVER End of the CE activities outside the building FINAL HANDOVER Partial handover granted from 02/09 , allowing service installation to start inside the building; Thus, 2wks of activities lost between 15/08 --> 02/09; Contractor propose a time window to access the building (15/07 --> 29/07, i.e. 2wks); EHN1 Temporary lighting; Installation of pits’ barrier; Crane cabling (commissioning after 11/08) Start installation of cable trays in the Hall Identification of the activities to be carried out inside the building Issue of access (personnel, material, etc..) to be identified; Crane commissioning potentially possible after 11/08 ; Activities inside the GHN106 can start from 04/04. Proposition for mid-June. Can we create an access on the existing concrete wall ?