TAS & TEPPC Update CCTA Assumptions

Similar presentations


Presentation on theme: "TAS & TEPPC Update CCTA Assumptions"— Presentation transcript:

1 TAS & TEPPC Update - 2026 CCTA Assumptions
Vijay Satyal - RPCG Liaison, Sr. Policy Analyst & Colby Johnson - Associate Engineer, SAP Western Electricity Coordinating Council

2 Inputs to the WECC Common Case
Resources (DWG/SWG) Process: Transmission Assumptions (RPCG) Loads (DWG) 2026 Common Case

3 Western Electricity Coordinating Council
CCTA process Transmission topology  C Case 2026 Regional Planning Groups  Key entities Mindful of RPGs’ complying with FERC Order 1000 and their criteria Not influenced by FERC Order 1000 criteria Cost-allocation is not the focus for selection RPCG – Ideal forum for such feedback Western Electricity Coordinating Council

4 Project Information Portal (PIP)
1 3 We have began an outreach/sent a letter to ask for project updates from present project contacts/sponsors 2 Western Electricity Coordinating Council

5 Edit existing projects through interactive map
*Paths shown are approximations and are provided to us in the form of Keyhole Markup Language (KML) by project sponsors/contacts Add new/edit projects through “list view”

6 CCTA Selection Process Review
2026 CCTA Inclusions All Prior CCTA Projects 2026 CCTA Criteria Under Constr. Not Under Constr. Newly-Submitted CCTA Projects 2026 CCTA Exclusions Western Electricity Coordinating Council

7 CCTA Not CCTA Criteria 1 No Yes Criteria 2 Criteria 3 Yes No No Yes
Regional Significance No Project A Project … Project Z Yes Criteria 2 Under Construction Criteria 3 Financial Indicators Yes No No Yes Criteria 4 Implement. Indicators Yes No Passed RPCG Screen Criteria 5 Dependency Check N/A No CCTA Yes Not CCTA Western Electricity Coordinating Council

8 5 criteria used for review
Criteria 1: Regional Significance Based on Voltage: 500 kV and above 200 kV or greater if “backbone”1 facility Criteria 2: Construction Status Is the project currently under construction? Criteria 3: Financial Indicators Financial questions added to project survey to indicate if the project has financial commitment Criteria 4: Implementation Status Indicators Environmental Impact Status (EIS – if required) questions added to survey Criteria 5: Project Dependency Is this project dependent upon another transmission project to be completed and used for its intended purpose? If so, did the dependent project pass the CCTA criteria? 1 Backbone transmissions are facilities that provide network connectivity, typically kV Western Electricity Coordinating Council

9 CCTA Process Demo: “Everett – Madison Transmission Project”
Similar table to be created for all potential transmission projects This is the type of table we’d create for all potential candidates Highlighted fields will be considered in CCTA criteria/flow Western Electricity Coordinating Council

10 Ballot Results Neutral votes not counted
In instance of a “tie”, this group to determine Western Electricity Coordinating Council

11 Western Electricity Coordinating Council
2024 CCTA Update Western Electricity Coordinating Council

12 Western Electricity Coordinating Council

13 Overall Feedback on Process
CCTA 2026 Report by mid- Feb’ 2016 General RPCG consensus – Effective forum to give WECC feedback Review CCTA process for future improvements Criterion 3 and 4 to be reviewed and/or refined in future planning cycles Definitions Thresholds 2 / 3 hour RPCG meeting prior to late Summer TEPPC meeting Western Electricity Coordinating Council

14 Western Electricity Coordinating Council
Acknowledgements RPCG membership – 7 month process. Gary DeShazo – Chair Jeff Hein – Vice Chair Colby Johnson and Jon Jensen – SAP team WECC – IT (Taylor A) and Business Services – Project Portal and 2026 CCTA voting survey Non-RPCG TAS-TEPPC members Western Electricity Coordinating Council

15 CCTA Team Contact Information Vijay Satyal – RPCG Liaison Colby Johnson – Assoc. Planning Engineer Western Electricity Coordinating Council