AAU/AUA Association of African Universities
Association des Universités Africaines Serving Higher Education in Africa Au Service de l’Enseignement Supérieur en Afrique Explanation of logo African continent becomes green.
2
ACE PERFORMANCE ASSESSMENT RESULTS 2014-2017
By Jonathan Mba ACE Project Coordinator
5
ACE Workshop Participants
6
ATTENDANCE AT 7 WORKSHOPS
ABUJA WORKSHOP YAOUNDE WORKSHOP BANJUL WORKSHOP COTONU WORKSHOP ACCRA WORKSHOP ABIDJAN WORKSHOP LAGOS WORKSHOP 120 Participants 110 participants 142 participants 175 participants 190 participants 198 participants 215 participants 47 Completed form 55 (45 English; 10 French) Completed Form 134 (110 English; 24 French) Completed Form 126 (108 English; 18 French) Completed Form 124 (104 English; 20 French) Completed Form 153 (103 English; 53 French) Completed Form 180 (112 English; 68 French) Completed Form Online Response Rate: 39% Online Response Rate: 50% Online Response Rate: 94% Online Response Rate: 72% Online Response Rate: 65% Online Response Rate: 77% Online Response Rate: 84%
7
FEEDBACK ON LOGISTICS
8
FEEDBACK ON WORLD BANK
9
FEEDBACK ON WORLD BANK
10
FEEDBACK ON AAU
11
FEEDBACK ON NATIONAL GOVERNMENTS
12
ACE PROJECT SATISFACTION
Satisfaction Item Average Rate Abuja Yaounde Banjul Cotonu Accra Abidjan Lagos I feel proud of being part of this project 4.5 3.6 4.7 4.4 I am satisfied with the implementation progress 3.5 3.9 3.8
13
ACE PROJECT SATISFACTION
14
COMMENTS & SUGGESTIONS
“An addendum on creating private/business/industry partnerships with clear milestones should be done by the world Bank and AAU to ensure that the foundation for sustainability is laid before project winds up”. “Au titre des suggestions, je souhaite que la Banque mondiale mette en place des fonds additionnels pour soutenir les CEA à la fin du projet”. “The help desk session with the experts were very useful and highly commendable”. “We need to work more on sustainability”. “Programmer très vite les sessions sur la gestion financière et la passation de marchés”.
15
POTENTIAL IMPLEMENTAION RISKS
16
POTENTIAL IMPLEMENTAION RISKS
17
POTENTIAL IMPLEMENTAION RISKS
18
CONCLUSION Online completion of feedback form has been improving.
The project implementation risk though low is increasing. ACEs are concerned about project sustainability. Project satisfaction has remained virtually the same over time. Feedback on WB, AAU and Governments is positive.