Download presentation
Presentation is loading. Please wait.
Published byMarvin Barton Modified over 6 years ago
1
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
SPARC BUDGET 2004/2005 L. Palumbo SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
2
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Total cost: k€ (1st Review Committee April 2003) 2003 2004 Total Laser RF Gun Linac Magnets 63.000 Vacuum 65.000 Diagn. e Contr. Total Excluding RF deflector and by-pass !!! SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
3
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
1st Review Committee, April 2003 MIUR ACCELERATOR 3.057 k€ INFN 2.819 k€ ST 132 k€ Un. TV 96 k€ 2.525 k€ hardware 294 k€ contracts 98 k€ hardware . 34 k€ group supp. ENEA 10 k€ Contracts and group support group support MIUR Funding approved: INFN Funding for Injector: € year 2003, € year 2004, € SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
4
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Funding 2003 OK SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
5
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
6
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Funding 2004 Miss. Int. Miss. Est. Consumo Inventar. Apparato Totale LNF 19 55 50 27 759 910 Mi 17 11 30 69 Roma1 3,5 1,5 8,5 Roma2 1 4,5 7 Salerno 2,5 2 5,5 43 76 65 57 1000 Missing 623 kEuro for apparatus in the budget 2004 !! SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
7
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Furthermore, we need: 300 kE for the by-pass 40 kE for completion of the RF Deflector 3) Travel and consumable since July 2004 SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
8
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
23,65 FTE Request 2005: SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
9
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
LNF, 4.7 FTE (R) FTE (T) = 14.6 FTE SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
10
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
100 SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
11
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Milano FTE SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
12
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
ROMA1, FTE (R) FTE (T) = 3.2 FTE SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
13
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
ROMA2 , FTE SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
14
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Salerno, FTE No significant contribution so far from the Salerno group SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
15
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
The Lecce group needs the following financial support: 1) Travels: 5,000 Euros per year: conferences, exchange visits. 2) 15,000 Euros per year for consumables: laser gases, o-rings, targets, substrates, heating belts; 3) Durable equipments: ionic pump 150 l/s (5,500 Euros) and a linear gate valve (3,000 Euros); SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
16
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
COMMENTS - Uncertainty of INFN funding for 2004. - Full funding of the project necessary in 2005 - Urges that RC reports INFN board about the SPARC status and financial needs. SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
17
Collaborations and UE programs
MOU DESY BNL UE PITZ SPARC UCLA MOU UE EUROFEL MOU SLAC SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
18
EUROFEL Collaboration
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
19
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Status : Negotiation SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
20
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
21
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
MIUR approval of funding in June 2004 First year 1/3 of the budget , 3.3 MEur SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
22
Sparc Injector + Dafne Linac for a 10 nm SASE FEL source at LNF
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
23
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
E [GeV] 1 Dg/g [%] 0.1 I [kA] 2 lu [cm] 3 K 1.762 Gap [mm] 11 SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
24
SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
CONCLUSIONS - The SPARC project is entering, on schedule, the installation phase. - Collaboration with UE and USA major laboratories/Univ. - Access to UE research funding programs. - Perspectives of a further development with SPARX SPARC Review Committee L. Palumbo -RomaTV-Oct.04.04
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.