US CMS Detector Project Overview DOE/NSF Lehman Review, May 8-10, 2001
Dan Green US CMS Project Manager DOE/NSF Lehman Review, May 8-10, 2001 DOE/NSF Review May 8-10, 2001
2
Outline Project Status - Financial Schedule Changes (V31)
FY98+99 Closeout, 1 year “rolling” closeout Schedule Changes (V31) Installation -and Commissioning Technical Progress DOE/NSF Review May 8-10, 2001
3
US CMS - DOE, NSF Profile US CMS balance between DOE and NSF funds is roughly correct. We have modified I&C planning to match the CMS V31 schedule. NSF ends in FY03. DOE/NSF Review May 8-10, 2001
4
US CMS Detector Project
No trends are evident. No “divergence”. DOE/NSF Review May 8-10, 2001
5
Financial Overview - I BCWS 84.0 AYM$ BCWP 74.1 Obligations 80.6
Paid Actuals Obligations/BCWS % BCWP/BCWS % Paid Actuals/BCWP % We are getting the funds out to groups and we are getting the jobs under contract. There is some lag in schedule/reporting and in invoicing. DOE/NSF Review May 8-10, 2001
6
% Complete at L2 The CP is ~ completed up to progress payments. ECAL, EMU and HCAL are > 50% complete, while Tridas and FPIX are only ~ 25% complete DOE/NSF Review May 8-10, 2001
7
CSC - Labor Experience Early experience on CSC assembly is
favorable. Now have ~ 35 of 148 CSC DOE/NSF Review May 8-10, 2001
8
HCAL - M&S Cost Experience
HB-1 pre-assembled at Felguera. Shipped to CERN . Megatiles will be inserted in bldg # 186. The mating of optics to absorber will begin at CERN in CY 2001. DOE/NSF Review May 8-10, 2001
9
HB OPTICS - Labor Experience
Labor experience for CSC and for HCAL optics has been good. This is the bulk of US CMS labor costs. M&S ~ OK, Labor ~ OK ==> worry about electronics (schedule) and installation (EDIA too). DOE/NSF Review May 8-10, 2001
10
Closeout of Completed Tasks
FY completed tasks have been closed. The ACWP can be compared to the BCWS for CV on these tasks. In future tasks with end dates more than one year ago which are reported complete will be closed. DOE/NSF Review May 8-10, 2001
11
Contingency Usage and Performance
We have 34 months of monthly reporting. CR can be followed at any level of detail needed. We need to watch contingency following the SiTrkr baselineing. DOE/NSF Review May 8-10, 2001
12
Financial Overview - II
TPC = Constant (AYM$) BAC Contingency = TPC - BAC ETC = BAC - BCWP BCWP/BAC % Contingency/ETC % We have a fixed total cost. We are 54 % complete and retain 45% contingency on the estimated cost to complete. DOE/NSF Review May 8-10, 2001
13
US CMS Contingency Use We started with 48.7 M$ in contingency. We have used 19.7 M$, retain 29.0 M$, and we are 54% complete. Of the increase, ~ 7 M$ is due to scope increases, so we have used ~12.7 M$ on better estimates of > BCWP = 74.1 M$ tasks (<17 %). DOE/NSF Review May 8-10, 2001
14
US CMS Revised ML1 DOE/NSF Review May 8-10, 2001
15
LHC - V31 Single beam in LHC 1/06 2 months LHC, then run 1 month
shutdown - complete CMS /06 start run at 10^33 for 10 fb /06 Planning for installation and commissioning uses V31 for scheduling and planning. Note that late B.O. in UX means increased US CMS costs. DOE/NSF Review May 8-10, 2001
16
Installation of CSC Test of CSC Installation fixture
Balance limits w/ or w/o chamber Fully balanced chamber can rotate to any angle Counterweight Test of CSC Installation fixture DOE/NSF Review May 8-10, 2001 W. Mason, F. Feyzi - UW/PSL
17
HCAL Critical Path - V31 DOE/NSF Review May 8-10, 2001
18
WBS 1 - Endcap Muon Final or next-to final Prototype Boards for all on-chamber electronics produced and tested. CSC CFEB ALCT LVDB DOE/NSF Review May 8-10, 2001
19
Off-Chamber Electronics
First Prototype Boards produced and tested (8.99) M P C B DM CLCT TMB VME Cont ro l DDU-99 DMB-99 CLCT-99 TMB-99 CCB-99 DOE/NSF Review May 8-10, 2001
20
Location of Peripheral Crates
YE2 walkway showing 600 sector of ME2 and VME crate DOE/NSF Review May 8-10, 2001
21
WBS 2 - HCAL Over 20,000 scintillator tiles built and measured
RMS of fibers = 4.4% RMS of tiles = 6.5% RMS of wire/coll = 1.2% RMS of average layer light yield = 4.6% Optical Production DOE/NSF Review May 8-10, 2001
22
HF - EDIA, FNAL -> RDMS
0.5 cm spacing, packing fraction, source tubes, edge chamfer design complete. Redesign was US scope increase. DOE/NSF Review May 8-10, 2001
23
HPD - Anti-Reflection Angular “acceptance” and numerical aperture.
Wavelength “acceptance” and photocathode response DOE/NSF Review May 8-10, 2001
24
QIE Status - OK Yarema group is on track with their schedule
Input Amplifiers/Splitters: design finished, layout done. Integrators: design finished, layout partially done. FADC: design finished, layout done Range comparators and ranging logic: not done Biasing network: not done State machine, timing: design being worked on now LVDS drivers, receivers: not done Other digital logic: not done Total design submitted - on track so far - minor slippage. Yarema group is on track with their schedule DOE/NSF Review May 8-10, 2001
25
WBS 3.1 Trigger TDR Finished and available as CERN/LHCC , CMS TDR 6.1 December 15, 2000 Met Level 1 Milestone for submission to LHCC by end of 2000. Approved by LHCC, March, 2001 DOE/NSF Review May 8-10, 2001
26
Calorimeter Trigger Status (U. Wisconsin)
Successful Prototyping Program Crate, 160 MHz Backplane & Clock Card Receiver & Electron Isolation Cards tested Adder ASIC tested & production finished 4 Gbit/sec Copper 20 m link system tested ASIC Prototypes Tested* Phase & Boundary Scan delivered Tested* Isolation & Sort delivered *Tested by Vitesse Testing Program Plans Next generation Backplane finished Next generation Receiver, Elect. Iso. Cards Next generation Copper Link New Vitesse Chip (72147216) Test delivered ASIC prototypes Simulation Program New ORCA4 results verify performance DOE/NSF Review May 8-10, 2001
27
Muon Trigger System Tests
Muon Port Card (Rice) Sector Receiver (UCLA) Data successfully sent from input of one MPC, through 100m of optical cables, to output of SR Sector Receiver Sector Processor (Florida) Data successfully sent from input of one SR, through custom backplane, into the SP Successfully sent data from three SRs connected to the SP to emulate an entire trigger sector Clock and Control Board prototype (Rice) Distributed clock & control signals w/ programmable delays Port Card Sector Receiver Sector Processor Successfully sent data from the input of two MPCs (representing ME2 and ME3), through one SR, and reconstructed tracks correctly in the SP Complete chain test using simulated data from ORCA4 DOE/NSF Review May 8-10, 2001
28
WBS 3.2 DAQ The DAQ effort continues in an R&D phase - watching and evaluating commercial developments. The ML1 for DAQ is the TDR, due in 2002, postponed 1 year. Paris Sphicas is US CMS L2 DAQ manager and CMS L2 PRS manager. Much work on forming and launching the 4 PRS groups has been accomplished. DOE/NSF Review May 8-10, 2001
29
WBS 4 - ECAL Avalanche Photodiodes Front-End Electronics Monitor Laser
final structure selected. Neutron Source operational. Front-End Electronics FPPA pilot wafers back and under test. Honeywell Bit-serializer dropped, moved to CERN group. Monitor Laser Preparation for shipping laser to CERN. DOE/NSF Review May 8-10, 2001
30
FPPA2000 (UHF1x) FPU Gain FPU Logic Temp / Leak Output Buffer Leak / Temp Mux Bias Preamp The FPPA is in final preproduction. The responsibility has shifted from Princeton to LBNL. Evaluation is in train. DOE/NSF Review May 8-10, 2001
31
FPix. Sensors, 1st Subm. WBS 5 - FPIX Sensor Submission
Before irradiation 90% of pixels have Vbrkdwn >300V After = 1x1014 p/cm2 increase in current after 300V (2-8)% noisy channels (PSI) With = 6x1014 p/cm2 same I with pixels at -100C DOE/NSF Review May 8-10, 2001
32
VHDI - Prototype VHDI for Row of 5 ROCs Test Station DOE/NSF Review
May 8-10, 2001
33
SiDet Assembly R&D Assembly of Detectors; NIKON coord. meas.
Need 672 units Assembly of Butterflies; OMIS II meas. coord. Need 96 units DOE/NSF Review May 8-10, 2001
34
CERN Test Beam Pixels at 20o to beam 150 m / 12 = 43 m
Charge sharing vs position Pixels at 20o to beam = 14 m over pixel 150 m 150 m Charge sharing vs position 150 m / 12 = 43 m = 46 m over pixel Pixels normal to beam DOE/NSF Review May 8-10, 2001 D:\LHM\2001\Presentations\Plenary Presentations\For Dan \Cern Test Result.ppt
35
WBS 8 - SiTrkr DOE/NSF Review May 8-10, 2001
36
Preparation for Pre-Production
Mock-up frames for training gantries KSU Probe Station DOE/NSF Review May 8-10, 2001
37
WBS 6 - Common Projects DOE/NSF Review May 8-10, 2001
38
Detector Project Summary
M&S cost experience has been good. The labor for CSC and HCAL absorber has been well estimated. Contingency use has been good enough to allow for modest scope increases - SiTrkr Planning for I&C is in train, with cost increases due to delay and re-estimations. DOE/NSF Review May 8-10, 2001