Download presentation
Presentation is loading. Please wait.
Published byMoris Knight Modified over 6 years ago
1
Joint Parking Task Force Update Procurement & Strategic Sourcing
Request for Proposal and Specifications for Construction Manager for STEM Innovation Center October 31, 2017 11
2
Welcome and Introduction
Kimberly Tomaszewski, Senior Buyer Allen Gigliotti, Project Manager Architect Not Awarded Other University Attendees Sign-in Sheet will be posted to the website. A copy of this presentation will be posted to the website
3
About Wayne State University:
Was founded in 1868 Our Mission is to create and advance knowledge, prepare a diverse student body to thrive, and positively impact local and global communities Has more than 27,000 students Has 13 colleges and schools Offers more than 380 academic programs including bachelor’s, master’s and doctoral degrees Classified by the Carnegie Foundation for the Advancement of Teaching as a Research University, Very High research activity (RU/VH) (
4
ListServe Services: Bid notices are sent only to those Construction Managers registered to receive them via our Bid Opportunities Listserve service. To register, go to and click on the “Join our Listserve” link at the top of the page.
5
Competency of Bidders Please Note: The competency and responsibility of Bidders will be considered in making the award. The Owner does not obligate himself to accept the lowest or any other bids. The Owner reserves the right to reject any and all bids and to waive any informalities in the Proposals
6
RFP Opportunity The University is soliciting proposals for Construction Management Services for the STEM Innovation Center, WSU Project For the purposes of this proposal, a total construction budget of $32M has been presumed We are seeking superior quality & competitive pricing Specifications are in RFP and any Drawings on the Website
7
Calendar of Events Mandatory Pre-bid meeting - November 7, 2017 at 3:00 pm. Questions due to Procurement & Strategic Sourcing - November 10, Noon Delivery of Proposals - November 22, 2017 by 2:00 pm Time of Completion - As Stated in Final Contract Short List Announced Week of December 1, 2017 Post Bid Interviews tentatively scheduled for December 4, 2017 Selection during the Week of December 11, 2017 Contract Negotiations and Execution Week of December 18, 2017
8
Bids Due Sealed Bids are due November 22, 2017 at 2:00 pm
Delivered to Procurement & Strategic Sourcing, 5700 Cass Avenue, 4th Floor – Suite 4200, Detroit, MI 48202 We require an original plus five copies (6 total) of your proposal. An electronic version is required, which should be submitted to Proposals are limited to 30 pages total, one sided. Prices and other requested data must be on Schedule C.1, Fee Proposal, and Schedule C.2, Level of Effort Proposals must acknowledge all Addenda including Pre-bid Meeting Minutes
9
Project Schedule Schematic Design Development Completion March 2018
Design Development Completion July 15, 2018 Construction Document Completion April 1, 2019 GMP Change Order Completion of DD by October 15, 2018 Construction beginning no later than February 1, 2019 Final Completion June 1, 2020
10
RFP Information Liquidated Damages of $500.00 per day
Project Delivery Method: Construction Management Construction Manager Deliverables and Services Questions on CM Deliverables?
11
Proposal Requirements
30 Page Limit, 1 side, 11 pt font Executive Summary Firm Overview Relevant Experience Construction Manager’s Personnel Project Management, Scheduling, Changes in the Work Proposed Fee Basis and Fee Proposal
12
Selection Process and Evaluation Criteria
Proposals received in response to this RFP The quality and comprehensiveness of the plans provided The qualifications of the proposed project team A check of references Fees will be considered to determine best value
13
Prevailing Wage Rates Schedule will be provided upon request
All Contractors and Subcontractors Certified Payroll Required Sworn Statements Required
14
Schedules to be submitted with Vendor Proposals
Schedule A: Proposal Certification Schedule B: Insurance Requirements Schedule C1: Fee Proposal Form for Construction Manager Schedule C2: Level of Effort Table Schedule D: Summary of Questionnaire
15
RFP Appendices Appendix 1, WSU Campus Map / Available Parking
Appendix 2, Pre-bid Registration Form Appendix 3, WSU Construction Management Service Sample Contract Appendix 4, General Conditions of Construction Appendix 5, Supplementary General Conditions of Construction Appendix 6, Contract for Design Professional Services Appendix 7, Payment Package Document Requirements Appendix 8, Project Site Map
16
Reminders The UNIVERSITY reserves the right to accept, reject, modify, and/or negotiate any and all proposals All information related to this RFP will be posted to the Project site at If a List Serve has been established, those wishing notifications must register as listed in the RFP All questions concerning this Request for Proposal are to be directed to Kimberly Tomaszewski, Senior Buyer, ; A copy should be submitted to Leiann Day, Associate Director, ; Do not contact Facilities Planning & Management or other University Units directly, as this may result in disqualification of your proposal
17
Joint Parking Task Force Update
?? Questions ?? 11
18
Joint Parking Task Force Update Procurement & Strategic Sourcing
Request for Proposal and Specifications for Construction Manager STEM Innovation Center October 31, 2017 Kimberly Tomaszewski Senior Buyer 14 11
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.