Overview of the Frascati Production Facilities
Chamber assembly Developed and implemented in Frascati since many years (BML98, BML96) Now finalized to the final decisions made on the chamber Wiring Machine At the end of ’98 started a program of design and development of a fully automated machine.
2
Wire tension measurement
A system, based on electrostatic method, capable of measuring up to 16 tubes at a time has been developed and built. Gas leak and HV test station A system capable of measuring 64 tubes has been developed and built Wire-tube position measurement The EMMI, developed and built by Rome and Pavia, has been adopted
3
A large hall in which the clean room is located is available Storage
The above listed facilities are housed in separate areas inside a single large clean room. Hall Space A large hall in which the clean room is located is available Storage Storage (and transport) structures have been designed and 2 prototypes have been built
4
Cosmic Ray Test Station
It is under construction Chamber gas leak test stand It has to be designed and realized Data Base The Data Base system is being implemented
5
Module 0 Module 0 is being built 2 layers - one on each side – glued
praxial alignment platforms glued Produced > 200 tubes The construction is going on with continuity. Interventions for the optimization of the performances are postponed
6
Module 0 After full experience with module 0 effort for the optimization before moving to full speed production