1 SPS Planning for the EYETS 2016-2017 Meeting 9 (14/12/2016)
David Mcfarlane EN-ACE-OSS EN-ACE D. Mcfarlane

2 SPS - EYETS: Main Activities
LIU SPS - EYETS: Main Activities Consolidation HL-LHC BA2 EN-ACE: TT20 Realignment BE-RF: Damper maintenance EN-EL: Cable Campaign BA1 SMB-SE: Repair & paint floor in Access Gallery EN-STI: Replace TIDVG TE-VSC: Replace ion pumps TE-ABT: Replace MKP EN-EL: Cable Campaign BE-BI: New Diamonds BLM BA3 EN-EL: Cable Campaign EN-EL: New Emergency lighting SPS TE-MSC: Magnet Campaign. TE-VSC: Vacuum Sectorization. EN-ACE: Vertical & Horizontal Re-alignment BA4 EN-EL: Cable Campaign EN-EL: BPM Fibre Optic upgrade TE-VSC: aC Coating Campaign TE-ABT: Swap MKE, X, Y Tanks TE-ABT: Exchange 6 MSE BA5 EN-HE: Renovation of the over head crane (ECX5) EN-EL: De-cabling & Cabling Campaign SMB-SE: Concrete block works for new beam dump BE-BI: New fast BCTs in LSS5 BA6 BE-RF: Crab Cavity installation work EN-EL: Cable Campaign EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

3 SPS - EYETS: Main Activities
LIU SPS - EYETS: Main Activities Consolidation HL-LHC BA2 EN-ACE: TT20 Realignment BE-RF: Damper maintenance EN-EL: Cable Campaign BA1 SMB-SE: Repair & paint floor in Access Gallery EN-STI: Replace TIDVG TE-VSC: Replace ion pumps TE-ABT: Replace MKP EN-EL: Cable Campaign BE-BI: New Diamonds BLM BA3 EN-EL: Cable Campaign EN-EL: New Emergency lighting SPS TE-MSC: Magnet Campaign. TE-VSC: Vacuum Sectorization. EN-ACE: Vertical & Horizontal Re-alignment BA4 EN-EL: Cable Campaign EN-EL: BPM Fibre Optic upgrade TE-VSC: aC Coating Campaign TE-ABT: Swap MKE, X, Y Tanks TE-ABT: Exchange 6 MSE BA5 EN-HE: Renovation of the over head crane (ECX5) EN-EL: De-cabling & Cabling Campaign SMB-SE: Concrete block works for new beam dump BE-BI: New fast BCTs in LSS5 BA6 BE-RF: Crab Cavity installation work EN-EL: Cable Campaign EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

4 SPS - Activities on the Critical Path
BA1 Replacement of TIDVG 28/02/17 – 24/03/17 (19 working d) Any delay in the delivery of TIDGV#4 will affect the closure date of the 24th March! BA5 De-cabling & Cabling Campaign 15/12/16 – 24/03/17 (12.3 weeks) Any delay will affect the closure of 24th March BA6 Crab Cavity installation work 15/12/16 – 24/03/17 (12.4 weeks) Any delay in this works will affect the closure date of the 24th March Specific care has been taken to allow the passage of magnets and the TIDVG past this work area Pressure testing and radiographic tests of the new cryo-line to be done outside the normal working hours EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016

5 Understanding the planning layout
The planning has been split into Zones. (BA1, BA2 etc) Each Zone has then been split into surface works and underground works. The works in each zone has been laid out by group. EN-EL, TE-VSC etc. Each work has a person responsible assigned to this task. (taken from the associated IMPACT) In the underground areas. The location identifies the exact area of work. (TS44 is arc 4-. TS45 is LSS4 and TS46 is arc 4+. BA4 underground means that the work goes across several areas in BA4) Any works that are marked RED means that this work will block access into the area. Any works that are marked in Purple means that this work will be taking place during the XMAS vacation. EN-ACE D. Mcfarlane

6 SPS Planning EN-ACE D. Mcfarlane

7 SPS Ring Main works Magnet exchange campaign (TE-MSC) Trench repairs
9th to 20th January Trench repairs Vacuum sectorization. Changing RP dosimeters around the ring Survey Alignment around the ring. EN-ACE D. Mcfarlane

8 BA1 Planning EN-ACE D. Mcfarlane

9 BA1 Main works (15th December to 13th January)
TE-ABT: Surface works MKDV maintenance (9th to 20th January) EN-EL: Lighting maintenance (5th to 9th January) EN-STI: Scraper Inspection and Maintenance. EN-HE: Lift maintenance. (21st December 7:30 to 9:00) TE-VSC: Grounding campaign SMB-SE: Repair and paint resin floor. (15th December to 16th January) Repair caniveaux. (19th to 21st December) EN-ACE D. Mcfarlane

10 BA2 Planning EN-ACE D. Mcfarlane

11 BA2 Main works (15th December to 13th January)
EN-EL SPS BPM Upgrade phase 2 (Fibre Optics) 19th December to 27th January) (Surface) Lighting maintenance (15th to 21st December) (Approved by RP) EN-ACE Survey works. EN-STI: TED/TBSE - Inspection and maintenance EN-HE: Lift maintenance (15th December 07:30 to 9:00) Monte Charge refurbishment. (2 months) BE-RF: Removing and transporting all 4 dampers to the 867 building (5th January) SMB-SE: Repair Caniveaux. (9th to 11th January) EN-ACE D. Mcfarlane

12 BA3 Planning EN-ACE D. Mcfarlane

13 BA3 Main works (15th December to 13th January)
EN-EL: Cable Campaign (9th January to 3rd March) SPS BPM Upgrade phase 2 (Fibre Optics) 19th December to 21st January) (Surface) Travaux de renovation réseau UPS et 48 VDC au BA3 eclairage securite. (15th December to 19th January) EN-HE: Lift and monte-charge maintenance (19th and 20th December) BE-RF: 200 and 800 MHz cavity maintenance. Inspection cavité RF Cavité 3 SMB-SE: Repair caniveaux. (5th to 9th January) EN-ACE D. Mcfarlane

14 BA4 Planning EN-ACE D. Mcfarlane

15 BA4 Main works (15th December to 13th January)
EN-EL: Cable Campaign (5th January to 22nd March) SPS BPM Upgrade phase 2 (Fibre Optics) (19th Dec to 11th Jan) eclairage securite (15th Dec to 18th Jan) TE-VSC: aC Coating Campaign (15th Dec to 17th March) Coldex interventions EN-HE: Lift maintenance (19th Dec 13:00 to 14:30) Test pont ECX4 et controle palonniers (15th December) EN-ACE D. Mcfarlane

16 BA5 Planning EN-ACE D. Mcfarlane

17 BA5 Main works (15th December to 13th January)
TE-VSC: aC Coating Campaign (15th Dec to 17th March) EN-HE: Renovation of the over head crane (ECX5) )15th Dec to 27th Feb) Lift Maintenance. (20th Dec. 09:30 to 11:00) EN-EL: De-cabling & Cabling Campaign. (15th Dec to 23rd March) EN-STI: SPS Scrapers and dumps - Inspection and maintenance UA9 Experiment maintenance EN-ACE D. Mcfarlane

18 ECX5/ECA5 Week 1 (12th to 16th 17th Dec)
General access only possible on Thursday and Friday EN/EA Construction of scaffolding to protect machine for EN/HE 15th & 16th EN/HE Transport of scaffolding from BA6. 15th EN/HE Installation of lifting points for old hoist 15th & 16th EN/EA Construction of Scaffolding for EN/EL. 15th & 16th DGS/RP Remove RP monitors PAXU501/502 15th EN/HE Remove covers & half of the shielding wall. 12th,13th & 14th (Store in BB5) SMB/SE Steel structure for Crane racks 15th, 16th Electrical lockout possible in the evening of the 14th. After TE/MSC have completed their magnet tests.

19 ECX5/ECA5 Week 2 (19th to 21st 23rd Dec)
EN/EA Construction of scaffolding & dust protection for EN/HE. 19th, 20th & 21st Through Passage is BLOCKED EN/EA Construction of Scaffolding for EN/EL. 19th EN/HE Installation of lifting points for old hoist 19th SMB/SE Drill holes for Crane cables 19th, 20th, 21st If possible TS September EN/HE Removal of old hoist 20th & 21st EN/HE Installation of new lifting hoist 22nd, 23rd

20 ECX5/ECA5 Week 2.5 (2nd 5th to 6th 7th Jan)
Through Passage is BLOCKED EN/HE Crane Renovation works EN/EL De-cabling EN/EL Containers for De-cabling SMB/SE Steel structure for Crane racks

21 BA6 Planning EN-ACE D. Mcfarlane

22 BA6 Main works (15th December to 13th January)
EN-HE: Lift & Monte charge maintenance (19th Dec) EN-CV: Cutting of the compressed air in the tunnel on the 5th January (part of crab cavity works) BE-RF: Crab Cavity installation work (15th Dec to 24th March) Scaffolding, Vacuum, Repair floor, Decabling Cryo prep work. EN-ACE D. Mcfarlane

23 Crab Cavity Planning https://edms.cern.ch/document/1738907/1
EN-ACE D. Mcfarlane

24 BA7 Planning EN-ACE D. Mcfarlane

25 BA7 Main works (15th December to 13th January)
EN-EL: Replacement of irradiated fibres in TI2 25th January to 8th February EN-CV: Puisard consolidation works 12th to 14th December (Monte-charge out of service) EN-ACE D. Mcfarlane

26 Please fill out your IMPACTs correctly!!!!!
As of today there are 300 IMPACTS. Please fill out your IMPACTs correctly!!!!! Correct intervention period: DO NOT LEAVE IT BLANK!!!!!!! (EYETS-SPS-2016/2017) Do not leave proposed schedule Blank!!!! I am not psychic!!! If you clone an IMPACT: Check the dates are correct Check the location is correct Check the description is correct (not just the title) Basically, CHECK EVERYTHING!!!! If you have already completed your IMPACT them please check that the dates in IMPACT match that of your planning and are also correct in the master schedule planning. If they are not then please contact me so that we can rectify the problem. EN-ACE D. Mcfarlane

27 Don’t forget to add Vacuum to your IMPACT if you need them.
Supervisor: Chiara Pasquino e-group: te-vsc-ivm-LS1 40-30: Alain Grimaud 40-30: Frederic Vial 40-30: Lindsay Morgan Fabre 40-30: Olivier Pangolin EN-ACE D. Mcfarlane