ELCITA UPDATE August 2016
2
Estate Management Skywalk E – Toilets 16 e-toilets operational.
M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E – Toilets 16 e-toilets operational. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 100 % completed. GIS Web Application Software Installed in ELCITA server. Testing work in progress.
3
Siemens to Infosys Gate-3 Road
Road Works – Completed Siemens to Infosys Gate-3 Road Velankani Road
4
Road Works – Under Progress
BHEL to Wipro Gate 5 - Completed Concrete Pavements along Doddanagamangala Village Road
5
Drain Works – Under Progress
Drain Work From Wipro Gate 5 to Wipro Gate 16 Drain Work in front of CDac
6
Drain/Footpath Works – Under Progress
Removing the existing pavers & laying the new Pavers at Salarpuria Info Zone Police Station Drain
7
Drain Works – Completed
Drain Work along ITI property Drain Work in front of Venkatadri
8
Misc Works – Under Progress
Road Widening at Pump House Road Barbed Wire Fencing at Pump House
9
Misc Works – Completed Construction of Shoulder Drain along Café Corner Road Kerbstone Painting at Siemens Road
10
Misc Works – Completed MS Railing work below Fly over for E-Toilet
MS Railing work – Median Ecity Phase 2
11
Sustainability Projects
RWH works – Under Progress SI.NO DESCRIPTION NO OF PITS STATUS 1 RAIN WATER HATVESTING PIT 43 COMPLETED 2 WORK IN PROGRESS
12
20 feet deep well Rainwater Harvesting Pit at Various locations
13
Estate Management Contract Awarded
Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road MSME Entry Gate to Exit Gate for 300KLD STP Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road
14
Estate Management Contracts on Anvil
Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs along XIME Road Petrol Bunk Road & Golden Tulip Road Providing and laying of Asphalting using 60/70 grade bitumen along KSSIDC Complex Road Landscaping work below fly over (Phase 1 & 2) Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2