Low Level Road Project – Traffic Management Meeting August 2012
Construction Update Local Residents Meeting ( Block East 1st) April 10, 2013 Welcome: Good afternoon everyone. Thank you for attending this meeting as part of preliminary traffic management planning for the Low Level Road Project.
2
Low Level Road Project – Traffic Management Meeting August 2012
Meeting Agenda Topic Welcome/Introductions Construction Sequencing and What to Expect Schedule Key Contacts Pre-Condition Surveys Closing Remarks Meeting Agenda: Today’s meeting will consist of a presentation that is approximately 25 minutes in length. Then after some brief questions for clarification, we will break out into smaller groups to discuss in more detail some of the specific traffic staging and related traffic management ideas. Each group will have the opportunity to discuss all aspects of the traffic management, but it’s expected that some groups will want to focus more on specific areas, and that’s ok. After about an hour, groups will provide a brief summary of their discussion and then we will have a plenary discussion/QA session At the end of the meeting, we are also hoping you will take a few minutes to complete a feedback form that will give us some more specific information about your business’s specific interests and needs and give you with an opportunity to provide more detailed comments on the discussion topics. The session will take up to about 2.5 hours, and we will finish on time. Introductions: Before we begin, I would like to take this opportunity to introduce the project team representatives that are here today…. If group is small enough, do full intros, otherwise leave participant intros to small group work. Thank you everyone. And now, over to Richard Lyell, the project manager, to walk us through the presentation.
3
Construction Staging Locations and Cross Sections: St. Davids area
Behind East 1st End of Lane
4
Direction of Work Start Direction of Work
Finishing Works Start Aug for 6 weeks End
5
Types of Walls Shotcrete Wall Location
Finishing Works Start Aug for 6 weeks
6
Existing Ground – With Vegetation Removed
St Davids STA
7
Stage 1 – Excavation (Lane Closed)
Excavation Start April 29th for 6 Weeks St Davids STA
8
Excavation Soil collection and transfer (dust)
Trucks and heavy equipment (backup beepers, engine noise, vibrations)
9
Stage 2 – MSE Wall Construction (Lane Closed)
MSE Wall Start May for 6 weeks St Davids STA
10
MSE Wall Construction Material Placement (dust)
Trucks and heavy equipment (backup beepers, engine noise, vibrations) Fill compaction (vibration)
11
Stage 3 – Excavation (Lane Open)
Excavation Start Sept for 5 Weeks St Davids STA
12
Stage 4 – Lower MSE Wall (Lane Open)
Lower MSE Wall Start End Oct for 7 weeks St Davids STA
13
Stage 5 – Finished Construction
Project Completed Fall 2014 St Davids STA
14
Existing Ground – With Vegetation Removed
Behind E1st St STA
15
Stage 1 – Excavation (Lane Closed)
Excavation Start April 29th for 6 Weeks Behind E1st St STA
16
Stage 2 – MSE Wall Construction (Lane Closed)
MSE Wall Start May for 6 weeks Behind E1st St STA
17
Stage 3 – Shotcrete Wall (Lane Open)
Shotcrete Wall Start June for 16 Weeks Behind E1st St STA
18
Shotcrete Trucks and heavy equipment (backup beepers, engine noise, vibrations) Anchor installation (noise and vibration)
19
Stage 4 – Excavation (Lane Open)
Excavation Start Sept for 5 Weeks Behind E1st St STA
20
Stage 5 – Lower MSE Wall (Lane Open)
Lower MSE Wall Start End Oct for 7 weeks Behind E1st St STA
21
Example Images of Similar Construction
22
Stage 6 – Shotcrete Wall Facing (Lane Open)
Shotcrete Wall Facing Start Nov for 20 weeks Behind E1st St STA
23
Stage 7 – Finished Construction
Project Completed Fall 2014 Behind E1st St STA
24
Existing Ground – With Vegetation Removed
End of Lane STA
25
Stage 1 – Excavation (Lane Closed)
Excavation Start April 29th for 6 Weeks End of Lane STA
26
Stage 2 – MSE Wall Construction (Lane Closed)
MSE Wall Start May for 6 weeks End of Lane STA
27
Stage 3 – Excavation (Lane Open)
Excavation Start Sept for 5 Weeks End of Lane STA
28
Stage 4 – Lower MSE Wall (Lane Open)
Lower MSE Wall Start End Oct for 7 weeks End of Lane STA
29
Stage 7 – Finished Construction
Project Completed Fall 2014 End of Lane STA
30
Direction of Work Start Direction of Work
Finishing Works Start Aug for 6 weeks End
31
Approximate Schedule
32
Schedule of Work 2013 2014 Q1 Q2 Q3 Q4 Top Excavation Top MSE Wall
Shotcrete Wall Lower Excavation Lower MSE Wall Shotcrete Facing Finishing Works
33
Cindy McCarthy cindy.mccarthy@portmetrovancouver.com 604-665-9382
Key Contacts Cindy McCarthy Porttalk.ca
34
Pre Condition Surveys
35
Low Level Road Project – Traffic Management Meeting August 2012
Thank You Closing Remarks How feedback will be used Next Steps Thank you
36
Example Images of Similar Construction