Presentation is loading. Please wait.

Presentation is loading. Please wait.

McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved.

Similar presentations


Presentation on theme: "McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved."— Presentation transcript:

1 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved.

2 Materials Requirements Planning
Chapter 18 Materials Requirements Planning

3 Material Requirements Planning
18-3 Material Requirements Planning Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced Dependent demand drives MRP MRP is a software system 3 3

4 Example of MRP Logic and Product Structure Tree
18-4 Example of MRP Logic and Product Structure Tree Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed Product Structure Tree for Assembly A Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day B(4) E(1) D(2) C(2) F(2) D(3) A Total Unit Demand Day A Day B (Spares) Day D (Spares) 4 4

5 18-5 First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10. LT = 1 day 5 5

6 LT = 2 Spares B(4) E(1) D(2) C(2) F(2) D(3) A
18-6 Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time. LT = 2 Spares B(4) E(1) D(2) C(2) F(2) D(3) A 4x50=200 6 6

7 18-7 Finally, repeating the process for all components, we have the final materials requirements plan: B(4) E(1) D(2) C(2) F(2) D(3) A spares Part D: Day 6 6 6

8 Master Production Scheduling (MPS)
18-8 Master Production Scheduling (MPS) Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan (Product Groups) MPS (Specific End Items) 8 8

9 No schedule changes allowed within this window Moderately Firm
18-9 Types of Time Fences Frozen No schedule changes allowed within this window Moderately Firm Specific changes allowed within product groups as long as parts are available Flexible Significant variation allowed as long as overall capacity requirements remain at the same levels 9 9

10 Forecast and available
18-10 Example of Time Fences Exhibit 15.5 8 15 26 Weeks Frozen Moderately Firm Flexible Firm Customer Orders Forecast and available capacity Capacity 10 10

11 Material Requirements Planning System
18-11 Material Requirements Planning System Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times 11 11

12 Secondary reports Primary reports Exception reports Planning reports
18-12 Firm orders from known customers Forecasts of demand from random Aggregate product plan Bill of material file Engineering design changes Inventory record file transactions Master production Schedule (MPS) Material planning (MRP computer program) Primary reports Secondary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control 11 11

13 Bill of Materials (BOM) File A Complete Product Description
18-13 Bill of Materials (BOM) File A Complete Product Description Materials Parts Components Production sequence Modular BOM Subassemblies Super BOM Fractional options 13 13

14 Inventory Records File
18-14 Inventory Records File Each inventory item carried as a separate file Status according to “time buckets” Pegging Identify each parent item that created demand 14 14

15 Planned orders to be released at a future time
18-15 Primary MRP Reports Planned orders to be released at a future time Order release notices to execute the planned orders Changes in due dates of open orders due to rescheduling Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule Inventory status data 15 15

16 18-16 Secondary MRP Reports Planning reports, for example, forecasting inventory requirements over a period of time Performance reports used to determine agreement between actual and programmed usage and costs Exception reports used to point out serious discrepancies, such as late or overdue orders 15 15

17 Additional MRP Scheduling Terminology
18-17 Additional MRP Scheduling Terminology Gross Requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release 19 19

18 A(2) B(1) D(5) C(2) X C(3) MRP Example
18-18 MRP Example A(2) B(1) D(5) C(2) X C(3) Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10 18 18

19 18-19 X A(2) It takes 2 A’s for each X 21 21

20 18-20 X A(2) B(1) It takes 1 B for each X 21 21

21 18-21 X A(2) B(1) C(3) It takes 3 C’s for each A 21 21

22 18-22 X A(2) B(1) C(3) C(2) It takes 2 C’s for each B 21 21

23 18-23 X A(2) B(1) C(3) C(2) D(5) It takes 5 D’s for each B 21 21

24 Closed Loop MRP Yes Production Planning Master Production Scheduling
18-24 Closed Loop MRP Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning No Feedback Realistic? Feedback Execute: Capacity Plans Material Plans Yes 22 22

25 Lot Sizing in MRP Programs
18-25 Lot Sizing in MRP Programs Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC) Which one to use? The one that is least costly! 23 23

26 18-26 Question Bowl Which type of industry has only “medium” expected benefits from the use of MRP? Assemble-to-stock Fabricate-to-stock Assemble-to-order Fabricate-to-order Process Answer: e. Process 7

27 Never lose sight of the aggregate plan
18-27 Question Bowl To ensure good master scheduling, a master scheduler must do which of the following? Never lose sight of the aggregate plan Identify and communicate all problems Be involved with customer order promising Be visible to all levels of management All of the above Answer: e. All of the above (Correct answer can also include objectively trade off manufacturing, marketing, and engineering conflicts and include all demands from product sales, warehouse replenishment, spares, and interplant requirements.) 7

28 Answer: b. Control flow through the production system
18-28 Question Bowl The purpose of a “time fence” is which of the following? Make sure the cows don’t get out of the barn Control flow through the production system Maximize sales to retailers All of the above None of the above Answer: b. Control flow through the production system 7

29 Which of the following is an objective under an MRP system?
18-29 Question Bowl Which of the following is an objective under an MRP system? To improve customer service Minimize inventory investment Maximize production operating efficiency All of the above None of the above Answer: d. All of the above 7

30 18-30 Question Bowl Which of the following is one of the three main inputs into an MRP system? BOM file Exception report Planning report All of the above None of the above Answer: a. BOM file (Correct answer can also include Master Schedule and Inventory Records File.) 7

31 None of the above Answer: c. Time bucket
18-31 Question Bowl An MRP program accesses the status of a job according to specific time periods called which of the following? Peg record Time fence Time bucket Time clock None of the above Answer: c. Time bucket 7

32 Renegotiate the due date and reschedule Subcontract to an outside shop
18-32 Question Bowl In MRP, workload per work center can be determined. When the work capacity is exceeded, which of the following options can be implemented to correct the imbalance of workload? Work overtime Renegotiate the due date and reschedule Subcontract to an outside shop All of the above None of the above Answer: d. All of the above (Correct answer can also include selecting an alternative work center and rescheduling the work at a different time.) 7

33 Answer: e. All of the above
18-33 Question Bowl Which of the following are reasons why a Lot-For-Lot (L4L) method of lot sizing can be used in an MRP application? Minimizes carrying costs Sets planned orders to exactly match the net requirements Produces exactly what is needed Does not carry any units over into future periods All of the above Answer: e. All of the above 7

34 18-34 End of Chapter 18


Download ppt "McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved."

Similar presentations


Ads by Google