Presentation is loading. Please wait.

Presentation is loading. Please wait.

Contracting Officer Podcast Slides

Similar presentations


Presentation on theme: "Contracting Officer Podcast Slides"— Presentation transcript:

1 Contracting Officer Podcast Slides
Knowledge & Insights From Contracting Officers

2 What is a Letter Contract?
Episode 046 What is a Letter Contract? Original Air Date: September 27, 2015 Hosts: Kevin Jans & Paul Schauer

3 Formatting notes Hyperlinks: Blue font indicates hyperlinks – presentation must be in ‘Slide Show’ mode to activate the link Red bold font indicates a point of emphasis Green bold font indicates CO’s personal comment or perspective

4 Introduction Purpose of this podcast: To examine and discuss Letter Contracts This is a way for Government to get work started quickly, before agreeing to every detail of the contract Letter contracts are used when: In Government’s interest to start work immediately, AND Negotiating a definitive contract is not possible in sufficient time to meet the requirement

5 Introduction Should be as complete and definite as possible under the circumstances Factors: Sole-source negotiation situation When based on price competition, must include a ceiling Performance needs to start NOW!

6 When do Letter Contracts happen?
Acquisition Time Zones (from Podcast Episode 003) Requirements Zone Market Research Zone RFP Zone Source Selection Zone (or sole source) These interactions occur throughout the entire Pre-Award phase of the process

7 Letter Contract – Definition
FAR – A letter contract is a written preliminary contractual instrument that authorizes the contractor to begin immediately manufacturing supplies or performing services Sometimes called an undefinitized contract action (UCA)

8 Three “Shall Nots…” Letter contracts SHALL NOT:
Commit the Government in excess of funds available at the time the letter contract is executed Be entered into without competition when it is required (FAR Part 6) Justification & Approvals (J&As) and letter contracts go hand-in-hand Be amended to new add requirements unless inseparable from the existing letter contract

9 More Factors of Letter Contracts
Must have a negotiated definitization schedule that includes: Proposal due date, pricing data requirements, make/buy, & subcontract plans Negotiation start date Target date for definitization (stick to this like it is a competitive source selection)

10 More Factors of Letter Contracts
Definitization Shall be the earliest practicable date Within 180 days or before 40% of the work is complete (whichever is first) Can be extended “in extreme cases”

11 More Factors of Letter Contracts
Government’s maximum liability SHALL NOT exceed 50% of the estimated cost of the definitive contract unless approved in advance (of reaching 50%) by whoever authorized the letter contract If price/fee agreement can’t be reached, CO can UNILATERALLY determine a reasonable cost or fee (with HCA approval)

12 Three Clauses One that describes the rules for starting work
One that says Government will only pay up to the max amount stated in the letter contract One that spells out the definitization schedule

13 Why are Letter Contracts important?
Government contracting process can take a long time A letter contract allows work to start NOW!

14 Why Should Government Care?
Might be your only chance of meeting a critical schedule requirement Sometimes perceived as giving away all negotiation power because you’re already committed to the contractor If allowed to linger, definitized price will be whatever the contractor spends Contractor ends up defining requirements because work is complete or past the point where changes are feasible Easy to be lax about schedule once work starts and urgency seems to be over

15 Why Should Government Care?
What usually happens: the CO moves on to other urgent work and ends up negotiating mostly actuals Not good for Government: no cost control Not good for Industry: Government assumes a low fee (performance is already or nearly complete, so there is negligible risk)

16 Why Should Industry Care?
Letter contracts are not a free-for-all Difficult to price when actuals and estimates are combined Difficult to complete work efficiently if requirements are a moving target

17 Summary Letter contracts cut through the red tape and get work started NOW Include a schedule for definitization that should be followed as if it is a source selection Limit the contractor’s expenditures to an established ceiling Requires communication and trust Be mindful of the user/acquisition office line User needs/requirements must be “officially” passed through the contracting officer Lots of room for confusion/complication/frustration if communications aren’t clear

18 Contact us We are on LinkedIn, Twitter and Facebook
We also started the Government Contracting Network Group on Facebook. Join us there! Send your topics to For Community support, contact Shelley Hall at


Download ppt "Contracting Officer Podcast Slides"

Similar presentations


Ads by Google