1 Toronto Pearson Runway Closures September / October 2013

2 Construction: Summary of events Jul-Aug 2013
Completed: July: Runway 15R-33L Re-habilitation. July - August Navigational aides re-certification.

3 Runway Closure Schedule
Runways 05/23 and 15R/33L September 6 (2200) until September 11 (1500) Runway 06L/24R September 16 (0700) until October 4 (1500)

4 Impact – Closure of Runways 05/23 and 15R/33L
Increased departures on runways: 06L/24R (Flight Zones D3 and D5) 33R (Flight Zone D1) Increased arrivals on runways: 06R/24L (Flight Zones D3 and D5) 15L (Flight Zones A4, A7, A2) Increased night non-preferential operations.

5 Impact – Closure of Runways 05/23 and 15R/33L

6 Impact – Closure of Runway 06L/24R
Higher traffic volumes on Runway 05/23 and 06R/24L Departures on Rwy 06R/24L will result in flights closer to the communities south of the airport Increased night non-preferential operations

7 Impact – Closure of Runway 06L/24R

8 Communications Regular updates on Toronto Pearson Advisory page
updates to CENAC members and elected officials when changes occur, or when particular impacts are anticipated 8 8