Download presentation
Presentation is loading. Please wait.
1
Target and Horn status report
Simone Gilardoni - PS Division Helge Ravn – EP Division For the Target and Horn Working Group
2
Schedule of the CERN Horn and Hg-jet R&D work in 2001
January Off-line tests of the Hg pump and jet January Delivery and test of the endoscope and camera February Commissioning of a Hg-jet in a 1.5 T CERN magnet February Test the Hg-jet in a 13T magnet at Grenoble February Planning a Hg-jet test in a 20 T Grenoble magnet February Final design of the chamber for the Hg-trough test April Successful tests of Hg-trough and –jet at Brookhaven June Design and construction of a horn prototype July Design and construction of a prototype horn power supply September Hg-trough installation and feasibility test at ISOLDE September Test the Hg-jet in a 20 T Grenoble magnet October Redesign the Hg-jet chamber for the 20 T magnet October Find specialists in hydrodynamics and heat transfer from the direct water- cooled granular metal target December Finish and start testing the horn power supply Work done Work in progress
3
Ongoing effort to integrate target and horn
Where we are …. Ongoing effort to integrate target and horn Target experiment trough test at ISOLDE New horn design a short historical introduction Horn test Plans for future
4
Target+Horn station CERN work scenario
5
Isolde Mercury test setup
p beam frontend Hg container mirror camera
6
Plans of the CERN Hg-jet R&D work in 2002
January Test the Hg-jet in a 20 T Grenoble magnet. January Start designing the spent beam absorber for the super- beam target version. February Make a plan for which parameters of solid and liquid metal targets should be experimentally determined, what equipment is needed for their measurement. April Systematic Hg-trough tests at ISOLDE. April Modify existing hydrodynamic codes to which the experimental results should be compared. April Start planning the in-beam tests of the Hg-jet in the ISOLDE target area. March Design the vacuum vessels and support including Hg circulation and on-line distillation needed for the in-beam Hg-jet. September Building and off-line testing of the in-beam Hg-jet. October Request on-line tests of the Hg jet in the ISOLDE proton beam.
7
From results of target experiment ...
Inner Hg pipe Shock due to Hg disruption Thickness and material Hg hydrodynamics Speed of the Hg drops Effective target length Hg damping surface best place thickness
8
Old horn design Current: 300 kA Inner radius: 1.6 cm
Outer radius: 100 cm Technical Limits High inductance Reduce high B field volume Space for target Hg - inner conductor insulation LARGER INNER RADIUS
9
New “double” horn design
Increase of B at large radius 600 kA 300 kA Old horn neck R = 1.6 cm New horn neck R = 4 cm B field is 2.5 times smaller ! First decay channel solenoid
10
Horn to maximise the m flux for the phase rotation
Beam dynamics study Horn to maximise the m flux for the phase rotation Muons: MeV < EKinetic < 300 MeV With new design flux losses of % Pions have to be injected in the fringe field of the first decay channel solenoid Constraints: max R = 30 cm, max P 80 MeV/c (Bsol=1.8 T) Matching between horn and solenoid under study Open question: relative position between horn and solenoid Overlapping the fields? One solution found: better to inject with small spot size but with a non parallel beam
11
From results of beam dynamics and Monte Carlo study ...
Inner Hg pipe Max thickness allowed for pion absorption First decay channel solenoid Fringe field effect on focusing Energy deposition in the first coil Beam composition pronton and neutrons flux Hg damping surface Max thickness allowed for pion absorption
12
Inner horn technical drawing
Water spray Water channel
13
Where is the life time limit ?
Life time CNGS horn: ~ 2*107 pulses years at 95% C.L. Life time NuMI horn: ~ 107 pulses year Life time Nufact horn: ~ 2*108 pulses weeks at 95% C.L. Who is the killer? fatigue limit stress due to electro-magnetic forces thermal stresses joule losses particle energy deposition (still to be evaluated)
14
Plans for ongoing horn program
Power supply for Test One in construction in BA7 Ready for first test in December First “inner” horn 1:1 prototype in construction Ready for test in February Test One: 30 kA and 1 Hz First mechanical and thermal stresses measurements Test of numerical results for vibration (work in progress) Test of cooling system Based on existing power supply Test Two: 300 kA and 1 Hz Depending on power supply Last test: 300 kA and 50 Hz
15
Discussion of Design Methodology Cooling
To print from original ! Nozzle Heat Transfer Coefficient Measurement
16
A lot of work for results in a near future is going on Hot topics:
Conclusion A lot of work for results in a near future is going on Hot topics: Results from ISOLDE experiment Results from horn test Target and horn study has to proceed in parallel: material budget horn shape Thanks to all the collaborators also from outside CERN
17
Remark on pbar-horn Current : 400 kA Protons: GeV *1013 p/pulse sx=1 mm rms
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.