SPS LS1 Planning meeting (No.34) 16/04/14

Similar presentations


Presentation on theme: "SPS LS1 Planning meeting (No.34) 16/04/14"— Presentation transcript:

1 SPS LS1 Planning meeting (No.34) 16/04/14
David Mcfarlane

2 Topics Lifts and Monte-charges.
Dates for changing the alarm systems in the lifts. Bank holidays. Detection Incendie tests. AUG tests. GE/ASE Access tests. Cleaning campaign dates. Main works in each of the points. EPC tests of the Auxiliary Converters. The end of LS1. Planning. False floors open in the BAs. E.C.Rs. Access rights and safety equipment. Important Information. A.O.B.

3 Lift Maintenance Mar/Apr/May/ June
AS Ascenseurs have to change the alarm systems. This will put each lift out of service will this is done (the zone however is NOT blocked) (BA2,3,4,5 and 6) AS Ascenseurs propose : Avril :  du lundi 14 au jeudi 17 avril  ( 4 ascenseurs) OU du mardi 22 au vendredi 25 avril  (4 ascenseurs) Mai :  du  lundi 5 au vendredi 9 mai  (5 ascenseurs) OU du mardi 13  au vendredi 16 mai (4 ascenseurs)

4 Changing alarm system in the lifts (The lift will be out of service for the entire day)
BA2 – Tuesday the 13th May BA3 – Tuesday the 22nd April BA4 – Friday the 16th May BA5 – Wednesday the 14th May BB5 – Thursday the 15th May BA6 – Wednesday the 23rd April BA7 – Friday the 25th April BA80 – Thursday the 24th April TT70 – Wednesday the 7th May Although the lift is out of service the Zone is NOT closed!

5 Bank holidays (CERN is closed and no access into SPS)
Friday the 18th April. (Good Friday) Monday the 21st April. (Easter Monday) Thursday the 1st May. (Labour Day) Thursday the 29th May. (Ascension Day) Monday the 9th June. (Whit Monday)

6 Detection Incendie tests
The sirens will be tested after 17:30 on the final day of the tests in each zone!

7 AUG tests

8 GE/ASE Access tests

9 Cleaning campaign

10 BA1 main works Finish the works in TT10
Mainly Alignment and Vacuum. Reinstallation of the beam line and equipment in LSS1 GE/ASE Access tests 23rd June

11 BA2 main works Replacement of magnet MDLV.211512 in TT20
Repair works on the floor (Done) Replace magnet (Thursday the 17th April.) Replacement of Collimator TCE Replacement Done EN/EL cabling campaign Ongoing until the end of April Changing alarm system in the lift Tuesday the 13th May AUG tests 14th May GE/ASE Access tests 9th June Cleaning campaign 23rd to the 27th June

12 BA3 main works New cable trench to be built between CCC and BA3 (surface) Still waiting for the revised quote. EN/EL Câblage nouveau câbles secours SPS BK3. 17th April(ZONE BLOCKED) (Lift maintenance not affected) Fibre optic works in the pit area 22nd April to the 20th May AUG tests 15th May GE/ASE Access tests 10th June Cleaning campaign 16th to the 20th June

13 BA4 main works Installation of 2 pumps for crab cavities AUG tests
19th May GE/ASE Access tests 10th and 11th June Cleaning campaign 12th to the 16th May

14 BA5 main works Re-installation of 4 coated magnets due to vacuum leaks. Beginning of May?? Transport will be moving all of the equipement stored in ECX5 back to LSS1 (via BA6) Starting on Monday the 7th April. THEY HAVE PRIORITY IN THIS AREA!!! BE/BI works. AUG tests 20th May GE/ASE Access tests 12th June Cleaning campaign 19th to the 23rd May

15 BA6 main works Replacement of the crane in BA6 (surface)
22nd to 25th April ATLAS works on cooling towers (BA6 water OFFLINE) 22nd April to the 13th May. AUG tests 21st May GE/ASE Access tests 13th June Cleaning campaign 26th to the 30th May

16 EPC tests of the Auxiliary Converters
With this planning, OP can start the commissioning of the Software with a 1 week delay from our activities: e.g, OP tests for BA2 could start on 9th June.    What we need: The magnet interlocks shall be tested in May by MPE (R.Mompo/P.Dahlen): support from EPC is requested during this period, Services shall be present in each BA in time: water (magnet + surface building), no consignation (except BA1 until end of June), A general signalisation that some tests are ongoing: coordination EPC/MSC, EIS ( from past experiences, this is a difficult point for us during our tests, especially for TI2/TI8. I propose that when the planning is agreed on, Marc Tavlet will be contacted by EPC.

17 The end of LS1

18 Planning

19

20

21

22

23

24

25

26 False floors lifted in Surface BAs
Below is a table showing the dates that EL will be pulling cables at each point of the SPS. During these periods large sections of the false floor in these surface buildings will be lifted. Any works in the BA’s that involve lifting of the false floors MUST be reported to the Coordination team BAs Cabling pulling start Cable pulling end BA1 (TS1- works) BA1 (Irradiated cable works) BA1 (Fibre Optics) 29/04/2013 08/10/2013 08/04/2013 02/08/2013 25/03/2014 24/04/2013 BA2 06/01/2014 28/04/2014 BA3 BA3 (Fibre Optics) 27/03/2013 22/04/2014 31/05/2013 20/05/2014 BA4 BA4 (Fibre Optics) 27/05/2013 07/10/2013 12/07/2013 25/10/2013 BA5 BA5 (Fibre Optics) 30/09/2013 24/05/3013 11/10/2013 BA6 BA6 (Fibre Optics) 13/09/2013 13/5/2013 08/11/2013 24/05/2013 BA7 14/10/2013 07/11/2013 If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first.

27 Engineering Change Requests
Any and all new equipment being installed in the SPS requires an ECR BEFORE it can be installed. It must also be approved by planning and coordination. Templates and Guidelines for Engineering Change Requests: EDMS: SPS ECR template (in DFS):

28 Current ECR’s for LS1 Removal of AEWB Pick-up from position to 31502 (EDMS No ) UNDER IMPLEMENTATION Removal of a BPWA Pick-up from position to 31101 (EDMS No ) UNDER IMPLEMENTATION Installation of a new Wideband Kickers system in position 32173 (EDMS No ) RELEASED Installation of a new HBW Damper Pick-up in place of BPWA & AEWB 31932 (EDMS No ) RELEASED Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2 (EDMS No ) RELEASED Reinstallation of pump and gauges (Pirani + Penning) in (vacuum sector 150) (EDMS No ) RELEASED Modification LSS1 sectorization (new VVSF + displacement VVSB 11772) (EDMS No v.2) RELEASED Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS. (EDMS No ) UNDER IMPLEMENTATION

29 Current ECR’s for LS1 Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5. (EDMS No ) RELEASED SPS Beam Position Monitoring Prototyping Setup in LSS4. (EDMS No ) RELEASED Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper. (EDMS No ) RELEASED Installation d'un nouveau moniteur de position de type BPCR en LSS2 au (EDMS No ) RELEASED Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel. (EDMS No ) UNDER IMPLEMENTATION Interlocking of Injection Tunnel upstream areas with LHC powering. (EDMS No ) RELEASED Move of BPH to BPH (EDMS No ) RELEASED Optical Fibre Racks. (EDMS No ) UNDER IMPLEMENTATION

30 Current ECR’s for LS1 Removal of old fixed TMP vacuum groups in (EDMS No ) RELEASED BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS). (EDMS No ) UNDER IMPLEMENTATION Installation de Coffrets d'Alimentation en LSS1 et TT10. (EDMS No ) UNDER IMPLEMENTATION Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement. (EDMS No ) UNDER IMPLEMENTATION Installation de nouveaux chemins de câbles en LSS1+ du SPS. (EDMS No v.2) RELEASED TPSN replacement in LSS2 of SPS. (EDMS No v.1) UNDER IMPLEMENTATION Replacement of pumps in 3 tanks MKP in LSS1 of the SPS . (EDMS No v. 0.1) RELEASED Suppression of VVFA in LSS1 of SPS. (EDMS No v. 0.1) RELEASED

31 Current ECR’s for LS1 New shielding wall behind TIDV in SPS . (EDMS No v. 0.1) RELEASED Modification of Numbering of SPS Civil Works. (EDMS No v. 0.1) RELEASED New Cable Tray in LSS5- of SPS. (EDMS No v. 0.1) UNDER IMPLEMENTATION Helium 2K Pumping Units Installation in the Alcove Region of SPS Point 4 (BA4). (EDMS No v. 1.0) UNDER IMPLEMENTATION Installation of a wire scanner BWSRE in LSS5 of the SPS. (EDMS No v. 0.1) UNDER APPROVAL Increase of the MDHD steering strength for the LIU-SPS Q20 optics. (EDMS No v. 0.1) UNDER APPROVAL Modification of 2 Shielding Towers in LSS5 of the SPS. (EDMS No v. 0.1) RELEASED Upgrade of the UA9 equipment during LS1. (EDMS No v. 0.1) UNDER APPROVAL Removal of a BCT in TT10 during LS1. (EDMS No v. 0.1) RELEASED

32 Access rights and safety equipment
Everyone who enters the SPS MUST have the following: Completed the correct courses. (sir.cern.ch) Safety course levels 1, 2 and 3. or CERN Safety Introduction Safety during LS1 Habilitation Electrique. Electrical Safety Awareness Radiological Protection. (RP Training for CERN Supervised Radiation Areas) Self Rescue Mask Training. The correct access authorisation (via EDH). Zone Code “SPS” for access into the SPS Zone Code “NA_TARG” for access into BA80 Zone Code “CNGS” for access into the CNGS areas Zone Code “SPS-KN-000” for “Autorisation conduite RTL” Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. All contractors must all have a company passive dosimetre!!! Helmet plus Light. Please note that personnel are not allowed to work in the tunnel alone!!

33 Important information
Useful Contact Numbers SPS Coordination Team David MCFARLANE Franck BAIS – James RIDEWOOD Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Elodie Aubert Kurt Weiss (BA1) Coordination Safety Emmanuel Paulat – John Etheridge

34 A.O.B. Please make sure you fill out your IMPACTS correctly!!!! And in plenty of time!!!!!! The intervention period is “LS1-SPS” Do not put “OPERATION 2013” or leave it blank as no one will sign it. With the exception of BA80, no IMPACT should have an end date after the 27th June 2014 Do not just put SPS for you location. Be more specific! There are currently 51 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT. If you have ANY concerns about not being complete before the 27th June I need to know about it NOW!!!! Its very important to ensure that you leave the work site clean and tidy and that you put any rubbish in the correct bins.

35 SPS coordination website
\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1 Next meeting 30/04/2014 112-R-028 14:00 Hrs