1 Local Transmission Planning Process: Local Transmission Plan Update Meeting
December 15, 2016

2 Single System Projects
Agenda Planning Cycle Website Single System Projects Next Steps

3 Planning Cycle Study Development Meeting
Planning assumptions, data gathering Customer input July 14, 2015 Review of Study Results/Draft Transmission Plans Meeting Review results of the study process Draft Local Planning Report December 15, 2015 Local Transmission Plan Update Meeting Provide an update to the Local Planning Report Q3 Q4, 2016

4 Attachment K Website…

5 Avista Areas

6 Single System Projects and Corrective Action Plans
Any project Avista wants to construct Needed for load growth, asset management, reliability Corrective Action Plans Subset of Single System Projects Required to meet reliability performance criteria Developed to comply with NERC Standards “Applicable Facility Ratings shall not be exceeded” Project List Only Corrective Action Plans presented Refer to complete list in the 2016 Local Planning Report Update

7 2016 Projects Completed Corrective Action Plans Single System Projects
None Single System Projects Clearwater Station Upgrade Harrington Station Rebuild Pine Creek Transformer Replacement

8 General System Diagnosis
Single points of failure cause issues Tie breakers and double circuits 230/115 kV transformation capacity Spokane area is deficient Lack solid spare procedure Long, small conductor transmission lines Small thermal capacity and high resistance Infrastructure is aging

9 Big Bend Area Year Problem Starts Construction Start Construction End
Priority Cost Estimate 1-Completed Stratford 115 kV Station Rebuild 0.0100 2-Committed Benton - Othello SS 115 kV Transmission Line Rebuild Present 2015 2017 $7,100,000 Saddle Mountain Integration 2019 $16,000,000 Addy - Devils Gap 115 kV Transmission Line Reconductor at Ford Station 2018 $2,025,000 3-Planned Addy - Kettle Falls Protection Scheme $1,000,000 Chelan - Stratford 115 kV Transmission Line Rebuild $13,000,000 Saddle Mountain Integration Phase 2 $10,500,000

10 Coeur d’Alene Area Year Problem Starts Construction Start
Construction End Priority Cost Estimate 1-Completed Lancaster Interconnection 0.0100 Pine Creek Transformer Replacement 2-Committed Cabinet – Bronx – Sand Creek 115 kV Transmission Line Rebuild Present 2015 2017 $7,000,000 Coeur d’Alene – Pine Creek 115 kV Transmission Line Rebuild 2019 $15,025,000 3-Planned St. Maries Cap Bank 5.3125 $500,000 4-Conceptual Sandpoint Reinforcement $20,000,000

11 Lewiston/Clarkston Area
Year Problem Starts Construction Start Construction End Priority Cost Estimate 2-Committed North Lewiston Reactors Present 2015 2016 $5,000,000 South Lewiston Station Rebuild 2030 2017 2019 0.4464 $1,400,000 3-Planned Lolo Transformer Replacement 0.8750 $4,000,000 4-Conceptual Hatwai - Lolo #2 230 KV Transmission Line $8,025,000

12 Palouse Area Year Problem Starts Construction Start Construction End
Priority Cost Estimate 1-Completed Moscow 230 Station Rebuild 0.0100 4-Conceptual Palouse Area Transformation Outage Project Present $2,500,000

13 Spokane Area Year Problem Starts Construction Start Construction End
Priority Cost Estimate 2-Committed Spokane Valley Transmission Reinforcement Present 2015 2018 $8,500,000 Westside Transformer Replacement 2017 $4,500,000 Garden Springs 230 kV Station Integration Phase 1 2020 $10,025,000 Ninth & Central - Sunset 115 kV T-Line Copper Replacement $3,500,000 3-Planned Nine Mile - Westside Protection Upgrade $200,000 Ninth & Central 230 kV Integration $15,000,000 Garden Springs 230 kV Station Integration Phase 2 Westside Transformer Replacement Phase 2 5-New Proposal Indian Trail - Waikiki 115 kV Transmission Line 2026 0.2750 $12,000,000

14 Finalize 2016 Local Planning Report
Next Steps Finalize 2016 Local Planning Report Incorporate comments Minor editing Refine Conduct new studies in 2017 Improve project documentation Collaborate with internal/external stakeholders