1 LAL Status - based on inputs from W. Kaabi and A. Stocchi - cf
LAL Status - based on inputs from W. Kaabi and A. Stocchi - cf. report on RF couplers by W. Kaabi on 23/4 Philip Bambade Laboratoire de l’Accélérateur Linéaire Université Paris 11, Orsay, France 9th XFEL ACB meeting - DESY April 2015

2 Status of power couplers at LAL:
2014 420 Couplers 360 Couplers + 24 couplers delivered on 2013  48 modules 2015

3 Status of power couplers at LAL:
After production stabilization: rejection rate: 8,7% Before production stabilization: rejection rate: 19,4% 2015 2014 Weekly received Coupler Calendar week

4 Reception and deliveries projections
1/2/2016 End of Thales-RI delivery 14/2/2016 2016 Coupler Number Christmas break 2015 Assuming typical average rejection rates  15-20% Calendar Week

5 Highlights at LAL - Acceleration of Thales-RI deliveries - Just started CPI production
Thales & RI has recently been delivering 8-10 couplers / week Accelerated production (incentive based, 10/week) for 2 months Rejection rate upon inspection presently < 10% 8 prototype CPI couplers, assembled and conditioned at SLAC, were sent to IRFU (transiting via LAL without inspection)  7 are mounted in XM26 4 first serial couplers received at LAL April 9  first RF processing attempt failed  a second baking was performed, RF conditioning to be done again next week  close communication and exchange LAL & DESY  CPI 4 next serial couplers expected to be delivered next week From May, expect regular delivery of 4 couplers / week until January 2016 TBC: expect rejection rate of  10% from CPI after initial learning process Hope to reach (need…) < 10% rejection rate from Thales & RI and CPI Extend accelerated production if needed ? Up to 14 couplers / week can be handled at LAL

6 Prospects for future involvement
RF couplers are a key component of the SCRF technology, but also a very highly specialized one Strengthen and develop our position in this “niche” in view of other coming similar projects in the community Diversify and extend our scope within XFEL: Contribution to module testing @ AMTF Commissioning and operation Beam instrumentation and physics  training & education  synergies with a possible ILC, and others…

7 Status of power couplers at LAL:

8 Status of power couplers at LAL: