Presentation is loading. Please wait.

Presentation is loading. Please wait.

Tile Input Options for Phase-1

Similar presentations


Presentation on theme: "Tile Input Options for Phase-1"— Presentation transcript:

1 Tile Input Options for Phase-1
Topic in a nut-shell: Phase-1 FEXes receive digital signals from upgraded LArg (new FE plus DPS) Tile does not upgrade until Phase-2 Need to maintain legacy analogue path until FEXes are fully commissioned What is the best input route for Tile to FEXes? Thanks to many people who contributed to these slides and discussion 14th May 2013 Tile Input Options

2 Preliminaries 14th May 2013 Tile Input Options

3 The Three Options Numbering consistent with twiki below
TCPP RX PPM JEM TileCal L1A How to connect? FEXes L1A 14th May 2013 Tile Input Options

4 Option 1: ‘Tile DPS’ Requires splitting of signals at TCPP
Tile DPS modules similar to LArg DPS New TCPP RX PPM JEM TileCal L1A Tile DPS FEXes L1A 14th May 2013 Tile Input Options

5 Option 2: PPM RTM Requires new RTM for PPM
Also requires new LCD daughter-card TCPP RX PPM R T M JEM TileCal L1A FEXes L1A 14th May 2013 Tile Input Options

6 Option 3: JEM Requires new JEM daughtercard
Also same upgrade to PPM LCD daughtercard TCPP RX PPM JEM TileCal L1A FEXes L1A 14th May 2013 Tile Input Options

7 The overall picture 14th May 2013 Tile Input Options

8 IDR review request Establish a process, using external expertise, to evaluate the three options presented for directing Tile Calorimeter signals into jFEX. The evaluation should factor in the technical and funding risks, and the resources available to implement the options. A baseline should be established before the TDR. Passing note: need input to eFEX and jFEX! Will first review what steps we’ve taken Then move onto details of findings 14th May 2013 Tile Input Options

9 Review procedure Establish a process, using external expertise, to evaluate the three options presented for directing Tile Calorimeter signals into jFEX. The evaluation should factor in the technical and funding risks, and the resources available to implement the options. A baseline should be established before the TDR. Set up a group of 10 members drawn from L1Calo, TDAQ, Tile, Larg and outside, with representation of each of the options Christian Bohm, Philippe Farthouat, Stephen Hillier, Francesco Lanni, Robin Middleton, Thilo Pauly, Srini Rajagopalan, Carlos Solans Sanchez, Uli Schafer, Hans-Christian Schulz-Coulon Plus several ‘ex-officio’ Martin Aleksa, Phil Allport, Chris Bee, Ana Henriques Correia, Stefano Veneziano, Martin Wessels Regular meetings on a Friday subsequent to presentations in TDAQ week 14th May 2013 Tile Input Options

10 Criteria for Decision Establish a process, using external expertise, to evaluate the three options presented for directing Tile Calorimeter signals into jFEX. The evaluation should factor in the technical and funding risks, and the resources available to implement the options. A baseline should be established before the TDR. Technical feasibility Disruption to existing system Installation and commissioning effort Latency Physics performance Cost and effort requirements 14th May 2013 Tile Input Options

11 Time-scale for decision
Establish a process, using external expertise, to evaluate the three options presented for directing Tile Calorimeter signals into jFEX. The evaluation should factor in the technical and funding risks, and the resources available to implement the options. A baseline should be established before the TDR. Note: Planning for MoU also requires a decision TDR timescale is short Partial TDR time-line Robin Middleton has proposed for the L1Calo sections 23rd April: Draft 0.1 31st May: Baseline Finalized 15th June: Full Draft for L1Calo Feedback 14th May 2013 Tile Input Options

12 Original proposed milestones
Monday 25th March Agree process and encourage continuing investigations, such as: Each system to study design for the important criteria Finalize physics studies of LSB choice and noise Wednesday 10th April Dedicated meeting in TDAQ week with open discussion Decide if more work and open meetings required Post-TDAQ week Core group to meet and discuss as required Ask for additional information if needed ATLAS Upgrade week: May 13th – 17th Report from core group to be presented Initially in joint Calo/TDAQ meeting Aim for agreement from all sides End of May: Upgrade Steering Group Decision presented and finalized TODAY 14th May 2013 Tile Input Options

13 More details on options: a few key features
14th May 2013 Tile Input Options

14 Option 1: Tile DPS Data branching
Replace 64 TCPPs in 4 crates 256 Tile input cables 128 calo output cables 128 muon output cables Add ADCs and digital output 14th May 2013 Tile Input Options

15 Option 1: Tile DPS Data processing
Use pre-existing LArg DPS technology and crates Similar (if not identical) infrastructure, algorithms, firmware etc Just 1 or 2 extra DPS modules Option to include Tile D-layer from Day-1 Possible advantages for jet punch-through 14th May 2013 Tile Input Options

16 Option 2 and 3: Double speed data transmission
Both options require more data out of PPM Achieved via new MCMs (2015) and new LCD (2018) Internal double data rate already tested with nMCM 32 PPMs in two crates require new LCD 14th May 2013 Tile Input Options

17 Option 2: Data Branching via PPM REX
New RTM for 32 PPMs in two crates Contains FPGA for data conversion and optical outputs Legacy digital cables as before, signals pass through RTM 14th May 2013 Tile Input Options

18 Option 3: Data branching via JEM
JEM receives double data rate in new input daughtercards Three of these retransmit optical signals Signal transmission over 11m LVDS cables to be tested 14th May 2013 Tile Input Options

19 Evaluation 14th May 2013 Tile Input Options

20 Group evaluation of options
Initially I summarized my thoughts We sought extra input on some items Though not all issues can be addressed on this time-scale Looked in more detail at some topics Discussed evaluations Christian Bohm set up twiki for documentation and comments Evolved with input from several people Upcoming slides are a summary of the twiki as it stands 14th May 2013 Tile Input Options

21 General remarks Option 1 digitization is a new development, where we already have a digitization solution that is known to be working But it is no tougher than than the LArg FE upgrade The output of each option to eFEX and jFEX should be identical, no matter the route to get there For the core Tile towers anyway, and it should be similar to HEC output Most of the rest of the twiki addresses the criteria for the decision 14th May 2013 Tile Input Options

22 Technical Feasibility
The ‘active-TCPP’ has not yet been demonstrated, particular in its effect on the legacy signals But, as before, this solution is similar to the LArg FE, and should be no more difficult Transmission of double data rate over LVDS has yet to be demonstrated for Option 3 Though some of the path is already tested with the nMCM, so Option 2 is closer to being proved Overall, none of the solutions look to be ‘challenging’ Solutions near at hand, or at least if the solution does not work, then Phase-1 Upgrade is already in trouble No reason to believe any option is harder than the others 14th May 2013 Tile Input Options

23 Disruption to existing system/ Installation and commissioning effort
Option 3 appears to be favoured Purely replacement of daughter-cards Small amount of extra optical cabling, but this is necessary anyway for all solutions Option 1 and 2 require re-cabling Option 1: at least 384 analogue cables in four crates Option 2: about 500 LVDS cables in two crates Re-cabling in both cases will mean adjustment to strain relief From bitter experience, handling lighter LVDS cables is a lot easier than the heavy analogue cables Daughter-card replacements can be done in small quantities TCPP replacement likely to be one crate at a time (at least) Note, even with differences, probably small perturbation to overall disruption in LS2 due to LArg upgrade and addition of FEXes 14th May 2013 Tile Input Options

24 Latency Latency will be tight, and this is a key criteria
For Option 2 and 3, latency for signals to FEXes will be a 2-3 BCs more than current availability at processors Inevitable with addition of optical encoding Estimates for Option 1 in line with LArg processing and other options Probably no big difference to other routes Conclusion: though latency is critical, there’s probably not a big difference in the three options 14th May 2013 Tile Input Options

25 Physics Performance This divides into two areas: Signal Processing
Can we improve the signal quality to the processors? Does extra data (Tile D-layers) help the trigger? Signal Processing New filters, correction techniques may improve performance Flexibility not available with currents MCMs But these are already being replaced in 2015 Comparison of processing resources in FPGAs Tile DPS will use advanced powerful FPGAs But each one is expected to process several hundred channels Possible advantage by cross-correlating with other channels PPM nMCMs are smaller, but only process four channels each Overall, PPM will have more processing resources 14th May 2013 Tile Input Options

26 Physics Performance This divides into two areas: Tile D-layer
Can we improve the signal quality to the processors? Does extra data (Tile D-layers) help the trigger? Tile D-layer Could be available in Tile DPS from day-1 Slightly more expensive, baseline comparison is without this option For Option 2 or 3 could provide this data, but only when legacy system de-commissioned Possibility to improve jet resolution? Note that signals were designed for muon output High gain, saturate at 12 GeV Judge that there may be some advantage in Option 1 But usefulness is yet to be proven 14th May 2013 Tile Input Options

27 Cost Requirement Comparison of options without D-layer
Core costs only For details see the backup slides Option 1: €145,000 Option 2: €80,000 Option 3: €110,000 Of course all these depend on exact choice of FPGAs etc 14th May 2013 Tile Input Options

28 Effort Requirement To be honest we haven’t gone into this in detail
And we are all at the whim of funding agencies However, worth assessing likely available effort Option 1: Strong expectation that support for this will be funded and bring in new effort Option 2: Effort clearly available within PPM group Option 3: PPM effort again clear, but JEM effort will be split between this and other upgrade projects Note this commits effort to long-term maintenance of PPMs/JEMs 14th May 2013 Tile Input Options

29 Impact on Phase-2 Upgrades
Bold statement that hasn’t been challenged There should be no impact This is purely a stop-gap solution for LS2 to LS3 Hardware will be ‘junked’ in LS3 So vice-versa, I argue that there’s no Phase-2 ‘synergy’ argument for any option 14th May 2013 Tile Input Options

30 Availability of JEM effort?
Summary Table Caveat: Differences, where they have been identified, are not necessarily very large 1 = best, 3 = worst Item Option 1 Option 2 Option 3 Comment Feasibility = Commissioning 3 2 1 Small cf LArg Upgrade Latency Physics Perf. Need to study D-layer Cost Effort Availability of JEM effort? Phase-2 Impact 14th May 2013 Tile Input Options

31 Conclusion The core group has not reached a full consensus
Though there was a preference among many for Option 3 at the last meeting We would be grateful for further insights from this meeting today Ideally we would reach a decision Otherwise, we will meet again next week to decide how to proceed Again ideas welcome One option is to write a short document to be made available for a small group to make a decision Still would like to finish this in time for the Upgrade SG 14th May 2013 Tile Input Options

32 BACKUP 14th May 2013 Tile Input Options

33 14th May 2013 Tile Input Options

34 14th May 2013 Tile Input Options

35 14th May 2013 Tile Input Options

36 26th April 2013 Tile Input Options

37 26th April 2013 Tile Input Options

38 26th April 2013 Tile Input Options

39 26th April 2013 Tile Input Options


Download ppt "Tile Input Options for Phase-1"

Similar presentations


Ads by Google