Why Production Control is Essential for Lean in Construction Gavin Pearce & Andy Fielding, Costain, Keith Bennett, Bourton Group
2
Purpose of this Presentation
To provide an overview of Collaborative Planning and Production Control (CP/PC) and the purpose To describe how CP/PC fits within the overall Lean Thinking framework To discuss how CP/PC provides the stepping stone for construction teams who may struggle with conventional Lean approaches
3
Factory Thinking and Production Thinking Strategy
Common theme is PC
4
Factory Thinking Flywheel
5
What is Production Control
LEAN
6
Collaborative Planning and Production Control
Maps out the process Identify value and non-value Removes waste Production Control Route cause analysis Tools and techniques Measure/monitor performance
7
CP & PC…What is the overall purpose?
To reduce the Design/construction time and effort on the ground whilst at the same time improving programme predictability, without compromising quality, safety or impact on customers
8
Three Key Features of Production Control
9
The step process to understanding Lean
Lean – DMAICT/six Sigma Lean – 5S, visual mgt Production Control Collaborative Planning
10
Elements of Production Control
11
5. Continually Attack Waste
Lean & Production Control interface Agreed Programme of work Resolve Issues to Recover Capture Performance 5. Continually Attack Waste Develop Collaborative plan Create Medium to short term Plan Create 1 week look ahead Review Daily Progress Continuous Improvement Easy Capture Issues Ease of Solution 1. Understand Customer Needs 2. Understand the Processes 3. Create Process Flow Collaborative Planning Complex Improvement Interventions Production Control 4. Pull Value
12
Integrating CP/PC/Lean
Easy Complex Develop Collaborative plan Create Medium to short term Plan Create 1 week look ahead Review Daily Progress Capture Issues Capture Performance Ease of Solution Improvement Interventions Continuous Improvement Resolve Issues to Recover Collaborative Planning Production Control Develop High Level plan Plan To Protect Ease Benefits Matrix Brain Storming Fishbone 5 Whys Pareto Spaghetti Chart Run Charts Bar Charts Visual Displays 3 C’s Visual Management 8 Wastes SIPOC Process Mapping Ease Benefits Make Ready Needs 3C’s 5whys Visual Display DMAIC Quad of Aims Key
13
An Example - Thames Tideway Project
Percent Planned Complete (PPC)
17
Highways sectors Lean and PC dashboard
18
How CP/PC has helped Costain implement Lean
A stepped approach Simple language easily understood A less threatening methodology Addresses the immediate and obvious problems quickly – the programme timescales/constraints Allows Continuous Improvement (Lean) to be introduced by stealth
19
Questions?