Presentation is loading. Please wait.

Presentation is loading. Please wait.

Earned Value Management & Oracle Primavera P6

Similar presentations


Presentation on theme: "Earned Value Management & Oracle Primavera P6"— Presentation transcript:

1 Earned Value Management & Oracle Primavera P6
Oracle Primavera P6 EPPM Certified Implementation Specialist Global Project Management, LLC Trey Miller, MBA, PMP 3090 Gause Boulevard, No. 614 Slidell, LA 70461 Tel:

2 Global Project Management, LLC
Based in Slidell, LA Project consulting, training, and staffing since 1996 PMI Global Registered Education Provider Partner / reseller of: Oracle Hard Dollar View Point

3 Global Project Management, LLC
Consulting: Scheduling & Cost Controls Staffing: Schedulers, PMs, Planners, Estimators, and project support personnel. Training: Oracle Primavera Products: Primavera P6, Contract Manager, Contractor, Risk Analysis, P3, and SureTrak PMP® and CAPM® Certification Project Management and Scheduling Fundamentals Earned Value Management

4 What is Earned Value Management?
Earned Value Management (EVM) is a project management technique for measuring project performance and progress. A systematic approach to the integration and measurement of cost, schedule, and scope on a project.

5 EVM in History 1960s – DoD adopted it as an objective measure of project progress. 1970s – Continued use in DoD as a means to offset cost and schedule risk in cost reimbursable contracts. 1990s – Policy moved Earned Value into all federal agencies

6

7 Earned Value Management
Terminology Differences Three data points Actual Costs Planned Value Earned Value Terminology Differences (PMI vs. P6)

8 Actual Cost (AC) Primavera P6: “Actual Cost” Cumulative Graph: ACWP

9 Planned Value (PV) Primavera P6: “Planned Value Cost”
Budget at Completion X Planned % Complete Graph: BCWS

10 Earned Value (EV) Primavera P6: “Earned Value Cost”
Budget at Completion X % Complete “Completed Work Value” Graph: BCWP Concepts is that activities earn value as work progresses When you complete that piece of work, you have ‘earned’ its value!!!

11 Budget at Completion (BAC)
Primavera P6: “Budgeted Total Cost” PV at end of project Next Slide: So, what do we do with AC, PV, and EV?

12 Cost Variance Over / Under budget? CV = EV – AC Results?? AC EV
Abbreviated CV Over / Under budget? CV = EV – AC Results?? Negative Number Positive Number AC c EV

13 Cost Performance Index (CPI)
CPI = EV / AC Next is EAC….

14 Estimate at Completion (EAC)
The expected total cost of a project when the project work will be completed. AKA: Forecast At Completion EAC = BAC / CPI EV

15 To Complete Performance Index
TCPI is an index showing the efficiency at which the resources on the project should be utilized for the remainder of the project. Remaining Work / Funds Remaining TCPI = (BAC – EV) / (BAC – AC) CPI at .90 and we are 50% complete with the activity, TCPI would be 1.10.

16 “A fool with a tool is still a fool”
Oracle Primavera P6 “A fool with a tool is still a fool” - Grady Booch You need to understand EVM first!

17 Using P6 For EVM A few considerations… Understand EVM
Percent complete type? Customize the layout

18 Creating the Layout Step 1

19 Cost Loaded Schedule & Update it!
What is the Earned Value for activity A1020? $47,500.00 Step 2

20 Earned Value Calculations
So, what is the TCPI? 112% going forward! Step 3 – Review Output

21 Thank you! Global Project Management, LLC Trey Miller, MBA, PMP
Oracle Primavera P6 EPPM Certified Implementation Specialist Global Project Management, LLC Trey Miller, MBA, PMP 3090 Gause Boulevard, No. 614 Slidell, LA 70461 Tel:


Download ppt "Earned Value Management & Oracle Primavera P6"

Similar presentations


Ads by Google