STATUS OF THE SPORT AND RECREATION FACILITIES SRSA PORTFOLIO COMMITTEE

Similar presentations


Presentation on theme: "STATUS OF THE SPORT AND RECREATION FACILITIES SRSA PORTFOLIO COMMITTEE"— Presentation transcript:

1 STATUS OF THE SPORT AND RECREATION FACILITIES SRSA PORTFOLIO COMMITTEE
1

2 PRESENTATION OUTLINE Background DoRA MIG Framework:
Objective of the MIG MIG Conditions Planning Deadlines – Ensure Timeous Implementation Role of SRSA as per the MIG Framework General MIG Investments in Sports Facilities: Actual MIG Investments in Sports and Recreation – 30 June 2017 Type of MIG Investments in Sports and Recreation – 30 June 2017 Ring-Fenced Sports Projects - Status: Status of the 2016/17, 2017/18 and 2018/19 Sports Projects Key Challenges Remedial Actions Collaboration Efforts 2

3 BACKGROUND The National South African Sports and Recreation Amendment Act of and National Development Plan imposes a mandate on the Department of Sport and Recreation to ensure provision of sporting and recreation in the country. Schedule 5B of the Constitution requires municipalities to provide physical sporting facilities in their respective areas of jurisdiction. Notwithstanding a constitutional obligation to provide sporting facilities in their communities and the inclusion of mandatory allocation of funds to spend these facilities in MIG, there has been a poor delivery of sport facilities virtually in all parts of the country Amongst others, justification for poor delivery is prioritisation of municipal basic infrastructure for provision of basic services, and sport infrastructure is not recognised as such 3

4 BACKGROUND National Sport and Recreation Plan (NSRP) recognises that South Africa has a challenge of provision, equitable access and maintenance of sport and recreation facilities, which has far reaching consequences for the transformation and development of the sector NSRP acknowledges that failure to address sport infrastructure backlogs will compromise the country’s objective of transformation, sports development and increased participation because sport facilities forms the foundation of the entire sport and recreation system, and therefore provision of sport facilities is an indispensable requirement to achieve a 2030 vision of Active and Winning Nation. For these reasons, the ringfencing of R300 million was introduced as a pilot for innovative and effective delivery mechanisms to accelerate and broaden delivery of sport facilities. 4

5 BACKGROUND 2016/17 financial year R300 million of MIG funds allocated for sports facilities outside of the MIG formula. Funds allocated based on a Municipality Facility Project list identified by SRSA. 30 municipalities benefitting from the programme. SRSA encouraged Municipalities to prioritize sports infrastructure in line with their own IDPs. SRSA worked through the MIG structures to guide, assess and approve funding for these municipal projects. Conditions relating to the grant have been captured into the conditional Grant Framework and gazetted. The decision to allocate funds was communicated in October 2016 so timelines to finalise plans were very tight. 5

6 DoRA MIG FRAMEWORK 6

7 OBJECTIVE OF THE MIG Strategic goal: Subsidise the capital costs of providing basic services to poor households Grant purpose: To provide specific capital finance for eradicating basic municipal infrastructure backlogs for poor households, micro enterprises and social institutions servicing poor communities Outcome statements: Improved access to basic services infrastructure for poor communities 7

8 MIG CONDITIONS To receive the first tranche, municipalities must have followed the process for approval of 2016/17 projects and have confirmed by 2 June 2017 with the Department of Cooperative Governance (DCoG) their programme, project planning and implementation readiness; This above should be done prior to the year of implementation and be informed by their Integrated Development Plan (IDP) and three year capital plans; MIG priorities set by municipalities (as stated in there three year capital plan) can only be changed with municipal council approval, the concurrence of the sector departments and the approval of DCoG; Municipalities must spend at least 60 per cent of their previous transfer and comply with reporting provisions before the second and subsequent transfers are made; Municipalities must spend 40 per cent of their total MIG allocation by December 2016; Municipalities must comply with sector norms, standards and legislation as confirmed by sectors during the MIG project registration processes; Ring-fenced sport infrastructure allocation: municipalities that have allocations gazetted as part of the ring-fenced allocation for specific sport infrastructure projects may only spend these allocations on the projects identified by Sport and Recreation South Africa (SRSA) Withholding or stopping of transfers and reallocation of MIG allocations will be instituted where municipalities deviate from and/or do not comply with the conditions above. 8

9 PLANNING DEADLINES – ENSURE TIMEOUS IMPLEMENTATION
DoRA and MIG Framework Preparatory Requirements (e.g. 2017/18 F/Y): Municipalities must submit all technical reports to the sector departments responsible for water, sanitation, solid waste, sport and recreation, roads and transport by 29 July 2016, for all projects to be implemented in 2017/18 The responsible sector department must evaluate reports and provide final recommendations to the municipality by 30 September 2016 The municipality must submit all project registration forms by 3 October 2016, for the projects to be implemented in 2017/18, to the provincial department responsible for local government The provincial departments must provide final recommendations to municipalities by 30 November 2016 Municipalities must submit to DCOG by 31 January 2017, detailed project implementation plans for all the projects to be implemented in the 2017/18 and 2018/19 financial years Such plans should include timelines regarding project designs, initiation of procurement, and Environmental Impact Assessment (EIA) and/or relevant permit/license approvals in the prescribed format Municipalities must submit updated implementation plans as mentioned above by 2 June 2017, justifying any changes from the 31 January 2017 detailed plan Submission of 2018/19 projects should have been done by 31 July 2017 Final allocations to municipalities to be send to National Treasury by 01 December 2017, including SRSA R300 million targeted allocations to municipalities 9

10 Role of SRSA as per the MIG Framework
Responsibilities of provincial sector departments Develop sector norms and standards for basic services (including unit cost guidelines); Participate in district appraisal and progress committee meetings; Evaluate and provide recommendations on sector technical reports before projects are appraised; Each provincial sector department must fulfil a sectoral monitoring and guidance role on relevant sectoral outputs; Provide technical advice as required by a municipality through the feasibility, planning, design, tender and construction phases of a MIG project. 10

11 GENERAL MIG INVESTMENTS IN SPORTS FACILITIES AS AT 30 JUNE 2017
11

12 Actual MIG investments in sport and recreation facilities as at 30 June 2017
12

13 Type of MIG investments in sport and recreation facilities as at 30 June 2016
13

14 RING-FENCED SPORTS PROJECTS – STATUS:
Progress, Key Challenges And Remedial Actions 14

15 Status of the 2016/17, 2017/18 and 2018/19 Targeted Sports Projects – R900 million MTEF Allocations
R300 million MIG funding ring-fenced; 30 municipalities benefited from the allocation; An average15% spent by the 30 municipalities as at 30 June 2017. /18 Projects: 29 municipalities benefiting; 34 projects to be implemented; All 34 projects at planning stage; Projects must have been registered and appraised by Appraisal Committees by 30 November 2016. 2018/19 Projects: R300 million MIG ring-fenced; No beneficiary municipalities identified yet; process to be concluded 30th October Projects must be registered and appraised by the Appraisal Committees by 30 November 2017. 15

16 2016/17 PROJECTS PROGRESS STATUS

17 PROJECT STATUS 17 Province Municipality Project Cost
Expenditure to date % of Expenditure Progress on Site Comments EC Makana R ,00 R 8% 0% Rollover application lodged Engcobo R ,00 R 30% 60% King Sabatha Dalindyebo R ,00 R 71% 80% Ntabankulu R 47% 78% FS Mohokare R ,00 R Tokologo R 100% Project completed GP Rand West R 4% 17

18 PROJECT STATUS Province Municipality Project Cost Expenditure to date
% of Expenditure Progress on Site Comments KN Richmond R ,00 R 2% 0% No rollover application lodged Greater Kokstad R 3% uPhongola R 5% LP Greater Giyani R Rollover application lodged Maruleng R ,00 R 100% Molemole R ,00 R 10% Elias Motsoaledi R ,00 32%

19 PROJECT STATUS 19 Province Municipality Project Cost
Expenditure To Date % of Expenditure Progress on Site Comments MP Albert Luthuli R ,00 R 15% 35% Rollover application lodged Msukaligwa R ,00 R 81% 90% Lekwa R ,00 R 95% 100% Victor Khanye R ,00 R 83% 85% Emalaheni R ,00 R 99% NC Kamiesberg R ,00 R 0 0% Khai Ma R 4% 19

20 PROJECT STATUS 20 20 Province Municipality Project Cost
Expenditure To Date % of Expenditure Progress on Site Comments NC Umsobomvu R ,00 R 74% 68% Rollover application lodged Gamagara R ,00 R 29% 0% NW Ratlou R ,00 R 80% 95% Mahikeng R ,00 R 21% 20% Mamusa R ,00 R 83% 90% Lekwa Teemane R ,00 R 65% WC Cederberg R ,00 R 3% 20 20

21 PROJECT STATUS 21 21 Province Municipality Project Cost
Expenditure To Date % of Expenditure Progress on Site Comments WC Swellendam R ,00 R 4% 35% Rollover application lodged Beaufort West R ,00 R 0% 21 21

22 PROGRESS SUMMARY 22 22 PROVINCIAL SUMMARY Eastern Cape R 46 661 000.00
Eastern Cape R R 36% Free State R R 52% Gauteng R R 4% KZN R R 3% Limpopo R R 12% Mpumalanga R R 77% Northern Cape R R 31% North West R R 33% Western Cape R R NATIONAL TOTAL R R 30% 22 22

23 2017/18 PROJECTS PROGRESS STATUS
23

24 2017/18 FIN YR – EASTERN CAPE PROJECTS
PROJECT NAME BUDGET MUNICIPALITY PRPJECT STATUS DEVIATION STATUS EASTERN CAPE Construction of a Sport Facility within Mbizana Local Municipality R 12 000 000,00 Mbizana Local Municipality Waiting appraisal  Granted Upgrading of sports field within Sakhisizwe Local Municipality. R 12 500 000,00 Sakhisizwe Local Municipality Registered Granted Upgrading of a sSport field within Raymond Mhlaba Local Municipality R 5 000 000,00 Raymond Mhlaba Local Municipality Upgrading of a sport field within Water Sisulu Local Municipality R 10 821 016,00 Walter Sisulu Local Municipality R 40 321 016,00

25 2017/18 FIN YR – FREE STATE PROJECTS
PROJECT STATUS DEVIATION   Construction of a sport field within Ngwathe Local Municipality R 7 411 935,00 Ngwathe Local Municipality Registered Granted Upgrading of a Sport Facility within Nala Local Municipality R 4 373 040,00 Nala Local Municipality Construction of a sport field within Kopanong Local Municipality R 9 200 000,00 Kopanong Local Municipality Namahadi/Kgatholoha:Upgrading of sports ground. R 4 307 886,00 Mafube Local Municipality Rgistered Upgrading of a Sport field within Phumelela Local Municipality R 9 604 000,00 Phumelela Local Municipality Waiting Appraisal R 34 896 861,00

26 2017/18 FIN YR – GAUTENG PROJECTS
PROJECT STATUS DEVIATION   Zuurbekom Multi Purpose Sport and Recreation Community Centre:Soccer Facility R 8 171 805,00 Rand West Local Municipality Registered No application received Upgrading of President Park Swimming Pool Facility in Vereeniging. R 9 593 100,00 Emfuleni Local Munincipality Approved Construction of Heidelberg Ext 23 Sports Complex R 15 108 454,00 Lesedi Local Munincipality TOTAL R 32 873 359,00

27 2017/18 FIN YR – KZN PROJECTS KWAZULU-NATAL PROJECT STATUS DEVIATION
Construction of Sports Fields within Ndwedwe Local Municipality R 11 000 000,00 Ndwedwe Local Municipality Awaitng Appraisal but registered Granted Construction of Sports Fields within Nongoma Local Municipality Nongoma Local Municipality Construction of Sports Fields within Umshwati Local Municipality Umshwati Local Municipality Registered No application received Construction of Sports Fields within Nquthu Local Municipality Nquthu Local Municipality Refered back on MIG-MIS TOTAL R 44 000 000,00

28 2017/18 FIN YR – LIMPOPO PROJECTS
PROJECT STATUS DEVIATION  Construction of Stadium within Ba-Phalaborwa Local Municipality R 7 084 000,00 Ba-Phalaborwa Local Municipality Registered No application received Construction of Stadium within Greater Letaba Local Municipality R 2 564 000,00 Greater Letaba Local Municipality Granted Construction of Stadium within Ephraim Mogale Local Municipality R 10 832 000,00 Ephraim Mogale Local Municipality Construction of Sport Complex within Polokwane Local Municipality R 7 764 000,00 Polokwane Local Municipality Construction of Stadium within Lepelle-Nkumpi Local Municipality R 5 137 000,00 Lepelle-Nkumpi Local Municipality R 33 381 000,00

29 2017/18 FIN YR – MPULANGA PROJECTS
LIMPOPO PROJECT STATUS DEVIATION  Mkhondo LM Sport Complex Construction R 7 084 000,00 Mkhondo LM Registered  No application received Upgrading of sports complex Dr. Pixley Ka Isaka Seme LM R 2 564 000,00 Dr. Pixley Isaka Seme Construction of sports complex Thembisile Hani LM R 10 832 000,00 Thembisile Hani Granted Construction of sports complex Nkomazi LM R 7 764 000,00 Nkomazi LM Construction of sports complex Bushbuckridge LM R 5 137 000,00 Bushbuckridge LM R 33 381 000,00

30 2017/18 FIN YR – NORTHERN CAPE PROJECTS
PROJECT STATUS DEVIATION  Construction of sport field within Sol Plaatje Local Municipality R 6 866 588,00 Sol Plaatje Local Municipality Registered Granted Construction of sport field within Siyancuma Local Municipality Siyancuma Local Municipality Awaiting Appraisal No application received Construction of sport field within Hantam Local Municipality Hantam Local Municipality R 20 599 764,00

31 2017/18 FIN YR – NORTH WEST PROJECTS
PROJECT STATUS APPRAISAL   Construction of a sport facility within Moretele Local Municipality R 15 000 000,00 Moretele Local Muncipality  Not Registered No application received Upgrading of multi-purpose stadium within Ramotshere Local Municipality R 7 274 000,00 Ramotshere Moiloa Local Municipality Not registered Construction of a sport facility within Greater Taung Local Municipality Greater Taung Local Municipality R 37 274 000,00

32 2017/18 FIN YR – WESTERN CAPE PROJECTS
PROJECT STATUS   DEVIATION Construction of sports ground within Bitou Local Municipality R 13 000 000,00 Bitou Local Municipality Awaiting Appraisal No application received Upgrading of sport ground within Langeberg Local Municipality R 15 000 000,00 Langeberg Local Municipality Granted R 28 000 000,00

33 2017/18 - PROJECT SCHEDULE Task Name Duration Start Finish
Site assessment visits 5 weeks 2017/04/24 2017/05/26 Completion of detailed designs 7 days 2017/05/29 2017/06/06 Cost estimate of detailed designs 1 week 2017/06/07 2017/06/13 Approval of standardised design and cost estimate 2017/06/14 2017/06/20 Finalise construction drawing 3 week 2017/06/21 2017/07/11 Complete standard Bill of Quantities 2 weeks 2017/07/12 2017/07/25 Submit SDP for each project to municipalities for approval 2017/06/26 2017/08/01 Municipality invites contractors from panel to price the tender 2017/08/02 2017/08/15 Submission of priced tenders 0 days 2017/08/16 Evaluation & appointment of contractor 2017/08/17 2017/09/13 Site handover & construction start 0 day 2017/09/14 Construction period 9 months 2017/09/15 2018/05/24 Practical completion 2018/05/25 Defects liability period 90 days 2018/05/27 2018/09/27 Final completion & final account 1 months 2018/09/28 2018/10/25 33

34 GENERAL CHALLENGES Poor communication between the department and municipalities causing delay in critical activities of the project Limited time for project implementation. Both planning and implementation expected to be completed in a period less than financial year Alignment between MIG requirements and SRSA project selection Compliance with legislative framework that affect land development. (e.g. EIA in Gamagara and Kokstad) Poor/ Lack of planning for provision of sports facilities at municipal level Absence of project steering committees to drive and ensure implementation of projects Poor cooperation from some municipalities (i.e. attendance of provincial meetings, submission of reports and lack of response to communication send by department) 34 34

35 KEY CHALLENGES Limited capacity of provincial sports departments to play expected role in the MIG value chain Lack of needs based National, Provincial and Local Facility Plan(s) Inadequate consultation with Cogta resulting, in some instances, in identification not fully compliant with MIG conditions Poor consultation with targeted municipalities in identifying sports projects; Poor alignment between SRSA selection timelines and that of the MIG grant framework; Lack of a plan by SRSA to ensure that the sports facilities developed through MIG are utilised over their lifespan; (not related to R300 million) Limited capacity within SRSA to manage sports projects; Resistance to use transversal contracts, and delays in deviation process caused significant lag times Reluctance to cooperate with SRSA PMU for provision of technical and management support 35

36 REMEDIAL ACTION Increased technical and management support to individual municipalities Establishment of Provincial Project Steering Committees to ensure implementation Enforcement of submission of Project Implementation Plans for effective monitoring Improved cooperation between Department of Sports and Cogta to collaboratively resolve sticky issues during implementation of projects Participation in Treasury’s Rollover Meetings to ensure approval of applications for sports facilities SRSA must ensure cooperation of beneficiary municipalities with its PMU in respect to all phases of the project 36 36

37 REMEDIAL ACTIONS - Continue
Sector guidance on priorities – SRSA needs to finalise Natioanal Facility Plan with clear sector targets and priorities to ensure a well coordinated allocation of sport infrastructure investment SRSA must be in a positing to monitor projects – SRSA capacity needs to be addressed Strengthening the participation of the SRSA and its provincial counterparts in MIG business processes, i.e appraisal and MIG planning sessions with municipalities; Improved coordination of activities and efforts between government spheres (intergovernmental coordination) and government departments (inter-departmental coordination); 37

38 REMEDIAL ACTIONS - Continue
SRSA to develop a sports master plan that will inform municipal plans; SRSA and its provincial counterparts to participate in municipal IDP processes to inform sports priorities; Enforce identification of projects in line with IDP priorities Ensure identified projects comply with the MIG Framework and are aligned to NDP priorities SRSA to develop a three year project implementation plan and communicate it with beneficiary municipalities in time, to ensure timeous registration and implementation of projects; SRSA categorise suitability and level of service in line with its Facility Classification Framework Improve the efficiency of the use of transversal contracts or scrap it; SRSA will strengthen its support to municipalities to ensure that sports projects in general are properly operated and maintained; SRSA will enforce development and submission Sport Infrastructure Asset Management Plan as part of handover report to ensure full utilisation of sports facilities; SRSA to build internal capacity to undertake the above recommendations. 38

39 COLLABORATIVE EFFORTS
39

40 COLLABORATIONS Dedicated SRSA MIG workshop to address sports issues;
Regular meetings between SRSA, National Treasury, DCoG, Misa and SALGA: Engagements and support by provincial departments responsible for local government (i.e. Coghstas); Participation in the rollover assessment engagements in order to provide inputs/motivations; 40