Presentation is loading. Please wait.

Presentation is loading. Please wait.

J. Wenninger, A. Macpherson BE-OP

Similar presentations


Presentation on theme: "J. Wenninger, A. Macpherson BE-OP"— Presentation transcript:

1 J. Wenninger, A. Macpherson BE-OP
Session Summary What else can go wrong J. Wenninger, A. Macpherson BE-OP What else can go wrong - Session Summary

2 What else can go wrong - Session Summary
The session Maximum Credible Incidents – J. Strait Risks due to UPS malfunctioning – H. Thiesen Impact of SEUs – M. Brugger Beam induced damage - what is a safe beam? – V. Kain Worst case beam incident causes and protection – B. Goddard Weaknesses of the MPS – B. Holzer Not the most re-assuring session… What else can go wrong - Session Summary

3 MCI – Maximum Credible Incident
Bus failures, ‘19th September style’, seem to be the most serious SC magnet failures that one can think of. Worst consequences to be expected if it affects: A DBF. Triplets. Matching/dispersion suppr. sections. Collateral damage can be severe for: DBFs. SC cavities. Injection kickers. Experiment beam tubes/inner detectors. In general for the (beam) vacuum.. Issue of the ‘praying hands’ joints in MQM - insufficient protection? Improve cryostat pressure relief Beam vacuum relief, fast(er) valves? To MQM From N’ line What else can go wrong - Session Summary

4 UPS for Circuit Protection Systems
C12L C34LR C12R IP8 IP7 UPS_UA83 UPS_RE82 UPS_RE78 UPS_UJ76 C2n C2n+1 4 redundant UPS systems to protect 1 sector 1 UPS in UA => IT, IPQ and IPD 1 UPS in RE => C12L to C34L (77 MB and 24 MQ) 1 UPS in RE => C34R to C12R (77 MB and 24 MQ) 1 UPS in UJ => IT, IPQ and IPD Must be tested very carefully (AUG tests) and time must be allocated for these tests ! What else can go wrong - Session Summary

5 What else can go wrong - Session Summary
UPS Issues In the event of a failure of the UPS: power abort is initiated. Consequences: Post-mortem data is lost. No control over the 60A orbit correctors. RB & RQ (13 kA) circuits are not protected during the power abort. Decision (after Chamonix): upgrade of the UPS facility for the QPS. QPS connected to the UPS systems from 2 different points. C12L C34LR C12R IP8 IP7 UPS_UA83 UPS_RE82 UPS_RE78 UPS_UJ76 What else can go wrong - Session Summary

6 What else can go wrong - Session Summary
Radiation - SEUs Following the failure of CV equipment near the CNGS target area after only hours of high intensity running >> raising awareness about SEUs issues  R2E group. A lot of work ongoing within R2E to: Assess fluence/dose values. Complete inventory of electronics. Identify problem areas and find solutions (re-location). Outlook for 2009/2010: 156 bunch operation : no showstopper was identified. No problems with MPS equipment, but BIC and collimation crates in UJ56, UJ14/16 must be monitored carefully. Equipment must be moved if necessary. Monitoring of radiation levels to evaluate simulation assumptions. What else can go wrong - Session Summary

7 EN/MEF/LPC – J.Coupard & K.Foraz
Shutdown 08-09 Key Drivers Maintenances Priorities Schedule Critical Points Activities – service areas, LSS, Arcs Modification of the underground integration of Point 7 (TZ76 and UJ76) – Priority 1 Objective: relocation of UPS and electronics from UJ76 to the TZ76  until end of June 09 Reason for these modifications: radiation levels – triggered by R2E LHC Performance – 04th Feb. 2009 EN/MEF/LPC – J.Coupard & K.Foraz

8 Radiation Levels – Evolution
!! Simulations Only !! !! Loss Assumptions !! !! Failure modes !!

9 What else can go wrong - Session Summary
Damage from beams Damage limits for typical ‘metallic objects’ seem to be consistent (better than order of magnitude) – see next slide. >> plastic deformation & shock waves may lead to lower limits! Damage limit for complex equipment (SC magnet, RF cavity) is rather poorly known, or not at all. >> experimental verification on SC cables would be more than useful. Recent simulation results show that: tertiary collimator can be damaged by pilot bunch at 7 TeV. a SC magnet can be sliced open over a length of ~ meter with a beam of a few MJ >> possible trigger of a sector 34-like incident ! Even our ‘safe’ beams are not safe under all condition. What else can go wrong - Session Summary

10 What else can go wrong - Session Summary
Energy Scales 2 MJ ! 100 1k 10k 100k 1M 10M 100M 1T Pilot b 360 J Nominal b 8.3 kJ ‘Safe’ Beam Limit p 72 kJ Nominal beam 23.3 MJ Stored Energy (J) 450 GeV ‘156 b’ physics 0.5-1 MJ 5 TeV 100 1k 10k 100k 1M 10M 100M 1T Pilot b 4 kJ Nominal b 92 kJ ‘Safe’ Beam Limit - 1.7x1010 p 13.6 kJ Nominal beam 258 MJ Stored Energy (J) ‘156 b’ physics 5 -10 MJ What else can go wrong - Session Summary

11 What can go wrong with beam
… many things !!!! The MPS is designed to cope with the ‘worst’ scenarios: High reliability design for critical components. Equipment and beam monitoring (reaction times). Redundancy of the protection where possible. Beam loss monitors are the last line of defense! We are now analyzing more severe cases: Multiple failures. ‘Bird strikes’ : a single cause takes out more than one component. Birdstrikes – single causes can lead to multiple failures What else can go wrong - Session Summary

12 3.) What can go wrong ? a rough statistics of 20 years HERA
Injection: too early (during magnet cycle) too late (during accleration) into a filled bucket (timing problem) with kicker/septum off with magnet at transferline off after wrongly applied injection correction ... why ??? with closed collimators with closed vacuum valve with wrong magnet polarity (after maintenance day) Acceleration: failure of persistent current compensation errors in ramp correction tables tune jump during polarity switch of a quadrupole collimators too close to the beam head tail problems (chromaticity correction) magnet failures Luminosity: aperture limitations due to RF fingers beam quality issues: beam beam spoils the emittance (up to beam losses at the aperture limit) orbit correction loop: coil at limit or off dedicated beam orbit steering coasting beam (rf problems) failure at dump kicker failure of dump timing system collimator control defect (radiation problem) error in BLM / BPM signal processing (server) vacuum valve closes during luminosity run Some of those failures cannot happen at the LHC, prevented by the MPS ! All of them have been considered for the LHC. The LHC MPS strategy is based on a highly reliable and well tested interlock hardware network designed to catch ‘all’ failure scenarios. Some ‘flaws’ of Tevatron, HERA and SPS MPS systems have been avoided at the LHC. Nota bene: each of these errors lead to a beam loss alarm or quench

13 What else can go wrong - Session Summary
LHC Natural Predators Some specimens from the top of the food-chain… What else can go wrong - Session Summary

14 What else can go wrong - Session Summary
LHC Natural Predators Operators and experts are able to trigger a large palette of actions/failures that stress the MPS or that open cracks in our armor. Some ‘errors’ are inevitable when tuning the machine ! The LHC is not a turn-key system, commissioning the LHC is R&D !! Expert actions and errors may disable part of the MPS functions: leads to the worst possible failures, in particular a priori rare ‘combinations’. Follow procedures, log what you do. Think twice, consult a colleague / MPS expert. Track changes. Test, test, test. What else can go wrong - Session Summary

15 The Ultimate (and popular) MPS Question
“What do we do if the dump doesn’t react to a programmed request” Possible answers are Call Bruno and Etienne in to fix the problem. Cut RF Revolution Frequency to LBDS, to provoke synchronous dump. Force access system door to produce asynch. dump trigger. Start blowing beam up slowly with tune kicker, or transverse damper. Scrape beam slowly away with collimators, while staying below quench limit. Provoke a software interlock. We must agree and maintain a procedure for the CCC… What else can go wrong - Session Summary

16 The last word for the ‘scary’ session
The LHC is a difficult and ‘extreme’ collider, the risks have become very concrete on Sept. 19th. To cope with the risks of beam operation we have designed a large and reliable MPS, and the one thing that we absolutely need is TIME to test it very very carefully ! It will not be easy, but there is no reason to panic ! What else can go wrong - Session Summary


Download ppt "J. Wenninger, A. Macpherson BE-OP"

Similar presentations


Ads by Google