33KV PLUG-IN TERMINATION AT GAYATHI D6624 PROJECT
MANUFACTURE – PFISTERER ,SIZE – S3 FOR SIEMENS SWITCHGEAR
2
CABLE MARKING AS PER PFISTERER INSTRUCTION MANUAL
3
REMOVING OUTER JACKET & ARMOUR
4
PREPARING FOR REMOVING COPPER SCREEN
5
AFTER REMOVING OF COPPER SCREEN
6
REMOVING OF OUTER SHEATH ABOVE XLPE USING ROUND FILE
7
AFTER REMOVING OF OUTER SHEATH
8
REMOVING OF XLPE INSULATION FOR PLUG-IN CONNECTOR
9
INSTALLATION FOR COPPER MESH HOSE
10
INSTALLATION OF COTTON INSULATION TAPE BLOW THE COPPER MESH HOSE
11
SCREEN EARTH INSTALLATION
12
INSTALLATION OF SEMI CONDUCTOR TAPE
13
FINAL PREPARATION
14
APPLING FOR PFISTERER GREASE
15
INSTALLATION OF BELL FLANGE
16
INSTALLATION OF HV INSULATION PART & THRUST PIECE
17
INSTALLATION OF TENSION CONE
18
INSTALLATION OF CONTACT RING
19
CONTACT RING TIGHTING
20
READY FOR TERMINATION
21
TERMINATION AT SWITCHGEAR
22
INSTALLATION OF OUTER HEAT SHRINK TUBE
23
INSTALLATION OF OUTER HEAT SHRINK TUBE AFETR PLUG-IN
24
THANK YOU