1 The Way Forward ISS to IDS
ISS - Ended NuFact 2006 IDS – Starts NuFact 2007 Aims, Structure, Resources

2 ISS – Recapitulate Instigation
A Re-evaluation of the Neutrino Factory Situation Following the earlier studies mainly in the US And a new interest in the UK Was set up very quickly Meeting in London May 2005 – Launched NuFact 2005 Aim A Baseline Scenario for a more detailed study An R&D Programme Originally considered for a Neutrino Factory Solution But with the aim of comparison with other solutions 30 Mar 2007 P Dornan

3 ISS Structure Resources Physics Accelerator Detectors
Why do precision Neutrino Physics Compare the techniques for that phase Accelerator Origiinally Neutrino Factory but extended to Super beams following requests Detectors Sressed importance Considered all possibilities – magnetic and non-magnetic Resources Mainly a paper exercise - therefore mainly travel Institutions, Universities, Funding Agencies, BENE, NFMCC, UKISS 30 Mar 2007 P Dornan

4 Continuation → the IDS Should we continue? At NuFact06
From this meeting I consider YES At NuFact06 Aims for the Neutrino Factory Solution An Interim Design Report 2010/11 A Reference Design Report 2012/13 Problem How to Handle the different techniques Superbeam, Betabeam, Neutrino Factory 30 Mar 2007 P Dornan

5 Proposed Structure at NuFact06
This has cause some Unhappiness So we should discuss! 30 Mar 2007 P Dornan

6 Obtaining Resources Difficult Need Resources for both travel and R&D
FP7 bid to cover aspects of NuFactory, Betabeam and Super beam Other bids for Detector R&D Some from NFMCC and UKNFC But - Need more 30 Mar 2007 P Dornan

7 Preparing for IDS (NuFact) Launch at NuFact07
An ad-hoc Steering Group has Formed K Long (Co-ordinator), A Blondel, A Bross, P Dornan, M Dracos, R Edgecock, H Kirk. Y Kuno, Y Mori, M Lindroos, N Mondal, Y Nagashima, V Palladino, P Soler, M Zisman, Representatives from Betabeam and Superbeam Community Not Exclusve! All welcome to take part Next Meeting after this Discussion Aim to have a firm plan for the NuFact-IDS by NuFact07 30 Mar 2007 P Dornan

8 Venue: CERN Building 1-1-025. Agenda
1. Notes of previous meeting and review of actions Meeting Minute Initials Action Target date Status 09-Feb-07 2.4.1 KL Seek to establish small international communication team for glossy. 20-Feb-07 Done 21-Feb-07 2.1 KL, MZ, Abl Produce 10 page summary of working group reports by 14Mar07 14-Mar-07 2.2 PJD Assemble 10-page summaries into 30 page document by 28Mar07 28-Mar-07 2. Status of ISS report: 2.1 Physics Group report: KL 2.2 Accelerator Group report MZ 2.3 Detector Group report AB 2.4 Preparation of ’12-page’ glossy summary 2.5 Next steps PJD/All 3. ISS®IDS meeting at CERN 19–21Feb07 close-out 4.1 Discussion All 4. Summary of actions 5. Next meeting(s) · Phone: Friday 04Mar07, 13:30 GMT 6. AoB 30 Mar 2007 P Dornan