1
eMENTHE – Developing Master’s level eLearnig Material in mental health
Steering group meeting Tampere University of Applied Sciences 7. –
2
EU & Coordinating Institution
Project period in grant agreement: – Project costs eligible only during this period Grant agreement is made between the coordinating institution (TAMK) and the EU EU transfers project funding to coordinator Note! Self-financing part is not paid Coordinator transfers project funding to project partners according to their share EU funds kept in 0% interest bank account (=not making profit for coordinator)
3
EU’s timetable for payments
In eMENTHE project, EU pays the grant in 3 parts 40% at the beginning of the project 40% after the progress report has been accepted 20% after the final report has been accepted Last part of the grant comes long after the end of the project TAMK follows EU’s timetable for payments: TAMK pays partner expenses ONLY when TAMK has received EU grant and only UP TO the EU grant
4
EU’s timetable for payments
Note! 70 % of the first pre-payment has to be used before sending a payment request for 2nd pre-payment! It is highly important for every partner to send the payment request´s to TAMK in time!
5
eMENTHE Budget Total budget: 365.481,00€
EU-grant maximum 75% of the eligible budget used, however maximum up to ,00€ Project consortium’s self-financing in total: ,00€
6
Deadlines for Requests of Payments
Invoices (requests of payment) must be sent in every 3 months periods: 1st RoP covered the expences that took place between 1st quarter 2014: , request by 8th April 2nd quarter 2014: 1.4. – , request by 8th July 3rd quarter: 2014: 1.7. – , request by 8th October 4th quarter 2014: – , request by 8th January 1st quarter 2015: , request by 8th April 2nd quarter 2015: , request by 8th July 3rd quarter 2015: , request by 8th October 4rd quarter 2015: , request by 8th January 1st quarter 2016: , request by 8th April 2nd quarter 2016: , request by 8th July 3rd quarter 2016: , request by 8th October