ILC-EDR Kick-off Meeting, Cryomodule and Cryogenics
ILC-EDR Kick-off Meeting Cryomodule and Cryogenics Organization and Charges Sept. 12, 2007 Akira Yamamoto ILC-EDR Kick-off Meeting, Cryomodule and Cryogenics Held at KEK, Sept , 2007
2
ILC Project Management as a proposal for the organization toward EDR
V ILC Project Management as a proposal for the organization toward EDR ILC Council (ILCSC) Funding Agencies and Institutions Global Design Effort Director’s Office Director: B. Barish Project Managers: M. Ross*, N. Walker, A. Yamamoto Board - Accelerator Advisary - RD subpanel - Design & Industr. subpanel. - .. Executive Committee Director, Regional Directors, Accelerator Experts, PMs Regional Leadership (by Reional Directors) - Funding and Authorization Technical Leadership (by Project Managers) - Engineering Design and R&D Asiay M. Nozaki US M. Harrison Europe B. Foster ML Tech. A. Yamamoto Global Sys. M. Ross Accel. Sys N. Walker P. M. Office M. Ross Many Tasks Instit. …. Institution Institution Institution Instit. ….
3
Project Management Structure (baseline)
Director’s Office - Director (B. Barish) - Project Managers (Ross (chief), Walker, Yamamoto) Executive Committee Board - Accelerator Advisary - RD subpanel - Design & Industr. Subpanel. - Change Control Board Regional Effort ML Technology (Yamamoto, Shidara, Kerby) Groups: Cavity Process (Lilje) -Cavity Prod/Integ (Hayano) Cryomodule(Ohuchi/Carter) Cryogenics (Peterson) HL-RF(Fukuda) ML Integ. (Adolphsen) Global Systems (Ross, ) Groups: Civil Controls Convent. Facil. Accelerator Systems (Walker ) Groups: e- source e+ source Damp. Ring BDS RTML Simulations Project Man. Office (Ross, ) Groups: System integration Eng. Manage - Cost and schedule XFEL liaison
4
Technical Responsibilities : (from RDR Chapter 7)
Technical responsibility Green indicates a commitment: institute will deliver MoUs facilitate connection: Project Management (authority and responsibility) and institutions (funding and resources). The ‘C’ coordinating role in a WP Each WP has one coordinator.
5
ILC Project Management and Sharing Responsibilities
Project Managers responsible for Leading the world-wide technical development effort efficiently and effectively Setting technical direction and executing the project toward realization of the ILC Day-to-day project execution and commucniation Regional Directors and Institutional Leaders responsible for Promoting, funding and authorizing the cooperation programs. Formality to start institutional activities, and periodical oversiting the technical progress,
6
Project Management Structure Area: Main Linac Technology (to be completed)
Regional/Intsitutional Effort: - Director-US: Mike Harrison - Director-EU: B. Foster - Director-AS: M. Nozaki Technical Effort (ML (SCRF) Technology): - Project Manager: A. Yamamoto - Associate Managers: T. Shidara, J. Kerby, * Group leader, ** Co-leader Regions Institute Institute Leaders Cavity (Process) L. Lilje* (Prod./Int.) H. Hayano* Cryomodule N. Ohuchi* H. Carter** Cryogenics T. Peterson* HLRF S. Fukuda* ML Integr. C. Adolphsen US Cornell Fermilab SLAC ANL TJNL H.Padamsee R. Kephart T.Raubenhaimer C.Adolphsen H.Carter T.Peterson R. Larsen EU DESY CERN Saclay Olsay INFN Spain R.Brinkman J. Delahaye O. Napoly A.Variola C. Pagani L.Lilje Parma Franco Pal. Tavian AS KEK Korea Inst. IHEP India Inst. K.Yokoya Noguchi, Saito Hayano Tsuchiya/ Ohuchi Hosoyama/Nakai Fukuda
7
Technical efforts to EDR
Complete the critical R&D as identified by the (R & D Board and) S0, S1, S2 task forces. Make our best effort to establish the base-line design unified, Technologies to be chosen and to be further established, and demonstrate engineering for pre-mass-production Seek some flexibilities for “plug-compatibilities”, for maximizing performance/cost (value-engineering) Learn industrialization in the XFEL project Obtain the maximum benefit from the realized project formally launched June, 2007 Learn real industrialization and accumurate mass production experience,
8
Getting Started on the EDR:
Re-organize collaboration Project management-based structure, For day-to-day activities, Definition, scope and possible resources Re-look (self-review) RDR & plan EDR EDR kick-off meetings as a starting point
9
2007/08 EDR Milestones Aug. – Korea ILCSC:
New EDR organization start, Aug. to Oct. – EDR Kick Off Meetings Oct – Fermilab ILC-GDE meeting EDR Work Packages to be discussed Jan. to Feb. 08 – EDR RD Meetings March 2008 – Tohoku (Japan) GDE Meeting
10
Agenda: Sept. 12 Wednesday 12 September 2007
09:00 Introductory talk -- toward EDR (15') B. Barish 09:15 Organization and Charges of Cryomodule and Cryogenics (10') A. Yamamoto 09:25 Definition of work area between groups (25') N. Ohuchi clarify the interface between the groups 09:50 Basic strategy of designing cryomodule (30') H. Hayano unified cryomodule design or compatible cryomodule design 10:20 Coffee break 10:35 Status report and work package plan of US (45') H. Carter review of RDR work, present situation and work package plan of US 11:20 Status report and work package plan of Asia (45') N. Ohuchi review of RDR work, present situation and work package plan of Asia (Japan) 12:05 Lunch 13:30 Type 4 cryomodule design work (45') D. Mitchell review of T4CM design and present activity 14:15 Construction experience of LHC dipole cryostats (1h00') V. Parma cryostat design principles, description of main cryostat components,industrial production of cryostat components, assembly of the cryostat at CERN, cryostat performance 15:15 Coffee break 15:30 Drawing up the work and R&D list for EDR (1h30') H. Carter/N. Ohuchi - making the list of working items from the WPs of three regions 17:00 Break (some small meeting discussions) 18:00 connection to PISA via Webex (1h30') Industrialization plan at XFEL : C. (scheduled time can be changed) Status report and work package plan of Europe : TBD
11
Wireless network info tsubaki c15c0a1200
12
Agenda: Sept. 13 Thursday 13 September 2007 09:00 Cost estimation of cryomodule for EDR (45') R. Stanek review of the cryomodule cost for RDR, and guide-line for EDR 09:45 Industrialization of cryomodule for EDR (45') R. Kephart 10:30 Coffee break 10:45 Review of the cryogenic system RDR work (45') T. Peterson 11:30 Work package plan of cryogenic system for EDR (45') T. Peterson including the overlap between cryomodule and cryogenic system designs 12:15 Lunch 13:30 Cryogenic experience from CERN LHC (1h00') L. J. Tavian construction and operation experience of the LHC cryogenic system, and preliminary results for measured system static heat loads. 14:30 Coffee break 14:45 Work sharing between three regions (2h00') All including vacuum pump system for beam line, BPM-Quad package, special cold gate valve, HOM absorber, vacuum break, aligmnent issue, transportation, installation
13
Agenda Sept. 14 Friday 14 September 2007
08:00 possible slot: connection to US via Webex (2h00') 10:00 Time line and mile stone of work package for EDR (30') R. Kephart 10:30 EDR writing issue (30') H. Carter/T.Peterson including items in EDR, writing share and start time of writing EDR 11:00->11:30 Making summary of the meeting : N. Ohuchi/T.Peterson 11:30 Summary of the meeting (30') N. Ohuchi/T.Peterson Closing Remark A. Yamamoto