1 ROB at Pulianam Progress as on 4.11.2011
Manager : Jemymathew, RBDCK ,

2 Manager in Charge RBDCK : JemyMathew
Consultant : KITCO Ltd Contractor : Skilled construction Company ltd Manager in Charge RBDCK : JemyMathew Contact No Project Engineer KITCO : Mr.Gopalakrishna Panickar Site Engineer ,Skilled : Charls

3 PROJECT DETAILS ROB at Puliayanam in lieu of LC No.59 between Karukutti and Angamaly  Stations 1. Total Length of bridge including Railway Portion m                         2 .Length of Railway Portion (Not in the scope of RBDCK)   40m 3. Length of Approach portion towards Puliyanam-            m 4. Length of Approach portion towards NH side-                   m 5. Slope of ROB towards Puliyanam side                                 1 in 25 6. Slope of ROB towards NHside                                               1 in 20 7. Width of Carriage way                                                            7.5m 8. Total width of bridge including crash barriers                     8.5m 9.Agreed PAC of approach portion  to be done by RBDCK                                                               Crores 10.Period of Completion                                                             12months 11.Contractor for the project                       Skilled Construction Company Ltd 12.Consultant                                                       KITCO Ltd         

4 PROGRESS OF ROB WORK AS ON 4.11.2011
Progress Report For Pulianam  ROB for the week ending on Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 1 Pile towards NH side 26 TARGET ACHIEVED 2 Pile towards Puliyanam side 18 3 Pile cap at NH Side 6 4 Pile Cap at Pulianam side 5 RC wall at Puliyanam side 100% 25% 75% 0% 5% RC wall at NH side 95% Pier at NH Side 7 Pier at Puliyanam Side 8 Piercap at NH Side 9 Piercap at Puliyanam

5 Date Climate pleasant HOLIDAY RAIN No.of labours 50 53 40 45 availability of material materials Required Available Fine aggregate(M3) 7 10 Coarse aggregate(M3) 15 24 Cement(BAG) 300 600 Steel(TONN) 2 56

6 Progress graph

7 EARTH WORK FOR RC WALL NH SIDE

8 EARTH WORK FOR RC WALL PULIYANAM SIDE

9 PIER CAP P2 CONCRETE

10 PIER CAP P10 SHUTTERING.

11 PILE CAP P6 CONCRETE

12 RC WALL REINFORCEMENT WORK

13 SHUTTERING FOR RC WALL STEM

14 Thank you