Presentation is loading. Please wait.

Presentation is loading. Please wait.

The ISOLDE Solenoidal Spectrometer project

Similar presentations


Presentation on theme: "The ISOLDE Solenoidal Spectrometer project"— Presentation transcript:

1 The ISOLDE Solenoidal Spectrometer project
Robert Page

2 Spectrometer Systems for TSR@ISOLDE
The original plan: Move TSR to ISOLDE UK STFC funded project ~£5M investment Internal spectrometer External spectrometer Start January 2015 Completion March 2019

3 Physics Motivation

4 Solenoidal spectrometer concept
z θcm θlab vlab v0 Vcm CM Energy: CM Angle:

5 Spectrometer Systems for TSR@ISOLDE
Challenges: TSR not in CERN MTP

6 Internal Spectrometer
Plan to exploit Si detector system on

7 Spectrometer Systems for TSR@ISOLDE
Challenges: TSR not in CERN MTP ISS on XT02 beam line No TSR – beam quality (beam manipulation) No funding for magnet

8 Magnet procurement Magnet available from Brisbane (UQ)
OR66 4T ex-MRI magnet “Active shield” reduces stray field Installed February 2003 Discharged then warmed ~2013 Funding request (STFC/UoL) June 2015

9

10 Magnet in Wesley Hospital, Brisbane, September 2015

11 Magnet procurement Magnet available from Brisbane (UQ)
OR66 4T ex-MRI magnet “Active shield” reduces stray field Installed February 2003 Discharged then warmed ~2013 Funding request (STFC/UoL) June 2015 Magnet ordered November 2015

12 Magnet leaving Brisbane hospital February 2016

13 sailing across the globe…
Calicanto Bridge

14 sailing across the globe…
Sarah

15 & arriving at CERN, April 2016

16 Preparation & cleaning
magnet bore ~90 cm diameter

17 Vacuum test

18 Cooling down, January 2017 Thanks to CERN cryogenics team, Patrick Retz, ...

19 Energising, February 2017 ramped up to 2.75 T, held for 1 hour then ramped down

20 In the ISOLDE Hall ~18 tons – too heavy for ISOLDE hall crane!

21 on its stand, aligned & connected

22 Stray field

23 Magnetic shielding design
Jérémie Bauche, Kevin Buffet & Yacine Kadi (CERN)

24 ISS inside the magnet beam

25 ISS Mechanical Design Target & detector drive systems
Hexagonal Si tube ~50 cm long 4 DSSDs per face ASIC readout Cooled

26 ISS Si detector module 6 R3B ASICs 0 – 50 MeV 128 channels
100 MHz time stamp daisy-chained

27 Si detectors DSSDs: 1 mm thick x: 128 × 0.95 mm y: 11 × 2 mm

28 132Sn(d,p) with TSR beam quality
simulations by Marc Labiche

29 PCBs

30 PCB trial assembly

31 Si tube cross section

32 Reconstructing the z position
CM Energy: Algorithm devised by P. Butler Implemented in GEANT4 by M. Labiche

33 Exploitation plans early exploitation before LS2
stable & long-lived isotope running during LS2 + commissioning of the ISS Si array + commissioning of gas recoil detector… followed by ISS running after LS2

34 Conclusions Design work well advanced First Si DSSDs delivered
Prototype tests under way Magnet recommissioned ISOLDE integration continuing


Download ppt "The ISOLDE Solenoidal Spectrometer project"

Similar presentations


Ads by Google