Project members ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Project members Manager in Charge (RBDCK) : Radhakrishnan V mob : Site in Charge (KITCO) : Rahul mob : Project Engineer (GPT) : Nikhil mob : Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
2
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Revised Progress Report For Mulankunnathukavu ROB for the week ending on Si No Activity Description Total Quantity Cumulative progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work Planned for next week No of days remaining for completion as per the weekly plan Remarks 1 PILE SHORNUR SIDE 9 Completed 2 PILE M.C SIDE 36 3 PILE CAP SHORNUR SIDE 4 PILE CAP M.C SIDE 12 5 PIER SHORNUR SIDE 6 PIER M.C SIDE 7 PIER CAP SHORNUR SIDE 8 PIER CAP M.C SIDE pedestal concreting 2 No.s completed P7 & P8 RE/R WALL SHORNUR SIDE 100% 91% 10.00% 0.00% 76.00% 95 days 10 RE/R WALL M.C SIDE 5.00% 43.00% Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
3
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Si No Activity Description Total Quantity Cumulative progress up to last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work Planned for next week No of days remaining for completion as per the weekly plan Remarks 11 BEAM/SLAB SHORNUR SIDE 3 0* 65 days 12 BEAM/SLAB M.C SIDE 9 1 4 132 days concreting of 3 spans in the M.C side completed..reinforcement work and shuttering work of the girder of the fourth span P13-P12 is completed. Side shuttering and reinforcement of deck slab in progress. deshuttering work of the span P9-P10 completed except the beam bottom. concreting of the span P13-P12 to be done on April 30 13 HR/FP/KERB SHORNUR SIDE 100% 0.00% 53 days 14 HR/FP/KERB M.C SIDE 95% 2.00% 15 BC/PAINTING
4
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Availability of Men Date 23-4-'11 Nof labours 18 19 Material Stocking Status Required Available Remarks Fine aggregate {cft} 100 450 Cement(bag) 630 770 Steel inT 11 18 sufficient material available at the site Coarse Aggreagate (cft) 400 800 Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
5
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Utility shifting Utilities to be shifted Remarks BSNL CABLE REROUTED The BSNL has laid new cables to rerouted at the site but to be connect the joints. Hence no hindrance for canal deviation work. KSEB already shifted KWA hindrance The KWA has rerouted the new PVC pipelines .Therefore no hindrance. Others road diversion work IN PROGRESS.only bitumenous macadum layer is left to be done. canal diversion work will be started soon after closing the water flow. Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
6
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Progress Graph Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
7
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on Progress between to Staging and barbending work of fourth span P12-P13 is in progress. Staging work of fifth span P8-P7 is in progress. Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
8
ROB at Mulamkunnathukavu - Progress
ROB at Payyannur ROB at Mulamkunnathukavu - Progress Deshuttering of the span P9, P Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
9
Shifting of water supply pipe line - 23.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu - Progress Shifting of water supply pipe line Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
10
Shuttering and Reinforcement work of span P 1, P12 - 25.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu - Progress Shuttering and Reinforcement work of span P 1, P Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
11
Reinforcement work finishing stage of Span P 13 - P12 - 26.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu - Progress Reinforcement work finishing stage of Span P 13 - P Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
12
ROB at Mulamkunnathukavu - Progress
ROB at Payyannur ROB at Mulamkunnathukavu - Progress Reinforcement work for Span P P Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK
13
ROB at Mulamkunnathukavu Progress as on 29.04.2011
ROB at Payyannur ROB at Mulamkunnathukavu Progress as on LABOUR ATTENDANCE FOR ROB MULAMKUNNATHUKAVU SITE Date Barbender/Carpenter Welder Operators Labours Total 23/04/2011 2 1 3 12 18 24/04/2011 25/04/2011 26/04/2011 27/04/2011 13 19 28/04/2011 Site Engineer : Rahul ( ) Manager in charge :Radhakrishnan V ( ) KITCO RBDCK