The East Link Project A first step towards a new generation of Swedish railway mainlines Johan Sundin Commercial Director.

Similar presentations


Presentation on theme: "The East Link Project A first step towards a new generation of Swedish railway mainlines Johan Sundin Commercial Director."— Presentation transcript:

1 The East Link Project A first step towards a new generation of Swedish railway mainlines Johan Sundin Commercial Director

2

3 The East Link Project Scope
Estimated 55 billion SEK (approx. € 5,5 billion), in 2015 value Approx. 150 km of civil works for double tracks Approx. 30 tunnels (100 – 6000 m, total length 25 km) Approx. 200 bridges (total length 10 km) Slab track, catenary, signalling system (ERTMS), tele-communications systems Design assignments

4 The East Link Project General Time Schedule 2028
Completion and Inauguration Design and land acquisition Procurement process Preparatory/ enabling works Major Construction

5 The East Link Project Challenges ”Mega-project” - Work methodology
- Resources/competence New technology - Aerodynamics in tunnels - Slab track - Noise protection

6 The East Link Project Challenges Sustainability Economy Ecology
Social responsibility * Employment requirements *

7 Th East Link Project Learning from others
We have met with a lot of foreign colleagues and suppliers regarding - Project management Technology Contract forms Procurement

8 The East Link Project Strategy documents

9 The East Link Project Strategy for Good Competition
Continuous dialogue with the suppliers. Fair balance of risks between Buyer and Supplier. Transparent and calculable tender documents to reduce the suppliers´ risk-taking. Reduce barriers to entry for foreign suppliers.

10 The East Link Project Strategy for Innovation
Address the contractors' skills and experience with regard to technical solutions, methods of production and logistics solutions. Describe functions rather than technical solutions in the tender documents. Design shall allow a large degree of freedom for coming Contractors and for Design-Build contracts. Bonus for innovations.

11 The East Link Project Strategy for packaging of contracts
Enabling Works Separate contracts for respectively Demolition Temporary roads Site compounds Utility diversions

12 The East Link Project Strategy for packaging of contracts Civil Works
A small number of very big contracts (> 3 miljarder SEK) All civil works in a certain area included in the same contract Design-build contracts to a great extent Active choices regarding business form

13 The East Link Project Strategy for packaging of contracts
Railway Works Separate contracts for respectively Power supply Catenary Signalling Telecommunication

14 The East Link Project Main Contracts, Civil Works Contract Length
Magnitude Type of contract Economy Gerstaberg 2 km Embankments, bridges, tracks and EST Performance Fixed price with unit prices Vagnhärad 23 km Embankments, tunnels, bridges and tracks Design-Build Fixed price with unit prices for tunnels. Skavsta 35 km Ålberga 22 km Embankments, bridges and tracks Fixed price Kolmården 15 km EST = catenary, power supply, signalling, telecommunications

15 The East Link Project Main Contracts, Civil Works Contract Length
Magnitude Type of contract Economy Norrköping central 6 km Embankments, bridges, tracks and EST Performance Fixed price with unit prices Norrköping tunnel Tunnel and track Kardonbanan 7 km Embankments and bridges Norsholm 32 km Embankments, bridges and tracks Design-Build Fixed price Linköping 5 km Embankments, tunnels, bridges and tracks Not yet determined

16 The East Link Project Main Contracts, Railway Works Contract Length
Magnitude Type of contract Economy Signalling and power Entire East Link Signalling and power supply Performance Fixed price with unit prices Catenary/OHLE Telecom/IT Telecom- and IT Nyköping bibana 21 km Embankments, tunnels, bridges and EST Kardonbanan BEST 7 km Tracks and EST Norrköpings new freight depot 5 km Embankments, tracks and EST  Fixed price EST = catenary, power supply, signalling telecommunications

17 The East Link Project Lots of opportunities for local businesses
Our contractors will need Personell (a lot!) both white and blue collar Subcontractors; transport, excavation, installation Material; concrete, steel, timber Accomodation/food Equipment, vehicles, tools and other supplies Advisors; legal, trade unions, tax regulations, site management, enivironment, work safety etc.

18 The East Link Project Some hints Start looking for partners
Be very thorough when preparing bids Hire people with language skills Useful contacts Business Sweden ESIC Embassies

19 www.trafikverket.se/eastlinkproject Internet Twitter Facebook E-mail