SPS EYETS 2016/2017 Planning meeting (No.11) 18/01/17

Similar presentations


Presentation on theme: "SPS EYETS 2016/2017 Planning meeting (No.11) 18/01/17"— Presentation transcript:

1 SPS EYETS 2016/2017 Planning meeting (No.11) 18/01/17
David Mcfarlane EN-ACE D. Mcfarlane

2 Extended YETS 2016-2017 Reference time :
13 Weeks from Beam off until we close the SPS (12th December until the 24th March) EDMS: EN-ACE D. Mcfarlane

3 Key dates Beam off at 06:00 on Monday the 12th December
Access into BA7, TI2, TAG41, TAG42 & TI8: Monday the 12th December until Friday the 24th March 2017. 13 weeks of access. Access into BA3,4,5 & 6: Thursday the 15th December until Friday the 24th March 2017. 12.4 weeks of access. XMAS holidays: Thursday the 22nd December to Wednesday the 4th January inclusive Access into BA1 & BA2: Thursday the 5th January until Friday the 24th March 2017. 11.4 weeks of access. 4 weeks foreseen for EPC tests and cold-checkout by OP. SPS will take beam from the PS on Monday the 24th April 2017, followed by 1 week for beam setup. SPS ready to give beam to the LHC on Monday the 1st May 2017! EN/ACE/OSS BE/OP EN-ACE D. Mcfarlane

4 SPS Water Availability
Location De-min Circuit stop date Primary Water Off De-min Circuit start date Comments BA1 20/12/16 09-13/01/17 27/02/17 (Main Magnet & Power supplies for Kickers) Remaining circuit 13/03/17 BA2 14/12/16 (end) 06-10/02/17 20/02/17 Available for users from 06/03/17 BA3 19/12/16 27/02-03/03/17 (inc BEQ2 & BEQ3) 13/03/17 BB3 16-20/01/17 (except RF Skid) BA4 15/12/16 (end) 09-13/01/17 (Coldex) 17/02/17 (Main Magnet & Power supplies for Kickers) Remaining circuits 13/03/17 BA5 16/12/16 (end) 16-20/01/17 BA6 14/12/16(end) 16/12/16 – 16/01/17 (SF1) 27/02/17 Available for users from 13/03/17 BA7 12/12/17 EN-ACE D. Mcfarlane

5 Test AUG/ Access Tests (Access will be blocked)
Location AUG test Access tests Global test access safety system SPS Auto Transfer Test 4th & 5th February 16th December (15:00 to 17:00) 23rd March (chain 1) 24th March (Chain 2,3,4,5) BA1 13th February 27th January (PM) BA2 15th February 23rd January (PM) BA3 16th February 24th January (AM) BA4 ECX4 TAG42 TAG41 28th February 24th January (PM) 25th January (AM) 25th January (PM) 3rd February (PM) BA5 ECX5/ECA5 1st March 26th January (AM) 26th January (PM) BA6 20th January 27th January (AM) BA7 TT61 10th January 23rd January (AM) 30th January (AM) BA80 4th April 3rd February (AM) 13th March (1 day) “Test interverrouillage ventilation”

6 ENNC2017-003 - ELECTRICITE - SPS - ZONE 16 - BA6 - le 20. 01
ENNC ELECTRICITE - SPS - ZONE 16 - BA6 - le de 7h00 à 20h00 Veuillez prendre connaissance de la note de coupure « ELECTRICITE - SPS - ZONE 16 – BA6 – Réseaux Stable, Pulsé et Onduleur – Tests annuels des Arrêts d’Urgence Généraux (AUG) » prévue le vendredi 20 janvier 2017 de 7h00 à 20h00 EN-ACE D. Mcfarlane

7 ENNC2017-010 - ELECTRICITE - SPS - ZONE 13 - BB3 - BAT. 905 - le 24.01.2017 de 8h00 à 12h00
Veuillez prendre connaissance de la note de coupure « ELECTRICITE - SPS - ZONE 13 – BB3 – Bâtiment 905 – Dépose tableau EBD651/B3 » prévue le mardi 24 janvier 2017 de 8h00 à 12h00 EN-ACE D. Mcfarlane

8 Message to all users of UPS network in the BA3.
Vendredi dernier à 19h20 nous avons eu un problème sur le réseau 230 V ondulé du BA3 qui alimente l’armoire EOD /A3 (ensemble du hall BA3) . Apres investigation il apparait que l’UPS EBS23/A3 qui fournit le réseau ondulé est endommagé et doit être consigné. Afin d’éviter des coupures sur le tableau ondulé si l’UPS viendrait a retomber en panne, il est préférable de réalimenter sans coupure le tableau ondule sur une alimentation depuis le réseau normal CERN. En cas de coupure du réseau CERN France, le système auto transfert réalimentera le CERN depuis la suisse (environ 30s). PS : Cet UPS devant être remplacé dans le cadre de la rénovation du BA3 pendant le EYETS, dès que le nouvel UPS sera en place et mis en service nous rebasculerons les nouvelles armoires sur le nouveau réseau ondulé. EN-ACE D. Mcfarlane

9 Access restrictions to areas of the SPS
Zone Dates of restricted access Comments TI2 (LHC side) 10th February to 13th March LHC cool down in sector 1-2 TT20 6th March onwards EPC tests in TT20 TAG41/TAG42 1st February to 17th March AWAKE area will be closed TI8/TJ8 Not possible to access due to Laser tests in the AWAKE area.* *UPDATE! News from the AWAKE coordination: Go on with the activity related to cabling and fibre Optics for SPS, passing through AWAKE. (TAG41, 42) When there will be laser test, the date will be communicate to you and cabling team, and on that date the cabling will be interrupted; it will be only some days, but the laser team cannot define any specific date for the moment. EN-ACE D. Mcfarlane

10 EN-ACE D. Mcfarlane

11 Lift & Monte-charge Maintenance January
EN-ACE D. Mcfarlane

12 Consignations It is the responsibility of the Equipment owner to consign any equipment that they will be working on. Please ensure that The coordination team has a copy of all main consignations of the SPS. Do not assume something is consigned. Check first. EN-ACE D. Mcfarlane

13 All people who must enter in ECA5 will access by BA5.
Access into ECA5 While the shielding wall separating ECX5 and ECA5 is removed: All people who must enter in ECA5 will access by BA5. 12th December until 15th March. In order to keep the patrol and the integrity of the area safe, the lift in ECA5 should not be used during this period, only for evacuation. By accessing through BA5, we can guarantee that people are registered and they have their SPS safety courses. A security panel with a chain will be installed at the bottom of the lift : "Do not use the lift, only for evacuation" by the TSO (Franck Bais) If one of the 3 ECA5 doors at the top of the cavern is forced, the CSA will re-arm it at the end of the day. EN-ACE D. Mcfarlane

14 Magnet change Campaign
Position ordre Type aimant # série Action N° série Circuit ED à purger Secteur vide Date replacement 60150 1 MBB MB 267 Remplacement MBB 82 Main magnet 6- 610 9.01 61370 2 MBA MA 191 MBA 97 621 10.01 51470 3 MB 15 MBB 337 Main magnet 5- 520 41390 4 MA 247 MBA 301 Main magnet 4- 410 11.01 21270 5 MB 152 MBB 85 Main magnet 2- 210 22410 6 QF Q 130 QM 186 Main magnet 2+ 260 12.01 23310 7 QD Q 42 QM 220 Comments from Vacuum: 51470 – leak tested; 60150 – leak tested; 61370 – leak tested;  We will move in the afternoon to 420, then to BA2 is that is OK with Patrick! Comments from Survey: The and the are done as well, the is about to finish and the will follow this afternoon, tomorrow morning at the latest Comments from MSC: Re-brazing of the magnets should be completed by early next week! EN-ACE D. Mcfarlane

15 IMPACT Statistics (EYETS-SPS-2016/2017)
Number of IMPACTS “Waiting for Approval”: 38 Number of IMPACTS “in progress”: 146 Number of IMPACTS “approved”: 84 Number of IMPACTs “Late”: 55 Number of IMPACTs “Closed” or Finished”: 77 EN-ACE D. Mcfarlane

16 Please fill out your IMPACTs correctly!!!!!
Correct intervention period: DO NOT LEAVE IT BLANK!!!!!!! (EYETS-SPS-2016/2017) Do not leave proposed schedule Blank!!!! I am not psychic!!! If you clone an IMPACT: Check the dates are correct Check the location is correct Check the description is correct (not just the title) Basically, CHECK EVERYTHING!!!! If you have already completed your IMPACT them please check that the dates in IMPACT match that of your planning and are also correct in the master schedule planning. If they are not then please contact me so that we can rectify the problem. WHEN YOU HAVE COMPLETED YOU WORKS DO NOT FORGET TO CLOSE YOUR IMPACT!!!!!!! EN-ACE D. Mcfarlane

17 Don’t forget to add Vacuum to your IMPACT if you need them.
Supervisor: Chiara Pasquino e-group: te-vsc-ivm-LS1 40-30: Alain Grimaud 40-30: Frederic Vial 40-30: Lindsay Morgan Fabre 40-30: Olivier Pangolin EN-ACE D. Mcfarlane

18 Please fill out your IMPACTs correctly!!!!!
Correct intervention period: DO NOT LEAVE IT BLANK!!!!!!! (EYETS-SPS-2016/2017) Do not leave proposed schedule Blank!!!! I am not psychic!!! If you clone an IMPACT: Check the dates are correct Check the location is correct Check the description is correct (not just the title) Basically, CHECK EVERYTHING!!!! If you have already completed your IMPACT them please check that the dates in IMPACT match that of your planning and are also correct in the master schedule planning. If they are not then please contact me so that we can rectify the problem. WHEN YOU HAVE COMPLETED YOU WORKS DO NOT FORGET TO CLOSE YOUR IMPACT!!!!!!! EN-ACE D. Mcfarlane

19 Don’t forget to add Vacuum to your IMPACT if you need them.
Supervisor: Chiara Pasquino e-group: te-vsc-ivm-LS1 40-30: Alain Grimaud 40-30: Frederic Vial 40-30: Lindsay Morgan Fabre 40-30: Olivier Pangolin EN-ACE D. Mcfarlane

20 PLANNING EN-ACE D. Mcfarlane

21 SRRs and ECRs for the SPS
SPS planning and coordination meeting for EYETS 2016/2017 SRRs and ECRs for the SPS Sonia Bartolomé Jiménez EN-ACE-CL – 11th January 2017

22 SRRs and ECRs: reminder
All changes to the machine that will impact the beam shall be documented by SRRs/ECRs: SRR: Space Reservation Request (“light ECR”) ECR: Engineering Change Request Templates available on: To be sent to the SPS configuration manager: or

23 SPS ECRs for EYETS 2016/2017: status
LIU-SPS project EDMS Number Title Doc type EDMS Status Authors SPS-BCTW-EC-0001 SRR: New Fast BCT for SPS LSS5 (EYETS ) SRR Accepted (ECR) Lars Soby (BE/BI) SPS-V-EC-0005 Modification of the SPS sectorization in long vacuum sectors (arcs) ECR Chiara Pasquino (TE/VSC) SPS-VF-EC-0001 SPS flange impedance reduction in EYETS Jaime Perez Espinos (TE/VSC) SPS-BCTW-EC-0002 BCTW for LSS5 of the SPS ring (EYETS ) SPS-VC-EC-0001 SPS amorphous carbon coating in EYETS Mattias Van Gompel (TE/VSC) SPS-JHCAA-EC-0001 Construction of concrete support structure for new LIU beam dump in SPS ECX5 Approval Closed Richard Morton (SMB/SE) SPS-BLMD-EC-0001 Installation of a Beam Loss Diamond Detector in SPS LSS1 during EYETS Under Approval Lars Jensen (BE/BI)

24 SPS ECRs for EYETS 2016/2017: status
Non LIU-SPS project EDMS Number Title Doc type EDMS Status Authors SPS-LJ-EC-0004 Installation of a crab-cavity cryomodule and related infrastructure in LSS6 SRR Accepted (ECR) Giovanna Vandoni (BE/RF) ACC-RFB-EC-0001 New Table Format for Function Generator/Controllers (FGC) ECR Quentin King (TE/EPC) SPS-BSHV-EC-0002 Removal of the scraper BSHV from LSS5 of the SPS Edouard Grenier-Boley (EN/STI) SPS-LJ-EC-0006 HL-LHC Crab-cavity infrastructure in SPS: tunnel areas (EYETS ) SPS-TIDVG-EC-0001 Modifications to the TIDVG during 2016 Paula Rios Rodriguez (EN/STI) SPS-HJP-EC-0002 Installation of a protective barrier for SPS sectors 430 and 431 ground supports Roberto Salemme (TE/VSC) SPS-QRWPU-EC-0001 Installation of two Helium 2K Pumping Units in LSS6 SPS (BA6) New Giovanna Vandoni (BE/RF) SPS-Y-EC-0001 Radiation monitor interlocks at the SPS Under Approval Markus Widorski (HSE/RP) SPS-BLM-EC-0001 Pilot installation of Beam Loss Monitors along the COLDEX experiment SPS-B-EC-0004 Removal of obsolete BI equipment in LSS4 of the SPS Enrico Bravin (BE/BI)

25 External Visitors If you have any external personnel needing to access the SPS for visits before starting works then you need to read the following document: "Etapes à suivre pour organiser des visites professionnelles dans les installations faisceaux" by CHRISTELLE GAIGNANT Link: EN-ACE D. Mcfarlane

26 Access rights and safety equipment
EVERYONE who enters the SPS MUST have the following: Completed the correct courses. (sir.cern.ch) CERN Safety Introduction. Electrical Safety Awareness. (19 choices) Self Rescue Mask Training. (4 choices) CERN – Beam Facilities. SPS – Machine. The correct access authorisation (via EDH). CHECK YOUR ACCESS RIGHTS HAVE NOT EXPIRED!!!! Zone Code “SPS” for access into the SPS Zone Code “NA_TARG” for access into BA80 Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areas Zone Code “SPS-KN-000” for “Autorisation conduite RTL” Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns) Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. (All contractors must have an additional company passive dosimetre!!) Helmet plus Light. A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Please note that personnel are not allowed to work in the tunnel alone!! EN-ACE D. Mcfarlane

27 Important Contacts Useful Contact Numbers SPS Coordination Team
David MCFARLANE Franck BAIS – Aurelio Berjillos BARRANCO Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Kurt Weiss (BA7) EROS Engineering Referent for Operational Safety Emmanuel Paulat – John Etheridge EN-ACE D. Mcfarlane

28 Round Table (1) Group Contact Persons Comments EN/EL EN/CV EN/STI
Guillaume Gros Denis Ribiollet Jeremy Blanc EN/CV Bill Bannister (Water) Vivien Koutcheroff (Ventilation) EN/STI Jerome Lendaro Simone Montesano TE/MSC Jeremie Bauche Pascal Catherine TE/EPC Karsten Kahle (High power) Gilles Le Godec (Medium power) TE/VSC Jose A. Ferreira Anthony Harrison Chiara Pasquino TE/ABT Francesco Castronuovo (Kickers) Cedric Baud (Septas) BE/RF Eric Montesinos Christophe Renaud Gino Cipolla BE/BI Raymond Veness Morad Hamani BE/CO Magnus Bjork IT/CS Maryse Da Costa EN-ACE D. Mcfarlane

29 Round Table (2) Group Contact Persons Comments BE/ICS HSE/RP EN/ACE
Didier Vaxelaire (Access) Denis Raffourt (Fire detection) HSE/RP Christophe Tromel Angelito Herve EN/ACE Patrick Bestmann (Survey) Sonia Bartolomé (Integration) Fred Galleazzi (Intergration) Emmanuel Paulat (Safety) EN/HE Patrick Vallet (Transport) Nicolas Perez (Lifts) BE/OP James Ridewood Stephane Cettour Cave SMB/SE Alejandro Martinez Selles Crab Cavity Giovanna Vandoni EN-ACE D. Mcfarlane

30 A.O.B. EN-ACE D. Mcfarlane

31 Useful websites Link to SPS planning meetings on INDICO
Link to the SPS planning Roadmap: Schedule beyond LS1 Next meeting 25/01/2017 EN-ACE D. Mcfarlane