Office of Nuclear Materials Safety and Safeguards
NRC’s Response to GAO Materials Licensing Audit and Update on Licensing and Security Initiatives Duncan White Office of Nuclear Materials Safety and Safeguards November 7, 2016
2
Topics GAO’s 2007 Material Licensing Investigation
GAO’s 2016 Material Licensing Audit and Investigation NRC’s Initial Response to Current GAO Investigation Current Activities - Working Groups COMJMB
3
GAO 2007 Licensing Investigation GAO-07-0138T
Obtained valid NRC license using fake company Withdrew Agreement State application due to State’s plans for a site visit Ordered sufficient devices to obtain category 3 quantity of material Report and testimony July 12, 2007 Three recommendations by GAO Improve guidance for screening new applicants Conduct periodic oversight of license reviewers Prevent the counterfeiting of NRC licenses NRC considers all the recommendations closed
4
Actions in Response to 2007 Audit
Pre-Licensing Guidance Interim Guidance issued June 12, 2007 Final Guidance issued September 2008 SECY GAO Action Plan August 25, 2007 SRM issued September 18, 2007 IERP report issued March 11, 2008 MPWG report issued October 23, 2008
5
Status of NRC Actions from 2007 GAO Audit
94 individual tasks identified 87 tasks completed and closed via memo with management review 7 tasks still open 6 related to completion of NUREG-1556 revisions 1 related to completion of Management Directives 5.6, 5.9 and 5.10 Open tasks related to long term projects with other drivers
6
2016 GAO Audit - Timeline Determine if vulnerabilities identified during 2007 investigation were addressed by the regulatory framework and improvements Started April 2014 Investigation portion conducted February to October 2015 GAO notified NRC of investigation results in October 2015 NRC reviewed Statement of Facts in December 2015 Draft report provided: May 9, 2016 NRC provided comments: June 14, 2016 Final Report released: July 15, 2016
7
Recommendations from GAO-16-330
Take steps needed to include Category 3 sources in NSTS and add Agreement State category 3 licenses as quickly as reasonably possible At least until such time that category 3 sources can be verified using LVS, require that transferors of Category 3 quantities confirm the validity of the recipient’s license with the appropriate regulatory agency before the transfer until such time such verification can be done using LVS Consider requiring that an onsite security review be conducted for all unknown applicants of category 3 licenses to verify that the applicant is prepared to implement the required security measures before taking possession of licensed radioactive materials
8
Initial NRC Response to GAO Investigation October 2015
Notified affected parties Regions OAS and Agreement States Requested Agreement State that issued license to GAO: Revoke license Requested notification of vendors of revoked license Conduct self-assessment and root cause analysis Briefed Commissioner’s Chiefs of Staff Briefed Agreement States
9
Initial NRC Response to GAO Investigation November 2015
Received preliminary self-assessment/root cause analysis from Agreement State that issued license Held two webinars on pre-licensing guidance, site visits, RSRM checklist for Regional staff Met with GAO to provide additional responses to their additional questions
10
Initial NRC Response to GAO Investigation December 2015
Briefed Executive Director of Operations Issued Commissioner’s Assistants Note to Commission Briefed Commissioner Material TAs and Chiefs of Staff Requested NRC and Agreement State members for working groups to address GAO concerns Provided draft charters Reviewed GAO’s draft Statement of Facts and provided detail comments
11
Initial NRC Response to GAO Investigation December 2015
Held third webinar on pre-licensing guidance, site visits, RSRM checklist for Agreement State staff Agencies subject to investigation discussed experiences with GAO application and site visit Met with GAO to discuss individual comments on Statement of Facts and provided additional information
12
Long Term NRC Response to GAO Investigation - 2016
Two working groups to address GAO concerns Enhancements to Pre-Licensing Guidance License Verification and Transfer of Category 3 Sources Working groups met January to June 2016 Draft reports reviewed in July 2016 Final reports reviewed in October 2016 Issued temporary guidance on RSRM checklist Revision of RSRM checklist still in progress
13
NRC Response to Release of GAO Report July 2016 to present
Notifications Issued portions of NRC communication plan to Agreement States Blog post Public webpage Links to public version of working group charters Q&As Responded to media inquiries September 19, 2006 Letter from Chairman to Congress on NRC’s plan of action COMJMB issued July 15, 2016
14
Enhancements to Pre-Licensing Guidance
Perform gap analysis based on self-assessments and other information Revise the pre-licensing guidance Identify practices to minimize opportunities for malevolent intent Delivering of licenses combined with site visit Require Category 3 applications to have all security and safety equipment in place Practicality of issuing a license for calibration/testing Improvements to Training
15
Pre-Licensing Guidance - Enhancements Under Consideration
Several revisions to pre-licensing checklist Complete license review prior to site visit Discontinue hand delivery of licenses Enhance training during TTC training courses and qualification process Track denied/voided/withdrawn applications of “unknown” applications Require safety and security equipment in place prior to issuing license for unknown applicants
16
License Verification and Transfer of Category 3 Sources
Enhancement Strategies Change presumption of validity of license Require validation of licenses in LVS or issuing regulatory agency Inventory tracking of category 3 sources Implementation Strategies Interim measurements Rulemaking Compatibility and enforcement requirements Guidance development Any problems created with only one valid license
17
License Verification and Transfer of Category 3 Sources – Enhancements Under Consideration
Require verification of Category 3 licenses through LVS or regulatory agency. Include all Category 3 Agreement State licenses in WBL to facilitate electronic verification of licenses through LVS. Enhance Category 3 source accountability through NSTS or other method.
18
Commission Direction: COMJMB-16-001
Addresses all Category 3 source security and accountability efforts underway License process enhancements Pre-licensing guidance and RSRM checklist Require safety and security equipment in place prior to license License verification and transfer of sources License verification through LVS or regulator Category 3 sources in WBL and NSTS Part 37 program review Security measures for category 3 sources Reevaluation of aggregation definition
19
Specific Recommendations from COMJMB-16-001
Methods for verification of license’s validity Category 3 sources in NSTS Address GAO recommendations on source accountability Vulnerability assessment Regulatory impact analysis of cost/benefit Discussion on actions that do not require regulatory changes and monitoring their implementation through IMPEP Any other factors
20
Action Plan for COMJMB-16-001
Additional direction Use Part 37 program review to inform evaluation Assess the risk of aggregation of category 3 sources into category 2 quantities Collaborate with all affected stakeholders NRC/Agreement State working group Commission Paper due August 2017.