National Hydrology Project

Similar presentations


Presentation on theme: "National Hydrology Project"— Presentation transcript:

1 National Hydrology Project
NHP National Hydrology Project Ground Water CHHATTISGARH

2 Details of SPMU NPMU for Chhattisgarh is constituted vide, Govt. Of Chhattisgarh WRD Mantralaya Mahanadi Bavan Naya RAIPUR, NO.4613/ F-105/31/S-2/HP III/01/2015 Naya Raipur ,Dtd.03/11/2016 1 Project Coordinator Shri Ganesh Shankar Mishra Secretary, Government of Chhattisgarh Water Resources Department,Mahanadi Bhawan,Naya Raipur Chhattisgarh. 2 Nodal Officer Shri H.R. Kutare Engineer – in – Chief Water Resources Department Raipur Chhattisgarh. 3 Chief Engineer Shir Jayant Pawar Chief Engineer , Mahanadi Godawari Basin, Water Resources Department, Raipur Chhattisgarh 4 Superntending Engineer Shri S.K. Awadhiya Superntending Engineer, Water Resources & Ground Water Survey Circle Raipur Chhattisgarh 5 Sr. Water Management Expert Shri R.K. Sharma Executive Engineer, O/o Chief Engineer, Mahanadi Project Raipur Chhattisgarh 6 Procurement Expert Shri D.K. Sonkusale Executive Engineer, O/o Superntending Engineer, Water Resources & Ground Water Survey Circle Raipur Chhattisgarh 7 Geo-hydrologist Shri S.M. Sendiman Senior Geohydrologist, O/o Superntending Engineer, Water Resources & Ground Water Survey Circle Raipur Chhattisgarh 8 MIS Expert Shri J.N. Vishwakarma Assistant Engineer, O/o Deputy Director, Hydrometeorology Divison No. 04 Raipur Chhattisgarh 9 Hydrologist Shri V.K. Sonwani Assistant Engineer, O/o Superntending Engineer, Water Resources & Ground Water Survey Circle Raipur Chhattisgarh

3 Fund Received & Expenditure
Year Fund Received (In lakhs) Expenditure till date 10.85 - 92.00 3.95 Total 102.85

4 Major Procurement item in PIP
Item Code Item Amount (In lakhs) A1.2.01 Procurement of DWLR Telemetry for 450 New & 40 HP-II Piezometer 857.50 A1.2.03 Construction of 450 piezometers with protection work 495.00 Total

5 Major Procurement item in AWP 2016-17 & their Status
Item Code Item Amount (In Rs.) Status Nil

6 Major Procurement item in AWP 2017-18 & their Status
Item Code Item Amount (In Rs.) Status A1.2.03 Medium Piezometers + Protection work 165.00 BID Document sent on Dated 12/04/2017 & Reviewed on Dated 20/07/2017 by NPMU with remark that “Resubmit Bid Document after finalizations of monitoring network by sub committee constituted to finalize the Ground Water Monitoring Network”.

7 Physical Progress Completed PROCUREMENT OF IT EQUIPEMENT
1 No. Colour Printer 10 No. Printers A4 Size B/W 1 No. Digital Copier Multifunctional 1 No. Tablet Computer.

8 Physical Progress Proposed
Construction of Piezometer with Protection work Procurement of equipments 2 AC & 1 Refrigerator Procurement of online UPS 15 K Y A 1No Purchase of Vehicle 1 No.

9 Status of Bid Document Bid document of 450 Piezometer was submitted on dated 12/04/2017 . Document reviewed on dated 20/07/2017 by NPMU with remark that “resubmit bid document after finalization of monitoring network by sub committee constituted to finalize the Ground Water Monitoring Network”.

10 Status of various studies / PDS etc.
4 No. PDS proposed listed as below 1. Urban Hydrology and Ground Water Quality in and around Raipur aggonlomerate. 2. Ground Water Quality Assessment with special reference to Sulphate contamination in Bemetara District and suggesting ameliorative measures 3. Aquifer characterization of in and around Bilapur urban area. 4. Ground Water development and management in Pussore block area (Issue and Challenges) Request for Consent has been sent to NIH Roorkee for collaboration of above PDS. Out of 4, one PDS has been taken up with NIH Roorkee . Rest of 3 is under consideration with NIH Roorkee

11 Status of Hydromet Station (Both GW & SW), Reconciliation with state, CGWB, CWC. IMD etc.
Scheduled Meeting for “finalization of Ground Water Network Monitoring station Under NHP ” on 27/07/2017 at Ahmadabad was postponed due to heavy rain. Awaited for revised schedule of meeting of sub committee for finalization of GW Monitoring site.

12 Status Public Finance Management System (PFMS)
Support and Training is required for state staff for PFMS.

13 Any other issues E-procurement system for state is still not finalised . Insurance of DWLR TELEMETRY field equipments is essential for safety. So this may be taken in to consideration during finalization of Bid document.

14 Way forward

15 Thank You