Presentation is loading. Please wait.

Presentation is loading. Please wait.

33KV PLUG-IN TERMINATION AT GAYATHI D6624 PROJECT

Similar presentations


Presentation on theme: "33KV PLUG-IN TERMINATION AT GAYATHI D6624 PROJECT"— Presentation transcript:

1 33KV PLUG-IN TERMINATION AT GAYATHI D6624 PROJECT
MANUFACTURE – PFISTERER ,SIZE – S3 FOR SIEMENS SWITCHGEAR

2 CABLE MARKING AS PER PFISTERER INSTRUCTION MANUAL

3 REMOVING OUTER JACKET & ARMOUR

4 PREPARING FOR REMOVING COPPER SCREEN

5 AFTER REMOVING OF COPPER SCREEN

6 REMOVING OF OUTER SHEATH ABOVE XLPE USING ROUND FILE

7 AFTER REMOVING OF OUTER SHEATH

8 REMOVING OF XLPE INSULATION FOR PLUG-IN CONNECTOR

9 INSTALLATION FOR COPPER MESH HOSE

10 INSTALLATION OF COTTON INSULATION TAPE BLOW THE COPPER MESH HOSE

11 SCREEN EARTH INSTALLATION

12 INSTALLATION OF SEMI CONDUCTOR TAPE

13 FINAL PREPARATION

14 APPLING FOR PFISTERER GREASE

15 INSTALLATION OF BELL FLANGE

16 INSTALLATION OF HV INSULATION PART & THRUST PIECE

17 INSTALLATION OF TENSION CONE

18 INSTALLATION OF CONTACT RING

19 CONTACT RING TIGHTING

20 READY FOR TERMINATION

21 TERMINATION AT SWITCHGEAR

22 INSTALLATION OF OUTER HEAT SHRINK TUBE

23 INSTALLATION OF OUTER HEAT SHRINK TUBE AFETR PLUG-IN