Pinole Valley High School (PVHS) Project Status
Facilities Subcommittee Meeting June 9, 2015
2
PVHS Project Overview Project Efforts 2010 - present
Design Concept Development with Site, Community Traffic Impact Assessments and Coordination with City of Pinole Hillside Evaluation and Design Efforts Phasing Development & Coordination (5 Major Phases) Offsite Projects (Parking, Ball Field Improvements) Building Size 268,000 SF Student Capacity 1,600
3
PVHS Project Phase Status
Detention Basin Completed Summer 2014 Temp Housing (E) Campus Demo Completion Summer 2015 Hillside Reconstruction Completion Fall 2015 (N) Campus Construction Completion Fall 2018 Remaining Phases: Pinole Valley Road Improvements, Temp Housing Demo, Sports Fields/Courts
4
PVHS Scheduled Tasks Constructability & District Reviews
January – June 2015 Cost/Budget Reconciliation June/July 2015 DSA Back-check/Stamp-out Q4 2015 Project Bid Period Construction Start Q1 2016 Buildings Occupied Fall 2018
5
PVHS Budget Considerations
Phase Construction Cost/Estimate Detention Basin (Spring 2014) $3,121,600 Temp Housing, including offsite improvements (Summer 2014) $7,479,200 Hillside Reconstruction (Winter 2015) $1,890,800 (E) Campus Demolition (Winter/Spring 2015) $1,722,600 (N) Campus Construction & PV Road Improvements (BOE – 06/19/13) $104,234,610 Remaining Phases: Temp Housing Demolition, Sports Fields/Courts (Budget) $18,300,000 Total (Construction) $136,748,810 Supporting Costs (25% Project Cost) $45,151,190 Board Approved Budget (February 6, 2013) $181,900,000
6
PVHS Budget – New Campus
Soft Costs Cost/Budget Surveys and Reports $413,700 Thorton Tomasetti, Mercurial (OPSC seismic State fund eligibility) Geotechnical Reports $93,300 Kleinfelder (survey, analysis, seismic fault investigation) Other Design Cost $492,028 CHPS commissioning, waterproofing, constructability review, estimating Program Management $2,978,132 SGI - Planning, schedule/budget mgt., contracts/invoices, document management Design Manager $1,489,066 SGI - Project scope/budget management, meetings, consultant & district coord'n, bid structure Specialty Consultants $342,520 Commission'g - Solar, PV Road Design, Security Reproduction Costs $30,000 BPX (Budget - $14K Actual through March 2015) DSA Plan Check $610,585 (Basis - Construction Budget: $104,234,610) A/E Design & Bid $8,957,442 WLC (Contract portion through Amendment #4) A/E CA & Close-out $3,838,904 Construction Management $3,000,000 SGI - Projected (32 Mos. - 1 Sr. CM, 1 CM, 1 Estimator/Scheduler,1 Project Engineer) DSA Inspector of Record $800,000 Projected (32 Months) Testing & Materials $500,000 Move Services $100,000 Budget Furniture $1,500,000 Budget (Reference: DAHS - $1.2M, SGA - $1.34M) Technology Budget - To be confirmed Sub-Totals Soft Costs $26,645,676 Total allocated: $45,151,190 (~$19.5M for other 5 phases/sub-phases) Hard Costs Construction Contingency $4,963,553 (5% Projected) - Change Orders during construction Construction $99,271,057 Includes PV Rd. Improvements, Surveillance, etc. Sub-Totals Hard Costs $104,234,610 Budget (06/19/13) Soft Cost 20.4% Hard Cost 79.6% Total $130,880,286
7
PVHS Next Steps Completion of Constructability & Stakeholder Review Process Cost/Budget/Scope Reconciliation DSA Back Check & Stampout Project Bid