1 C2-SENSE WP2 Meeting Status of Task 2.4
Mert GENCTURK SRDC Ltd. Valenzano, Bari, October 2014 1

2 Step 1 – Use Case Analysis
Initial classes, interaction diagrams, responsibilities, attributes and associations Deadline: 15 September 2014 SRDC  SAGEM  AIT  LUTECH  PIAP Inputs were consolidated: 22 September 2014 2

3 Step 2 – Architectural Design
Design classes, packages, subsystems Deadline: 29 September 2014 (Extended to 6 October 2014) SRDC  SAGEM  AIT  LUTECH  PIAP Inputs were consolidated: 6 October 2014 3

4 Step 3 – Use Case Design Final and complete interaction diagrams
Deadline: 20 October 2014 SRDC  SAGEM AIT LUTECH PIAP Inputs will be consolidated: 27 October 2014 4

5 1st version of D2.3 Review by all partners and final version of D2.3 V1 Action plan Consolidated inputs: 27 October 2014 Reviews from all partners: 10 November 2014 Updated document: 17 November 2014 Final release to be sent to Commission: 28 November 2014 5

6 Step 4 – Class Design Final design classes with operation visibility, scope, dependencies etc. State charts Deadline: 8 December 2014 SRDC SAGEM AIT LUTECH PIAP Inputs will be consolidated: 15 December 2014 6

7 2nd version of D2.3 Review by all partners and final version of D2.3 V2 Action plan Consolidated inputs: 15 December 2014 Reviews from all partners: 22 December 2014 Final release to be sent to Commission: 26 December 2014 7