Presentation is loading. Please wait.

Presentation is loading. Please wait.

Presentation to the Portfolio Committee 17 AUGUST 2011

Similar presentations


Presentation on theme: "Presentation to the Portfolio Committee 17 AUGUST 2011"— Presentation transcript:

1 Presentation to the Portfolio Committee 17 AUGUST 2011

2 SUMMARY OF THE DEPARTMENT’S APPROPRIATED ALLOCATION (FIRST QUARTELY REPORT – 30 JUNE 2011
Financial overview (Summary) Appropriated amount R billion Actual expenditure (30/06/2011) R million Variance R4.047 billion Spending represents 16% of the overall final Appropriation.

3 FIRST QUARTELY REPORT – 30 JUNE 2011
Financial overview (1st Quarter) Appropriation (1st Quarter) R million Actual expenditure (30/06/2011) R million Variance R million Spending represents 81.6% of Appropriation for the 1st Quarter.

4 PROGRAMME 1: ADMINISTRATION
Appropriation for the year R1,245 billion Appropriation (1st Quarter) R million Actual expenditure (30/06//2011) R million Variance R million Actual spending recorded at 69.1% of Appropriation of the 1st Quarter and 13% overall final Appropriation.

5 2011/12 ROLL OVERS REQUEST CAPITAL PROJECTS Washington R 51.3 million London: Highveld R 15.7 million London: South Africa house R million Abuja R 12.5 million TOTAL R 82.3 million Approval awaited from National Treasury

6 PROGRAMME 1: ADMINISTRATION Sub programme: Capital Budget
Expenditure during the first quarter was R 4.4 million Achievements during first quarter Abuja completed and handed over Washington project: City Council and Utility Company approvals obtained Package of early works for the Chancery project approved Swing space fit-out Contractor appointed London Projects Elevator installations completed and commissioned Contractor for refurbishment of Highveld appointed Dar es Salaam and Lilongwe projects Pre qualification of Contractors commenced.

7 PROGRAMME 1: ADMINISTRATION Sub programme: Capital Budget
Expenditure on the Capital Budget Construction project expenditure during the second quarter is forecasted at R 42 million on the following projects: Abuja, payment of final account and release of retention money. Washington project: Payment for building permits, City Council and Utility Company fees and deposits. Payment to Contractor for early works, to commence on 15 August 2011, completed in November 2011 Payment to Contractor for the fit out of swing space which commenced first week of August 2011, work to be completed November 2011 London Projects Elevator installations payment of final account Commencement fee and progress payments to contractor for refurbishment of Highveld, work commenced May 2011, to be completed January 2012.

8 PROGRAMME 1: ADMINISTRATION Sub programme: Capital Budget
The Department is pursuing the acquisition of properties in the following locations: London, Cavendish Close, Deputy High Commissioners Residence R 50 million London, South Africa House, Chancery R 80 million Genève, Official Residence R 30 million

9 PROGRAMME 2: INTERNATIONAL RELATIONS
Appropriation for the year R billion Appropriation (1st Quarter) R million Actual expenditure (30/06/2011) R million Variance R million Actual spending recorded at 86% of the appropriation for the 1st Quarter and 21% for the overall final appropriation

10 PROGRAMME 3: STATE PROTOCOL & PUBLIC DIPLOMACY
Appropriation for the year R211.5million Appropriation (1st Quarter) R million Actual expenditure (30/06/2011) R million Variance R million Actual spending recorded at 82.3% of Appropriation for the 1st Quarter and 21% for the overall final Appropriation.

11 PROGRAMME 4: INTERNATIONAL TRANSFERS
Appropriation for the year R million Appropriated for (April to June) R million Actual expenditure (as at 30/06/2011) R million Variance (R million) Actual spending recorded at 102.% of Appropriation for the 1st Quarter and 1% for the overall final Appropriation. Variance analysis The following payments were processed post 15/08/2011 SADC R 41.7 million UN MEMBERSHIP R 14 million Commonwealth R million Total R million

12 Thank you


Download ppt "Presentation to the Portfolio Committee 17 AUGUST 2011"

Similar presentations


Ads by Google