1
Automatic Identification Technology IV Contract W91QUZ-09-D-0044
Project Progress Review (PPR) #7 24 August 2010
2
Agenda Status of current technological substitutions and additions;
Status of configuration and risk management activities; Status of Task Orders, Delivery Orders and purchase card orders, Actions under warranty and maintenance; Significant trends (quantities by CLIN, component reliability safety issues, problems, and recommended solutions); Minutes from the previous PPR; Activities determined to be of importance to the Government, such as unanticipated problems, and high visibility issues identified by the Government; Status of significant program events; Customer feedback; Agencies and organizations contacted and initiatives with each; Reason for delinquent Task Orders, Delivery Orders, and purchase card orders.
3
Intermec AIT-IV Program Team
Tom Glen Director, Federal Sales Public Sector Trenita Nowlin Sr. Admin. Assistant (Contractor) Sean Langham Mgr, SE Team Vacant Sr. Mgr, Bus. Development Larry Huseby Director, Bus. Development Ron Payne Legal Counsel/Contracts Regina Keitt Program Manager AIT IV Vacant Public Sector Marketing Communications Dave Boppell Systems Engineer – Navy & MC Pete Rouse Channel Business Mgr Federal Sector Paul Dembeck Account Manager HHS & Civilian Agencies Mike McNamara Mgr. of Professional Services Global Operations Darin Delaney Systems Engineer – Army Don Green Account Manager Navy, /Marines Ken Taylor Project Manager Professional Services Dennis Morgan Project Manager Hardware Orders ID/IQ means there are no guarantees that we will sell anything. This is a hunting license. Only difference from AIT-III: multi-award Sam Matchey Systems Engineer – Civilian Agencies Lars Hohmann Account Manager Civilian Agencies Ron Teeters Project Manager Professional Services Shannon Landis Program Manager Technical Engr. Services Dave Stone Systems Engineer – USPS, DLA, USAF Dave Jones Account Manager US Air Force Paul Marks Project Manager Professional Services George Moss Account Manager US Army
4
Intermec’s Primary POCs for AIT IV
5
Contract Change Proposals Status
CCP Description Date Submitted Status AIN 010 Updates Seagull Scientific BarTender Software CLIN 0031DA 8/17/2010 Pending Gov Review AIN 009 Change PN for DM 7500 & Removes PW Supply off CLIN 0005 AA 8/11/2010 AIN 008 Adds Configuration number to HHT w/ USB SNAP-ON CAC Substitution 8/18/2010 AIN 007 PN Change CK3 Handle 5/18/2010 Awarded 7 June 2010 P00008 AIN 006 Substitute HHT for BT enabled HHT w/ user Defined CAC reader 3/3/2010 Jun P00007 AIN 005 Add BT HHTs Configurations 1/19/2010 Withdrawn 3/3/10 AIN 004 Modify Smalls Arms Room WSW Pricing 11/13/2009 Rejected 3/3/2010 Intermec revising AIN 003 Add Aruba 3600 11/10/2009 21 Jan 2010 P00004 AIN 002 Update PN CK3 Stylus AIN 001 Update CLIN LIST; correct PN; No change to price of configuration 08/24/2009 Rev 1 09/11/2009 Rev 2 10/29/2009 15 Dec 2009 P00003
6
Current Technological Substitutions & Additions
CCP AIN Revising -Modify Smalls Arms Room CCP AIN Adds configuration number for substitution HHT w/SNAP-ON CAC CCP AIN Substitutes PN for DM 7500 CLIN 005BA & Removes PW Supply off CLIN 0005 AA CCP AIN Updates Seagull Scientific BarTender Software PN CLIN 0031DA
7
Configuration & Risk Management
Installing CAC enablement SW on HHTs CAC enablement SW is downloadable from Intermec AIT IV website for interim Solutions We are working to pre-load the IA SW at time of manufacture Note: CAC enablement SW supports both BT and USB readers
8
Task, Delivery & Purchase Card Orders As of 31 July 2010
9
Task, Delivery & Purchase Card Orders, Cont As of 31 July 2010
There were 2 Army Task Orders to date totaling $355,999 (no change ) Total of Delivery Orders & Task Orders 23 July 2009 (contract start) through 31 July 2010 $2,737,847
10
Actions Under Warranty & Maintenance
CLIN 0015BA being replaced under Warranty Replacement NEMA enclosure received at Intermec Intermec performing QA
11
Significant Trends (Quantities by CLIN, component reliability safety issues, problems, and recommended solutions) CLIN 0015BA Aruba NEMA enclosure for AP Intermec has received modified enclosure from OEM and is performing QA; CLIN 0005BA DM 7500 Stand Parts estimated to OEM 2nd week in Sep Intermec QA 3rd week in Sep Projected to ship to customer end of Sep
12
Minutes from the previous PPR
Available on Intermec AIT website (
13
Activities Determined Importance to Government Such as unanticipated problems, and high visibility issues identified by the Government; Ordering Catalog review completed by Gov; Intermec has returned OC to Gov for review and acceptance
14
Significant Program Events
Air Force AIT/IUID Warfighter Conference Jul Military Logistics Summit 13 – 16 Sep
15
Customer Feedback
16
Agencies & Organizations Contacted & Initiatives
Intermec AIT IV Road Show Huntsville; ANAD; Norfolk NAS; RRAD;CCAD
17
Delinquent Task, Delivery, & Purchase Card Orders
DO 0002 all CLINS delivered except ; CLIN 0005 BA Scanner Stand - EDD shifted to Late Sep BA01 Zebra Printer OEM experiencing various parts shortages Zebra plans to keep an inventory of printers/ parts to support the AIT IV contract in Vernon Hills facility; EDD is EOM
18
Q&A