GLADSTONE 1800mm Steel culvert rehabilitation
2
Callemondah 4680 QLD
3
History of the project Rainfall January 2011
4
Flooding 2011
5
Problems
6
Idea Repair the ground Repair the pipe Trenchless
7
Proposed Solution Tender Engineer and prove methodology
Rehabilitate the ground Rehabilitate the culvert Minimal disruption to public and rate payers Culvert remain in service. No excavation Needed to achieve equivalent to class 2 RC for Load requirements.
8
Newcastle University Composite only 150MPa 26.5kN/m
3. Finite Element Predictions The Table below shows the results of the finite element analysis work. Pipe Configuration Limiting Stress (MPa) Uniformly Distributed Load kN/m) Composite only 150MPa 26.5kN/m Composite only with support 150MPa 112kN/m Composite and steel 350MPa in the steel 30kN/m Composite and steel with support 350MPa in the steel 128kN/m
9
Uretek Injection Ground Engineering
Mainmark have injecting Urethane for 25yrs Used to fill voiding and stabilise the ground the ground and foundation of the culvert.
10
ENCAP6™ Advanced Structural Relining Technologies
Product Features Exceptional abrasion resistance Excellent chemical resistance High compressive strength Long-life hydrolytic stability Compliments our existing suite of advanced engineering solutions A liner that chemically and mechanically bonds with concrete and steel. Sprayable
11
ENCAP6™ Physical Properties
Properties at 25°C Method Units Encap6 with laminate Encap6 without laminate Flexural Strength ASTM D790 MPa 280 135 Flexural Modulus GPa 14 6 Flexural Break % 4.5 Tensile Strength ASTM D638 150 67 Tensile Modulus 6.2 Density ASTM D792 g/ml 1.6 1.3 Viscosity ASTM D2196 cP 4,000 6,000 Thix Index n/a 5.0 5.6 Glass Content Formula 50 12.5 Styrene Content 45% Barcol Hardness, Ultimate (GYZJ-935 scale) ASTM D2583 60 38 HDT ASTM D648 °C 105
12
Challengers Cleaning Rain Hot weather with resin Bypass pumping
13
Job Done Job completed on time and Budget
14
2013 Gladstone received 1100mm in 3x days
15
Take home message Don’t just reline the internal surface
Treat, Repair and Fill the foundation