PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
EN-CV Activities for YETS & LS2 PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting Serge Deleval EN-CV Gabor Petrika EN-CV Willy Van Den Broucke EN-CV
2
Maintenance YETS
3
Circuits Stop Restart Linac + Leir LEIR – LINAC 2 and 3 (Demi water) 20/12/2017 29/01/2018 LINAC 2 (Raw water) Running LINAC 3 (Raw water) 18/12/2017 19/02/2018 LINAC 4 ? Booster Booster / TT2 12/02/2018 Booster – chilled water (affecting PS 359 RF room) Compensator / bldg.242 PS PS – Central building Anneau 21/12/2017 PS – Main magnet POPS 19/12/2017 PS – Chilled water Thyristor cooling – PS rotating machine
4
Machine Circuits Stop Restart Isolde Cryo – Primary 14/12/2017 22/02/2018 BTY magnets cooling 4/12/2017 Hall (hall incl. Separator REX, EBIS, TRAP) HIE ISOLDE (HEBT lines + triplets REX + RF bldg. 199) Targets cooling Mixed water cooling (Ampli RF bldg REX cavities) East area 27/11/2017 19/03/2018 AD 21/12/2017 26/02/2018 09/01/2018 1/03/2018 AD Target CTF3 TBD nTOF Running
5
Works and projects
6
Scope: Progress report: 237 → 11.2017 (started 08.2017)
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Scope: New cooling towers; New cooling station (pumps, heat exchanges…); New electrical & control system; New instrumentation; Distribution network modifications Pressure rating upgrade; 361 Booster 141 Progress report: UR + WP (EDMS ) Preliminary P&ID P&ID Bdg D integration Bdg. 141 & Bdg. 237 3D Integration Engineering Specification Piping gallery 237 New Cooling Towers → (started ) → (started ) → 2018 Q1
7
Scope: New cooling towers (237); New chillers (361)
New cooling station (pumps, heat exchanges…); New electrical & control system; New instrumentation; CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Buffer tank 361 Booster Chillers 141 Piping gallery 237 New Cooling Towers
8
Progress report: Scope: UR + WP (EDMS …) Preliminary P&ID → 08.2017
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Scope: New AHUs; Filtration; New, separated smoke extraction system; New electrical & control system; New instrumentation; Existing air distribution network; Progress report: UR + WP (EDMS …) Preliminary P&ID P&ID 3D integration Engineering Specification → → → 2018 Q1 → 2018 Q2
9
Scope: BRF2 Progress report:
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Scope: New cooling branch for power converters (starts at BRF2) No simultaneous operation is possible ! (BRF2 and power converters in 1-203) Temporary installation BRF2 New piping Progress report: 3D integration proposal Power converters
10
Scope: Progress report: Heating system removal
(terminal units, pipes, valves) CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Progress report: Pre-VIC 3D integration Risk analysis Access / Machine protection WDP → → →
11
Scope: Progress report:
Dummy load magnets connections to the POPS cooling system CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Progress report: WP
12
PSB activities planning
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Ventilation commissioning YETS Cooling commissioning 141 ChilledW. commissioning
13
Scope: Works: Impact: Consolidation of both PS cooling plants.
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Scope: Consolidation of both PS cooling plants. Integrate LIU needs. Connect TT2 to the PS cooling plant. Cooling for new TT2 power converters in bldg Works: Create new cooling plant in Bldg. 355 Renovate 255 cooling towers. Replace and install new pipes in the PS. Connection to the 269. Impact: No water for Test with water circulating during January and February 2020. Works inside the PS tunnel, in Bldg. 355 and in front of Bldg. 255 Asbestos removal in the PS tunnel.
14
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion
15
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Scope: Consolidation of the Linac 3 ventilation. Lack of reliability, capacity and spare parts. Works: Replacement of the whole system Replacement of the false ceiling containing asbestos (Civil engineering works) Impact: No ventilation for several months. Suspended slab with reinforcement
16
YETS: Replacement of the PS chilled water control system.
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion YETS: Replacement of the PS chilled water control system. 4 wks of work in parallel with the maintenance but no possibility to restart before the 12th of February Decabling campaign for PS TT2: Identification of CV obsolete cables PS: BGI modification of the cooling. Connections to the chilled water circuit. Replacement of valves for magnets in TT2 Installation of a new motor for the Linac and Leir demineralised water cooling plant.
17
Area Title Instal. Remarks CV Projects Project overview PSB Cooling
PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Area Title Instal. Remarks Meyrin Replacement of the Siemens S5 cards in the cooling plants of Meyrin LS2 Cooling plant for Linac et LEIR, cooling plant (raw water for Linac 3, cooling plant for CTF3, … Replacement of 2 water cooled screw chillers (bldg. 2011) Impact on the air treatment of CTF3 Replacement of 1 air cooled screw chiller (bldg. 197) Impact on the air treatment of Isolde hall, HT room and old control room PS Consolidate the warm water network in the PS tunnel Strong impact in the accessibility in the PS. Project not really started Install a system to empty the demineralised cartridges in bdg 378 2018 Connect Linac4 to Booster transfer line Linac 4 cooling to stop and test to foresee. Install a demineralised water circuit for cable cooling the test bench in bdg 163 2018/2019 Consolidate the East Area Hall Consolidate the East Area Hall Cooling Consolidate the East Area Hall Ventilation Consolidate the East Area Hall Primary Zone Ventilation Consolidate the bld 251 cooling and ventilation in the frame of the East Area consolidation CV works for SMB during the East Area building consolidation Consolidate HVAC for the renovation of the EL station ME9 LS2
18
Area Title Instal. Remarks CV Projects Project overview PSB Cooling
PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Area Title Instal. Remarks Meyrin Consolidate the Meyrin (Bdg 200) compressed air station 2018 No compressed air cut. AD Consolidate the AD target ventilation system LS2 Consolidate the AD bdg 193 cooling tower and demi water cooling PS Consolidate the PS Complex chilled water piping - Phase II Not yet approved ISOLDE Consolidate el, instr, & control systems of the ventilation of ISOLDE Tunnel YETS 2021 Install the cooling system for the EL SVC MEQ 59 station
19
Conclusion: Huge amount of work for CV in the PS Complex during LS2
CV Projects Project overview PSB Cooling PSB Chilled water PSB Ventilation PSB – YETS POPS Cooling PSB activities planning PS Cooling Linac 3 Ventilation Other projets Others.. Conclusion Conclusion: Huge amount of work for CV in the PS Complex during LS2 Priority is given to the achievement of the projects. Needs of operation will be treated if possible. Please anticipate your request for works and operation needs Services will be interrupted for long period of time (even ventilation). All projects and works can not be done in parallel => some of them must be postponed to 2020 CV have to recuperate Bldg. 141 to comply with LS2 Booster planning.